This clause is valid for

Manifold
As per contract Cl. no 7.09.05 power cycle piping
connections shall
of Section IV, Vol 5B(TG), whereas this system is Please clarify whether the manifold connections will be above
hotwell high-high level. be above high high
NRVS are required for HP part of steam turbine
drains. Please clarify(typ.). water level.
integral piping and hence
not applicable.
Please clarify whether angled Straight
connections will be provided. connections shall
be provided.