Activity ID Activity Name Original Duration Remaining Schedule % Start Finish Total Float Qtr 4, 2018
Duration Complete
Oct Nov
NEWPROJ Milling & Overlay at Al Khair 19
Road 19 0% 08-Oct-18 01-Nov-18 0 01-Nov-18, NEWPROJ Milling & O
Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities