REKAP HARGA SATUAN S.N.

HARGA HARGA TOTAL


NO. URAIAN
MATRIAL UPAH harga
A B G=(CXE) H = (C X E ) I=(G+H)

PEKERJAAN PERSIAPAN
A 001 1 M2 PEMBERSIHAN LAPANGAN - 5,000 5,000
A 002 1 M' PEK. PENGUKURAN (SITE) & PEMASANGAN BOWPLANK 29,780 13,000 42,780
A 003 1 M2 PEMBUATAN DIREKSI KEET / GUDANG SEMEN DAN ALAT - ALAT 718,720 310,000 1,028,720
A 004 1 M3 BONGKARAN BETON BERTULANG + PEMBERSIHAN - 333,350 333,350
A 005 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH + PEMBERSIHAN - 250,013 250,013

PEKERJAAN TANAH

B 001 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 1 M' - 20,000 20,000
B 002 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 2 M' - 26,250 26,250
B 003 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 3 M' - 36,750 36,750
B 004 1 M3 PEK. GALIAN TANAH KERAS MAX KEDALAMAN 1 M' - 31,250 31,250
B 005 1 M3 PEK. GALIAN TANAH CADAS MAX KEDALAMAN 1 M' - 62,500 62,500
B 006 1 M3 PEK. GALIAN TANAH LUMPUR MAX KEDALAMAN 1 M' - 41,150 41,150
B 007 1 M² PEK. STRIPPING 1 M - 2,500 2,500
B 008 1 M³ PEMBUANGAN TANAH SEJAUH 150 M - 9,600 9,600
B 009 1 M3 URUGAN TANAH KEMBALI - 9,600 9,600
B 010 1 M2 PEMBUATAN JALAN (TEBARAN SIRTU), TEBAL 20 CM 33,310 18,750 52,060
B 011 1 M3 PEMADATAN TANAH - 25,000 25,000
B 012 1 M3 PEK. URUGAN PASIR 90,000 15,000 105,000

PEKERJAAN PASANGAN PONDASI

C 001 1 M3 PASANGAN BATU KALI KOSONG/AANSTAMPING 270,660 70,200 340,860


C 002 1 M3 PASANGAN BATU KALI 1 PC : 3PS 604,092 132,000 736,092
C 003 1 M3 PASANGAN BATU KALI 1 PC : 5 PS 526,036 132,000 658,036
C 004 1 M3 PASANGAN BATU KALI 1 PC : 6 PS 505,734 132,000 637,734
C 005 1 M3 PASANGAN PONDASI BATAKO 1PC : 3 PS 431,520 295,000 726,520

PEKERJAAN BETON

D 006 1 M2 MEMBUAT BETON RABAT 1 PC : 3 PS : 5 KR, TEBAL 10 CM 59,048 17,938 76,986


D 007 1 M3 MEMBUAT BETON RABAT 1 PC : 3 PS : 5 KR 590,480 102,500 692,980
D 008 1 M3 MEMBUAT BETON RABAT 1 PC : 4 PS : 6 KR 538,180 102,500 640,680
D 009 1 M3 MEMBUAT BETON COR 1 Pc : 2 Ps : 3 Kr 592,080 102,500 694,580
D 010 1 KG PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR 12,915 910 13,825
D 011 1 M2 PASANG BEKISTING 6,800 41,400 48,200
D 012 1 BUAH PONDASI FOOT PLAT 1 PC : 2 PS : 3 KR ( 0,6 X 0,6 X 0,2 M), SPASI TUL = 15 CM 85,765 234,120 319,885
D 013 1 M' MEMBUAT SLOOF 15/20 ( 116 KG + BEKISTING ), TUL 4 D10; SENGKANG D8 - 15 CM 623,476 15,219 638,695
D 014 1 M' MEMBUAT KOLOM 15/20 ( 143 KG + BEKISTING ), TUL 4 D12; SENGKANG D8 - 15 CM 788,209 24,750 812,959
D 015 1 M' MEMBUAT KOLOM 20/20 ( 110 KG + BEKISTING ), TUL 4 D12; SENGKANG D8 - 15 CM 805,345 26,480 831,825
D 016 1 M3 MEMBUAT KOLOM PRAKTIS 12/12 ( 200 KG + BEKISTING ), TUL 4 D10; SENGKANG D8 - 15 CM 612,381 9,014 621,395
D 017 1 M' MEMBUAT RING BALOK 12/15, TUL 4 D10; SENGKANG D8 - 15 CM 614,445 9,265 623,709
D 018 1 M' MEMBUAT BALOK GEVEL 12/15, TUL 4 D10; SENGKANG D8 - 15 CM 614,373 9,265 623,637
D 019 1 M' MEMBUAT BALOK STRUKTUR 15/25, TUL 4 D12; SENGKANG D8 - 15 CM 843,034 36,680 879,714
D 020 1 M3 MEMBUAT PLAT BETON BERTULANG ( 200 KG + BEKISTING ), SPASI TUL = 12 CM 15,223,480 604,000 15,827,480
D 021 1 M3 MEMBUAT PLAT CANOPY 8 CM( 130 KG + BEKISTING ) 10,390,765 604,000 10,994,765

PEKERJAAN DINDING

E 001 1 M2 PASANGAN BATA MERAH 1PC : 3PS 1/2 BATA 72,678 24,000 96,678
E 002 1 M2 PASANGAN BATA MERAH 1PC : 5PS 1/2 BATA 67,182 24,000 91,182
E 003 1 M2 PASANGAN BATAKO 1PC : 5 PS 1/2 BATA 47,352 29,500 76,852
E 004 1 M2 PASANGAN ROSTER TERAWANG 387,550 55,500 443,050

