NEWPROJ Milling & Overlay at Al Khair 19
Road 19 0% 08-Oct-18 01-Nov-18 0 01-Nov-18, NEWPROJ Milling & O

NEWPROJ.1 PRELIMINARIES 14 14 0% 08-Oct-18 25-Oct-18 5 25-Oct-18, NEWPROJ.1 PRELIMINARIES


A1000 START MILESTONE 0 0 0% 08-Oct-18 19 START MILESTONE, 08-Oct-18
A1010 FINISH MILESTONE 0 0 0% 08-Oct-18 19 FINISH MILESTONE,
A1030 NOCAPPROVALS 5 5 0% 08-Oct-18 12-Oct-18 14 NOCAPPROVALS
A1040 DETOURAPPROVALS 14 14 0% 08-Oct-18 25-Oct-18 0 DETOURAPPROVALS
NEWPROJ.2 CONSTRUCTION 5 5 0% 26-Oct-18 01-Nov-18 0 01-Nov-18, NEWPROJ.2 CONSTR
A1020 MILLING 5 5 0% 26-Oct-18 01-Nov-18 0 MILLING
A1050 ASPHALT LAYING 5 5 0% 26-Oct-18 01-Nov-18 0 ASPHALT LAYING
A1060 ROAD FURNITURE WORKS 5 5 0% 26-Oct-18 01-Nov-18 0 ROAD FURNITURE WORKS
NEWPROJ.3 HANDOVER 5 5 0% 08-Oct-18 12-Oct-18 14 12-Oct-18, NEWPROJ.3 HANDOVER
A1070 HANDOVER 5 5 0% 08-Oct-18 12-Oct-18 14 HANDOVER