PEKERJAAN PELESTERAN

F 001 1 M2 ACIAN BETON 4,550 14,400 18,950


F 002 1 M2 ACIAN DINDING 2,583 14,400 16,983
F 003 1 M2 PLESTERAN DINDING 1 PC : 3 PS, TEBAL 15 MM 16,450 27,000 43,450
F 004 1 M2 PLESTERAN 1 PC : 5 PS, TEBAL 15 MM 13,250 27,000 40,250
F 005 1 M2 PLESTERAN BETON & DINDING 1PC : 6 PS TEBAL 15 CM 11,746 27,000 38,746
F 006 1 M2 PELESTERAN SKONING LEBAR 10 CM 1PC : 2PS 9,782 36,000 45,782
F 007 1 M2 PELESTERAN CIPRAT/KAMPROTAN 1 PC : 2 PS 9,472 20,500 29,972
F 008 1 M2 SIAR PASANGAN BATU 1 PC : 2 PS 11,444 27,000 38,444

PEKERJAAN RANGKA ATAP

G 001 1 KG PASANG RANGKA ATAP BAJA 14,520 5,100 19,620


G 002 1M3 PASANG KONSTRUKSI KUDA - KUDA KAYU KLAS II 3,887,800 1,160,000 5,047,800
G 003 1M² PASANG KASO + RENG ATAP GENTENG 50,473 13,000 63,473
G 004 1M² PASANG KASO + RENG ATAP SIRAP KAYU BORNEO 57,478 15,600 73,078
G 005 1M' PASANG PAPAN RUITER 3 / 20 CM 26,760 21,000 47,760
G 006 1M' PASANG LISPLANK 3/20 CM 26,760 21,000 47,760
G 007 1M' PASANG LISPLANK 2 X 3/20 CM 52,975 27,500 80,475
G 008 1M' PASANG LISPLANK 2/20 CM 18,540 21,000 39,540
G 009 1M' PASANG LISPLANK 2 X 2/20 CM 35,580 13,000 48,580
G 010 1 M' PASANG TALANG DATAR KARET 13,380 39,500 52,880
G 011 1 M' PASANG TALANG SENG ½ LINGKARAN 85,600 27,500 113,100

PEKERJAAN PENTUP ATAP


H 001 1M² PASANG ATAP GENTENG PALENTONG KECIL 30,000 13,500 43,500
H 002 1M' PASANG BUBUNG GENTENG PALENTONG 35,548 36,000 71,548
H 003 1 M2 PASANG ATAP SENG GELOMBANG (240 X 80 CM) 39,980 13,000 52,980
H 004 1M2 PASANG ATAP SENG GELOMBANG (180 X 80 CM ) 39,450 13,000 52,450
H 005 1 M' PASANG NOK SENG PLAT 11,410 6,350 17,760
H 006 1 M2 PASANG ATAP GENTENG PRES BETON 82,500 13,900 96,400
H 007 1M' PASANG NOK GENTENG PRES BETON 63,968 36,000 99,968
H 008 1 M2 PASANG ATAP GENTENG METAL 78,200 13,900 92,100
H 009 1 M' PASANG NOK GENTENG METAL 51,205 24,500 75,705
H 010 1 M2 PASANG ATAP SIRAP 60,400 28,300 88,700
H 011 1 M' PASANG NOK SIRAP 43,750 26,250 70,000
H 012 1 M2 PASANG ROOFLIGHT FIBERGLASS ( 180 X 80 ) CM 72,600 12,360 84,960
H 013 1M2 PASANG ATAP SENG GELOMBANG (180 X 80 CM ) 53,050 13,000 66,050
H 014 1 M' PASANG NOK ASBES GELOMBANG 0,8 M 45,090 14,200 59,290

PEKERJAAN LANGIT - LANGIT

I 001 1 M2 RANGKA LANGIT - LANGIT 60 X 120 CM (RANGKA SAJA) 33,840 25,500 59,340
I 002 1 M2 RANGKA LANGIT - LANGIT 30 X 60 CM (RANGKA SAJA) 76,800 29,375 106,175
I 003 1 M2 LANGIT - LANGIT PLYWOOD + RANGKA KAYU ( 60 X 120 ) CM 57,838 45,500 103,338
I 004 1 M2 LANGIT-LANGIT PLYWOOD + RANGKA KAYU ( 30 X 60 ) CM 106,448 34,000 140,448
I 005 1 M2 LANGIT - LANGIT GYPSUM + RANGKA KAYU 60 X 120 CM 75,656 34,500 110,156
I 006 1 M2 LANGIT - LANGIT AKUSTIK + RANGKA ALLUMINIUM 60 X 120 CM 379,885 47,500 427,385
I 007 1 M' LIST LANGIT - LANGIT KAYU PROFIL 4,010 3,530 7,540
I 008 1 M2 RANGKA DINDING PEMISAH KAYU 94,600 43,500 138,100
I 009 1 M2 PASANG DINDING PEMISAH PLYWOOD RANGKAP + RANGKA KAYU 145,340 58,000 203,340

PEKERJAAN PINTU & JENDELA

J 001 1M3 PASANG KUSEN PINTU DAN JENDELA 3,943,000 1,900,000 5,843,000
J 001 - a 1 BUAH KUSEN PINTU P-1 (1 daun pintu & ventilasi) 217,715 113,954 331,670
J 001 - b 1 BUAH KUSEN PINTU P-2 (2 daun pintu & ventilasi) 285,705 150,822 436,527
J 001 - c 1 BUAH KUSEN PINTU P-3 (2 daun pintu tanpa ventilasi) 230,064 93,845 323,909
J 001 - d 1 BUAH KUSEN PINTU PJ-1 (2 daun pintu, 2 kaca matii) 416,934 194,393 611,327
J 001 - e 1 BUAH KUSEN PINTU PJ-2 (1 daun pintu, 2 jendela) 429,431 227,909 657,339
J 001 - f 1 BUAH KUSEN JENDELA J-1 (1 daun jendela) 161,673 83,790 245,463
J 002 1M2 PASANG PINTU TRIPLEKS 4 MM RANGKAP, RANGKA KAYU 139,290 190,000 329,290
J 003 1M2 PASANG PINTU TRIPLEKS LAPIS ALUMINIUM, RANGKA KAYU 137,290 171,000 308,290
J 004 1M2 PASANG PINTU PANEL 156,200 200,000 356,200
J 003 - a 1 BUAH PINTU PANEL 80 X 200 CM 373,500 240,000 613,500
J 003 - b 1 PASANG PINTU PANEL 80 X 200 CM 702,000 480,000 1,182,000
J 003 - c 1 BUAH PINTU TRIPLEKS 4 MM RANGKAP, RANGKA KAYU 388,864 228,000 616,864
J 003 - d 1 BUAH PINTU TRIPLEKS LAPIS ALUMINIUM, RANGKA KAYU 398,864 228,000 626,864
J 005 1M2 PASANG JALUSI 69,316 290,000 359,316
J 006 1M2 PASANG DAUN JENDELA KAYU + KACA 146,568 187,500 334,068
J 006 - a 1 BUAH DAUN JENDELA KAYU 60 X 100 CM + KACA 133,736 112,500 246,236
J 006 - b 1 BUAH DAUN JENDELA KAYU 60 X 180 CM + KACA 194,754 202,500 397,254
J 007 1 M2 PASANG KACA MATI 94,500 12,750 107,250
J 008 1 M2 PASANG PINTU / JENDELA BESI 500,000 84,500 584,500
J 009 1 M2 PASANG PINTU LIPAT HARMONIKA 900,000 175,000 1,075,000
J 010 1 M2 PASANG PINTU SUNCREEN ALLUMUNIUM 425,000 68,000 493,000
J 011 1 M2 PASANG ROLLING DOOR 350,000 180,000 530,000
J 012 1 M2 PASANG PINTU ALLUMUNIUM 450,000 136,500 586,500
J 013 1 M2 PASANG VENETIONS BLINDS 150,000 45,500 195,500
J 014 1 M2 PASANG KAWAT NYAMUK 56,230 13,000 69,230
J 015 1 M2 PASANG TERALI BESI 201,250 156,000 357,250
J 016 1 M2 PASANG JENDELA NAKO & TRALIS 11,861 14,135 25,996

PEKERJAAN PENUTUP LANTAI DAN DINDING

K 001 1 M2 PASANG LANTAI KERAMIK UKURAN 20 X 20 CM 89,170 41,300 130,470


K 002 1 M2 PASANG LANTAI KERAMIK UKURAN 30 X 30 CM 92,420 47,200 139,620
K 003 1 M2 PASANG LANTAI KERAMIK UKURAN 40 X 40 CM 92,420 47,200 139,620
K 004 1 M2 PASANG LANTAI KERAMIK TERALUX MARMER UKURAN 40 X 60 CM 108,170 47,200 155,370
K 005 1 M2 PASANG PLINT KERAMIK ARTISTIK UKURAN 10 X 30 CM 67,457 47,200 114,657
K 006 1 M2 PASANG LANTAI KARPET 53,375 22,100 75,475
K 007 1 M2 PASANG LANTAI PARQUET JATI 254,250 47,200 301,450
K 008 1 M2 PASANG DINDING PORSELEN 20 X 25 CM 79,122 47,200 126,322
K 009 1 M2 PASANG DINDING MARMER 104,066 59,000 163,066
K 010 1 M2 PASANG DINDING BATA KLINKER 5 X 5 X 24 CM 118,766 47,200 165,966
K 011 1 M2 PASANG DINDING BATU TEMPEL 312,690 47,200 359,890

PEKERJAAN PENGECATAN

L 001 1 M2 MENGIKIS / MENGEROK PERMUKAAN CAT TEMBOK LAMA 375 7,500 7,875
L 002 1 m2 Mendempul dan Menggosok Kayu 2,236 5,200 7,436
L 003 1 m2 Mengecatan Bidang Kayu Lama (1 lapis cat dasar, 1 lapis cat penutup) 20,750 3,448 24,198
L 004 1 M2 MENGECATAN KAYU BARU ( 1 LAPIS PLAMIR ), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP 31,000 4,220 35,220
L 005 1 M2 PELABURAN BIDANG KAYU DENGAN TEAK OIL 9,360 7,040 16,400
L 006 1 M2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER 2,275 6,280 8,555
L 007 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS 10,998 5,652 16,650
L 008 1 M2 PENGECATAN TEMBOK BARU ( 1 PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP ) 8,600 6,040 14,640
L 009 1 M2 CAT GENTENG (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) SECARA MANUAL 8,625 4,760 13,385
L 010 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI 1,685 6,600 8,285

PEKERJAAN BESI & PENGUNCI

M 001 1 BUAH PASANG KUNSI TANAM BIASA 100,000 8,500 108,500


M 002 1 BUAH PASANG ENGSEL PINTU 10,000 10,200 20,200
M 003 1 BUAH PASANG ENGSEL JENDELA 10,000 10,200 20,200
M 004 1 PASANG PASANG GRENDEL PINTU 10,000 5,950 15,950
M 005 1 BUAH PASANG GRENDEL JENDELA 5,000 5,950 10,950
M 006 1 PASANG PASANG KAIT ANGIN 30,000 5,950 35,950
M 007 1 BUAH PASANG DOOR CLOSER 25,000 5,950 30,950
M 008 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER 75,000 5,950 80,950
M 009 1 BUAH BEGEL 45,500 5,950 51,450
M 010 1 BUAH BAUT 4,500 5,950 10,450

PEKERJAAN SANITASI

N 001 1 BUAH KLOSET DUDUK / MONOBLOK 1,140,000 136,000 1,276,000


N 002 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN 85,540 119,000 204,540
N 003 MEMASANG 1 BUAH URINOIR 595,540 136,000 731,540
N 004 MEMASANG 1 BUAH BAK MANDI FIBERGLASS, VOLUME 0.30 M³ 324,500 119,000 443,500
N 005 1 BUAH MEMASANG BADKIP PORSELEN 1,080,000 136,000 1,216,000
N 006 1 BUAH BAK MANDI BATU BATA, VOLUME 0.30 M³ 501,500 540,000 1,041,500
N 007 1 BH FLOOR DRAIN 35,000 8,500 43,500
N 008 1 UNIT SEPTIKTANK 100 X 150 X 200 CM 1,502,618 387,456 1,890,074
N 009 1 M' MEMASANG PERESAPAN JENIS PIPA TANAM PVC 4" 238,707 14,000 252,707
N 010 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (40 X 40 ) CM, T = 50CM 516,880 108,840 625,720
N 011 1 BH BAK CUCI PIRING STAINLES STEEL 250,000 25,500 275,500
N 012 1 M' MEMASANG PIPA PVC 3" 29,250 4,950 34,200
N 013 1 BH KRAN Ø ¾" ATAU ½" 22,625 8,500 31,125

PEKERJAAN INSTALASI LISTRIK

O 001 1 TTK - INSTALASI LAMPU 101,450 38,620 140,070


O 002 1 BUAH SEKRING BOX (TANAPA GROUNDING LANGSUNG) 100,000 38,620 138,620
O 003 1 BUAH BOX PANEL 25 X 25 CM, 4 GRUP 317,600 43,300 360,900
O 004 1 BUAH LAMPU DOWN LIGHT 169,000 38,620 207,620
O 005 1 BUAH SAKLAR TUNGGAL 49,500 38,620 88,120
O 006 1 BUAH SAKLAR DOUBLE 55,500 38,620 94,120
O 007 1 BUAH STOP KONTAK 50,500 38,620 89,120

PEKERJAAN TAMBAHAN

P 001 1 M' PAGAR KAWAT DURI TINGGI 1.8 M 61,690 39,000 100,690
P 002 1 M2 MENGERJAKAN RABAT KELILING (1 PC : 3 PS ; 5 KR), T=7CM, L=80CM 192,479 19,340 211,819
P 003 1 M' MENGERJAKAN SALURAN SAMPING 149,525 149,525
P 004 1 M2 MEMASANG PAVING BLOCK 80,250 24,000 104,250
ANALISA HARGA SATUAN S.N.I

HARGA HARGA TOTAL


NO. URAIAN KOEF SAT HARGA SAT
MATRIAL UPAH harga
A B C D E G=(CXE) H = (C X E ) I=(G+H)

PEKERJAAN TANAH

B 001 1 M3 PEK. GALIAN TANAH BIASA MAX KEDALAMAN 1 M'


Tenaga
Perkerja 0.400 Oh 50,000 20,000
Mandor 0.040 Oh - -
20,000 20,000
B 012 1 M3 PEK. URUGAN PASIR
Bahan
Pasir Urug 1.200 m3 75,000 90,000
Tenaga
Perkerja 0.300 Oh 50,000 15,000
Mandor 0.010 Oh - -
90,000 15,000 105,000

PEKERJAAN PASANGAN PONDASI

C 001 1 M3 PASANGAN BATU KALI KOSONG/AANSTAMPING


Bahan
Batu Belah 15 / 20 1.100 m3 216,600 238,260
Pasir Urug 0.432 m3 75,000 32,400
Tenaga
Perkerja 0.780 Oh 50,000 39,000
Tukang Batu 0.390 Oh 80,000 31,200
Kepala Tukang 0.039 Oh - -
Mandor 0.020 Oh - -
270,660 70,200 340,860
C 003 1 M3 PASANGAN BATU KALI 1 PC : 5 PS
Bahan
Batu Belah 15 / 20 1.100 m3 216,600 238,260
Semen Portland 2.448 sak 70,000 171,360
Pasir Pasang 0.544 m3 214,000 116,416
Tenaga
Perkerja 1.200 Oh 50,000 60,000
Tukang Batu 0.600 Oh 80,000 48,000
Kepala Tukang 0.060 Oh - -
Mandor 0.075 Oh - -
526,036 108,000 634,036

PEKERJAAN BETON

59,048 17,938 76,986


D 002 1 M3 MEMBUAT BETON RABAT 1 PC : 3 PS : 5 KR
Bahan
Semen Portland 4.360 sak 70,000 305,200
Pasir Beton 0.520 m3 214,000 111,280
Koral Beton 0.870 m3 200,000 174,000
Tenaga
Perkerja 1.650 Oh 50,000 82,500
Tukang Batu 0.250 Oh 80,000 20,000
Kepala Tukang 0.015 Oh - -
Mandor 0.018 Oh - -
590,480 102,500 692,980
D 004 1 M3 MEMBUAT BETON COR 1 Pc : 2 Ps : 3 Kr
Bahan
Semen Portland 6.640 sak 70,000 464,800
Pasir Beton 0.520 m3 214,000 111,280
Koral Beton 0.780 m3 200,000 156,000
Tenaga
Perkerja 1.650 Oh 50,000 82,500
Tukang Batu 0.250 Oh 80,000 20,000
Kepala Tukang 0.015 Oh - -
Mandor 0.018 Oh - -
732,080 102,500 834,580
D 005 1 KG PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR
Bahan
Besi Beton ( Polos / Ulir ) 1.050 Kg 12,000 12,600
Kawat Beton 0.015 Kg 21,000 315
Tenaga
Perkerja 0.007 Oh 50,000 350
Tukang Besi 0.007 Oh 80,000 560
Kepala Tukang 0.0007 Oh - -
Mandor 0.0003 Oh - -
12,915 910 13,825
D 006 1 M2 PASANG BEKISTING
Bahan
Papan begisting kls III 0.022 m3 2,000,000 44,000
Kayu kaso kls III 0.038 m3 1,900,000 72,960
Paku Biasa 2" - 5" 0.400 Kg 17,000 6,800
Tenaga
Perkerja 0.300 Oh 50,000 15,000
Tukang Kayu 0.330 Oh 80,000 26,400
Kepala Tukang 0.0330 Oh - -
Mandor 0.0060 Oh - -
6,800 41,400 48,200
D 007 1 M3 MEMBUAT BETON BERTULANG ( 200 KG + BEKISTING )
Bahan
Kayu kls III 0.320 m3 2,000,000 640,000
Paku Biasa 2" - 5" 3.200 Kg 17,000 54,400
Besi Beton 210.000 kg 12,000 2,520,000
Kawat Beton 3.000 Kg 21,000 63,000
Semen Portland 6.720 sak 70,000 470,400
Pasir Beton 0.540 m3 214,000 115,560
Koral Beton 0.810 m3 200,000 162,000
Tenaga
Perkerja 6.350 Oh 50,000 317,500
Tukang Batu 0.275 Oh 80,000 132,000
Tukang Kayu 1.650 Oh 80,000 22,000
Tukang Besi 1.400 Oh 80,000 112,000
Kepala Tukang 0.333 Oh - -
Mandor 0.316 Oh - -
4,025,360 583,500 4,608,860

PEKERJAAN DINDING

E 002 1 M2 PASANGAN BATA MERAH 1PC : 5PS 1/2 BATA


Bahan
Bata merah kelas I 80.000 bh 550 44,000
Semen Portland 0.194 sak 70,000 13,552
Pasir Pasang 0.045 m3 214,000 9,630
Tenaga
Perkerja 0.320 Oh 50,000 16,000
Tukang Batu 0.100 Oh 80,000 8,000
Kepala Tukang 0.010 Oh - -
Mandor 0.002 Oh - -
67,182 24,000 91,182
E 003 1 M2 PASANGAN BATAKO 1PC : 5 PS 1/2 BATA
Bahan
Batako 14.500 bh 2,000 29,000
Semen 0.125 sak 70,000 8,722
Pasir pasang 0.045 m3 214,000 9,630
Tenaga
Pekerja 0.350 Oh 50,000 17,500
Tukang batu 0.150 Oh 80,000 12,000
Kep Tukang 0.015 Oh - -
Mandor 0.002 Oh - -
47,352 29,500 76,852
E 004 1 M2 PASANGAN ROSTER TERAWANG
Bahan
Roster 36.000 bh 10,000 360,000
Semen 0.256 sak 70,000 17,920
Pasir pasang 0.045 m3 214,000 9,630
Tenaga
Pekerja 0.300 Oh 50,000 15,000
Tukang batu 0.100 Oh 80,000 8,000
Kep Tukang 0.010 Oh - -
Mandor 0.015 Oh - -
387,550 23,000 410,550

PEKERJAAN PELESTERAN

F 001 1 M2 ACIAN BETON


Bahan
Semen Portland 0.0650 sak 70,000 4,550
Tenaga
Perkerja 0.0800 org 50,000 4,000
Tukang Batu 0.0960 org 80,000 7,680
Kepala Tukang 0.0080 org - -
Mandor 0.0080 org - -
4,550 11,680 16,230
F 002 1 M2 ACIAN DINDING
Bahan
Semen Portland 0.0110 sak 70,000 770
Mild Stone 0.2550 sak 12,500 3,188
Tenaga
Perkerja 0.0800 org 50,000 4,000
Tukang Batu 0.0960 org 80,000 7,680
Kepala Tukang 0.0080 org - -
Mandor 0.0080 org - -
3,958 11,680 15,638
F 003 1 M2 PLESTERAN BETON 1 PC : 3 PS, TEBAL 15 MM
Bahan
Semen Portland 0.1414 sak 70,000 9,898
Pasir Pasang 0.0210 m3 214,000 4,494
Tenaga
Perkerja 0.2600 org 50,000 13,000
Tukang Batu 0.2000 org 80,000 16,000
Kepala Tukang 0.0200 org - -
Mandor 0.0130 org - -
14,392 29,000 43,392
F 004 1 M2 PLESTERAN 1 PC : 5 PS, TEBAL 15 MM
Bahan
Semen Portland 0.1037 sak 70,000 7,258
Pasir Pasang 0.0280 m3 214,000 5,992
Tenaga
Perkerja 0.2000 org 50,000 10,000
Tukang Batu 0.1500 org 80,000 12,000
Kepala Tukang 0.0150 org - -
Mandor 0.0100 org - -
13,250 22,000 35,250
F 005 1 M2 PLESTERAN BETON & DINDING 1PC : 6 PS TEBAL 15 CM
Bahan
Semen Portland 0.088 sak 70,000 6,182
Pasir Pasang 0.026 m3 214,000 5,564
Tenaga
Perkerja 0.2000 Oh 50,000 10,000
Tukang Batu 0.1500 Oh 80,000 12,000
Kepala Tukang 0.0150 Oh - -
Mandor 0.0100 Oh - -
11,746 22,000 33,746
F 006 1 M2 PELESTERAN SKONING LEBAR 10 CM 1PC : 2PS
Bahan
Semen Portland 0.100 sak 70,000 7,000
Pasir Pasang 0.013 m3 214,000 2,782
Tenaga
Perkerja 0.057 Oh 50,000 2,850
Tukang Batu 0.038 Oh 80,000 3,040
Kepala Tukang 0.038 Oh - -
Mandor 0.002 Oh - -
9,782 5,890 15,672
F 007 1 M2 PELESTERAN CIPRAT/KAMPROTAN 1 PC : 2 PS
Bahan
Semen Portland 0.086 sak 70,000 6,048
Pasir Pasang 0.016 m3 214,000 3,424
Tenaga
Perkerja 0.250 Oh 50,000 12,500
Tukang Batu 0.100 Oh 80,000 8,000
Kepala Tukang 0.010 Oh - -
Mandor 0.010 Oh - -
9,472 20,500 29,972
F 008 1 M2 SIAR PASANGAN BATU 1 PC : 2 PS
Bahan
Semen Portland 0.127 sak 70,000 8,876
Pasir Pasang 0.012 m3 214,000 2,568
Tenaga
Perkerja 0.300 Oh 50,000 15,000
Tukang Batu 0.150 Oh 80,000 12,000
Kepala Tukang 0.015 Oh - -
Mandor 0.010 Oh - -
11,444 27,000 38,444

PEKERJAAN RANGKA ATAP


G 002 1M3 PASANG KONSTRUKSI KUDA - KUDA KAYU KLAS II
Bahan
Balok Kayu Klas II 1.100 m3 3,500,000 3,850,000
Paku Biasa 2" - 5" 2.520 Kg 15,000 37,800
Tenaga
Perkerja 4.000 Oh 50,000 200,000
Tukang Kayu 12.000 Oh 80,000 960,000
Kepala Tukang 1.200 Oh - -
Mandor 0.200 Oh - -
3,887,800 1,160,000 5,047,800
G 003 1M² PASANG KASO + RENG ATAP GENTENG
Bahan
Usuk 5/7 Klas II 0.010 m3 3,500,000 33,688
Reng Klas II 0.004 m3 3,500,000 13,860
Paku Biasa 2" - 5" 0.195 Kg 15,000 2,925
Tenaga
Perkerja 0.100 Oh 50,000 5,000
Tukang Kayu 0.100 Oh 80,000 8,000
Kepala Tukang 0.010 Oh - -
Mandor 0.005 Oh - -
50,473 13,000 63,473
G 008 1M' PASANG LISPLANK 2/20 CM
Bahan
Papan Kayu 0.0048 m3 3,550,000 17,040
Paku Biasa 2" - 5" 0.100 Kg 15,000 1,500
Tenaga
Perkerja 0.100 Oh 50,000 5,000
Tukang Kayu 0.200 Oh 80,000 16,000
Kepala Tukang 0.025 Oh - -
Mandor 0.005 Oh - -
18,540 21,000 39,540
G 009 1M' PASANG LISPLANK 2 X 2/20 CM
Bahan
Papan Kayu 0.0096 m3 3,550,000 34,080
Paku Biasa 2" - 5" 0.100 Kg 15,000 1,500
Tenaga
Perkerja 0.150 Oh 50,000 7,500
Tukang Kayu 0.250 Oh 80,000 20,000
Kepala Tukang 0.025 Oh - -
Mandor 0.075 Oh - -
35,580 27,500 63,080

PEKERJAAN PENTUP ATAP

H 001 1M² PASANG ATAP GENTENG PALENTONG KECIL


Bahan
Genteng Palentong 25.000 bh 1,200 30,000
Tenaga
Perkerja 0.150 Oh 50,000 7,500
Tukang Kayu 0.075 Oh 80,000 6,000
Kepala Tukang 0.008 Oh - -
Mandor 0.005 Oh - -
30,000 13,500 43,500
H 002 1M' PASANG BUBUNG GENTENG PALENTONG
Bahan
Genteng Bubung Palentong 5.000 bh 3,500 17,500
Semen Portland 0.160 sak 70,000 11,200
Pasir Pasang 0.032 m3 214,000 6,848
Tenaga
Perkerja 0.400 Oh 50,000 20,000
Tukang Kayu 0.200 Oh 80,000 16,000
Kepala Tukang 0.020 Oh - -
Mandor 0.002 Oh - -
35,548 36,000 71,548
H 004 1M2 PASANG ATAP SENG GELOMBANG (180 X 80 CM )
Bahan
Asbes Gelombang 0.950 lbr 39,000 37,050
Paku Seng 0.100 Kg 24,000 2,400
Tenaga
Perkerja 0.140 Oh 50,000 7,000
Tukang Kayu 0.075 Oh 80,000 6,000
Kepala Tukang 0.008 Oh - -
Mandor 0.005 Oh - -
39,450 13,000 52,450
H 005 1 M' PASANG NOK SENG PLAT
Bahan
Seng Plat 50 cm 1.100 m' 9,500 10,450
Paku Seng 0.040 Kg 24,000 960
Tenaga
Perkerja 0.015 Oh 50,000 750
Tukang Kayu 0.070 Oh 80,000 5,600
Kepala Tukang 0.008 Oh - -
Mandor 0.005 Oh - -
11,410 6,350 17,760

PEKERJAAN LANGIT - LANGIT

I 003 1 M2 LANGIT - LANGIT PLYWOOD + RANGKA KAYU ( 60 X 120 ) CM


Kayu usuk 4/6 0.009 m3 3,500,000 32,340
Plywood 4 mm 0.365 lbr 65,000 23,698
Paku Biasa 2" - 5" 0.120 Kg 15,000 1,800
Tenaga
Perkerja 0.270 Oh 50,000 13,500
Tukang Kayu 0.400 Oh 80,000 32,000
Kepala Tukang 0.040 Oh - -
Mandor 0.0135 Oh - -
57,838 45,500 103,338
I 007 1 M' LIST LANGIT - LANGIT KAYU PROFIL
Bahan
List Kayu Profil 0.320 btng 12,000 3,840
Paku 0.010 Kg 17,000 170
Tenaga
Perkerja 0.021 Oh 50,000 1,050
Tukang Kayu 0.031 Oh 80,000 2,480
Kepala Tukang 0.015 Oh - -
Mandor 0.0015 Oh - -
4,010 3,530 7,540
I 007a 1 M' LIST LANGIT - LANGIT GYPSUM
Bahan
List gypsum 1.050 m 25,000 26,250
Lem Kayu 0.200 Kg 14,000 2,800
Tenaga
Perkerja 0.021 Oh 50,000 1,050
Tukang Kayu 0.031 Oh 80,000 2,480
Kepala Tukang 0.015 Oh - -
Mandor 0.0015 Oh - -
29,050 3,530 32,580

PEKERJAAN PINTU & JENDELA

J 001 1M3 PASANG KUSEN PINTU DAN JENDELA


Bahan
Balok Kayu 6/14 1.100 m3 3,500,000 3,850,000
Paku 6.200 kg 15,000 93,000
Tenaga
Perkerja 6.000 Oh 50,000 300,000
Tukang Kayu 20.000 Oh 80,000 1,600,000
Kepala Tukang 2.000 Oh - -
Mandor 0.300 Oh - -
3,943,000 1,900,000 5,843,000
J 003 - a 1 BUAH PINTU PANEL 80 X 200 CM
Bahan
Papan Kayu 4 cm 0.070 m3 3,550,000 248,500
Kunci Tanam 2 slag 1.000 bh 100,000 100,000
Engsel 1.000 psng 10,000 10,000
Grendel 2.000 bh 5,000 10,000
Tenaga
Perkerja 0.960 Oh 50,000 48,000
Tukang Kayu 2.400 Oh 80,000 192,000
Kepala Tukang 0.240 Oh - -
Mandor 0.048 Oh - -
368,500 240,000 608,500
J 003 - c 1 BUAH PINTU TRIPLEKS 4 MM RANGKAP, RANGKA KAYU
Bahan
Papan Kayu 4 cm 0.0314 m3 3,550,000 111,328
Paku Biasa ½" - 1" 0.048 Kg 17,000 816
Lem Kayu 0.480 Kg 14,000 6,720
Tripleks 4 mm 2.000 Lbr 65,000 130,000
Kunci Tanam 2 slag 1.000 bh 100,000 100,000
Engsel 2.000 psng 10,000 20,000
Grendel 2.000 bh 5,000 10,000
Tenaga
Perkerja 0.720 Oh 50,000 36,000
Tukang Kayu 2.400 Oh 80,000 192,000
Kepala Tukang 0.240 Oh - -
Mandor 0.036 Oh - -
378,864 228,000 606,864
J 006 1M2 PASANG DAUN JENDELA KAYU + KACA
Bahan
Papan Kayu 3,5 cm 0.020 m3 3,550,000 71,568
Kaca 3 mm 1.000 m2 75,000 75,000
Tenaga
Perkerja 0.750 Oh 50,000 37,500
Tukang Kayu 1.875 Oh 80,000 150,000
Kepala Tukang 0.188 Oh - -
Mandor 0.038 Oh - -
146,568 187,500 334,068
J 006 - a 1 BUAH DAUN JENDELA KAYU 60 X 100 CM + KACA
Bahan
Papan Kayu 3,5 cm 0.012 m3 3,550,000 43,736
Kaca 5 mm 0.500 m2 90,000 45,000
Engsel jendela 1.000 psng 10,000 10,000
Grendel jendela 1.000 bh 5,000 5,000
Haag angin kuningan 2.000 bh 15,000 30,000
Tenaga
Perkerja 0.450 Oh 50,000 22,500
Tukang Kayu 1.125 Oh 80,000 90,000
Kepala Tukang 0.113 Oh - -
Mandor 0.023 Oh - -
133,736 112,500 246,236
J 007 1 M2 PASANG KACA MATI
Bahan
Kaca 5 mm 1.050 m2 90,000 94,500
Tenaga
Perkerja 0.015 Oh 50,000 750
Tukang Kayu 0.150 Oh 80,000 12,000
Kepala Tukang 0.015 Oh - -
Mandor 0.001 Oh - -
94,500 12,750 107,250

PEKERJAAN PENUTUP LANTAI DAN DINDING

K 002 1 M2 PASANG LANTAI KERAMIK UKURAN 30 X 30 CM


Bahan
Keramik 30 x 30 cm 1.050 m2 50,000 52,500
Semen Portland 0.228 sak 70,000 15,932
Pasir Pasang 0.0420 m3 214,000 8,988
Semen Warna 0.7500 Kg 10,000 7,500
Tenaga
Perkerja 0.4340 Oh 50,000 21,700
Tukang Batu 0.245 Oh 80,000 19,600
Kepala Tukang 0.0245 Oh - -
Mandor 0.0225 Oh - -
84,920 41,300 126,220
K 008 1 M2 PASANG DINDING PORSELEN 20 X 25 CM
Bahan
Porselen 20 x 20 cm 1.050 m2 45,000 47,250
Semen Portland 0.186 sak 70,000 13,020
Pasir Pasang 0.018 m3 214,000 3,852
Semen Warna 0.7500 Kg 10,000 7,500
Tenaga
Perkerja 0.4800 Oh 50,000 24,000
Tukang Batu 0.360 Oh 80,000 28,800
Kepala Tukang 0.0360 Oh - -
Mandor 0.0240 Oh - -
71,622 52,800 124,422

PEKERJAAN PENGECATAN

L 004 1 M2 MENGECATAN KAYU BARU ( 1 LAPIS PLAMIR ), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
Bahan
Cat Meni 0.200 Kg 12,500 2,500
Dempul 0.150 Kg 24,000 3,600
Cat Dasar 0.170 Kg 55,000 9,350
Cat Kayu 0.260 Kg 55,000 14,300
Minyak Cat 0.100 Ltr 12,500 1,250
Tenaga
Perkerja 0.0700 Oh 50,000 3,500
Tukang Cat 0.009 Oh 80,000 720
Kepala Tukang 0.0060 Oh - -
Mandor 0.0025 Oh - -
31,000 4,220 35,220
L 008 1 M2 PENGECATAN TEMBOK BARU ( 1 PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP )
Bahan
Plamir 0.200 Kg 9,250 1,850
Cat Dasar 0.100 Kg 18,750 1,875
Cat Tembok 0.260 Kg 18,750 4,875
Tenaga
Perkerja 0.0200 Oh 50,000 1,000
Tukang Cat 0.063 Oh 80,000 5,040
Kepala Tukang 0.0063 Oh - -
Mandor 0.0025 Oh - -
8,600 6,040 14,640
PEKERJAAN BESI & PENGUNCI

M 001 1 BUAH PASANG KUNSI TANAM BIASA


Bahan
Kunsi Tanam Biasa 1.000 Bh 100,000 100,000
Tenaga
Perkerja 0.010 Oh 50,000 500
Tukang Kayu 0.100 Oh 80,000 8,000
Kepala Tukang 0.010 Oh - -
Mandor 0.005 Oh - -
100,000 8,500 108,500
M 002 1 BUAH PASANG ENGSEL PINTU
Bahan
Engsel Pintu 1.000 Psng 10,000 10,000
Tenaga
Perkerja 0.007 Oh 50,000 350
Tukang Kayu 0.070 Oh 80,000 5,600
Kepala Tukang 0.002 Oh - -
Mandor 0.001 Oh - -
10,000 5,950 15,950

PEKERJAAN SANITASI

N 008 1 UNIT SEPTIKTANK 100 X 150 X 200 CM


Bahan
bata merah 720.000 bh 550 396,000
semen 3.717 sak 70,000 260,207
pasir 0.417 m3 214,000 89,298
kerikil 0.206 m3 200,000 41,184
papan begisting 0.066 m3 2,000,000 132,000
kayu usuk 5/7 0.033 m3 1,900,000 62,178
besi dia 10 28.396 kg 12,000 340,752
Pipa GIP Ø 2" 2.000 M' 28,000 56,000
Pipa PVC Ø 4" 4.000 M' 31,250 125,000
Tenaga
pekerja 4.918 Oh 50,000 245,920
tukang batu 0.792 Oh 80,000 63,392
tukang kayu 0.607 Oh 80,000 48,576
tukang besi 0.370 Oh 80,000 29,568
kep tukang 0.177 Oh - -
mandor 0.278 Oh - -
1,502,618 387,456 1,890,074

PEKERJAAN INSTALASI LISTRIK

O 001 1 TTK - INSTALASI LAMPU


Bahan
Fiting keramik 125 watt 1.000 bh 7,150 7,150
NYM 2 x 2.5 mm2 10.000 m¹ 6,500 65,000
Klem 0.200 bh 1,500 300
Pipa Conduit PVC klas D 3.000 m¹ 1,000 3,000
Lampu SL 18 watt 1.000 bh 26,000 26,000
Tenaga
Pekerja 0.3714 Oh 50,000 18,570
Tukang listrik 0.1065 Oh 80,000 8,520
Pembantu instalator 0.2306 Oh 50,000 11,530
101,450 38,620 140,070
O 005 1 BUAH SAKLAR TUNGGAL
Bahan
Saklar Tunggal 1.000 bh 14,000 14,000
Kabel NYM 2x2,5mm2 5.000 m 6,500 32,500
Pipa Conduit PVC klas D 3.000 m¹ 1,000 3,000
Tenaga
Pekerja 0.3714 Oh 50,000 18,570
Tukang listrik 0.1065 Oh 80,000 8,520
Pembantu instalator 0.2306 Oh 50,000 11,530
49,500 38,620 88,120
PNPM MANDIRI PERDESAAN
TAHUN 2013

DAFTAR HARGA SATUAN UPAH DAN BAHAN


HARGA
NO. URAIAN SATUAN KET.
(Rp.)
DAFTAR HARGA SATUAN UPAH

1 Pekerja 50,000 hok


2 Tukang batu 80,000 hok
3 Tukang kayu 80,000 hok
4 Tukang besi 80,000 hok
5 Tukang las 80,000 hok
6 Tukang cat 80,000 hok
7 Tukang listrik 80,000 hok
8 Pembantu tukang listrik 50,000 hok
9 Kepala tukang 0 hok
10 Mandor 0 hok
11 Operator alat berat 250,000 hok
12 Supir 50,000 hok
13 Instalatir listrik 20,000 titik

DAFTAR HARGA SATUAN BAHAN

Material Alam
1 Tanah urug 62,500 m3
2 Pasir urug 75,000 m3
3 Pasir cor 214,000 m3
4 Sirtu alam 75,700 m3
5 Pasir pasang 214,000 m3
6 Kapur pasang 375,000 m3
7 Kerikil 2/3 (alam) 200,000 m3
8 Kerikil 2/3 (split) 250,000 m3
9 Batu spit 5/7 110,000 m3
10 Batu kali/belah 216,600 m3
11 Batu bata klas I 550 buah
12 Batako 2,000 buah

Bahan Pasangan

1 Semen (50 kg) 70,000 sak


2 Semen warna 10,000 kg
3 Mild stone 12,500 sak
4 Roster polos (15x25) 10,000 buah
5 Roster kembang 20,000 buah
6 Batu paras 275,000 m2
7 Bata Pelapis Klinker 1,200 buah
8 Paving block (press hidrolis) 1,500 buah
9 Buis beton 1/2 diameter 30 cm (P = 1 m) 47,500 buah
10 Buis beton bulat diameter 50 cm (P = 0,5 m) 75,000 buah
11 Buis beton 1/2 diameter 80 cm (P = 0,5 m) 90,000 buah

Bahan Kayu

1 Papan kayu klas I 5,500,000 m3


2 Papan kayu klas II 3,550,000 m3
3 Papan kayu klas III 2,000,000 m3
4 Balok kayu klas I 5,000,000 m3
5 Balok kayu klas II 3,500,000 m3
6 Balok kayu klas III 1,900,000 m3
7 Kayu Dolken o 10 cm (4 m) 30,000 btg
8 Triplek 122x242x3 mm 45,000 lbr
9 Triplek 122x242x4 mm 65,000 lbr
10 Triplek 122x242x9 mm 120,000 lbr
11 Triplek 122x242x4 mm lapis aluminium 75,000 lbr
12 Kalsiboard (120cmx240cmx6mm) 53,000 lbr
13 Gypsum 45,000 lbr
14 List gypsum 25,000 m'
15 List kayu profil (3x3x4) 12,000 btg
HARGA
NO. URAIAN SATUAN KET.
(Rp.)
Bahan Penutup atap
1 Rangka baja ringan 180,000 m2
2 Genteng metal 75,000 m2
3 Bubungan genteng metal 45,000 m'
4 Genteng pejaten lokal 1,200 buah
5 Bubungan genteng pejaten lokal 3,500 buah
6 Genteng beton lokal 1,300 buah
7 Bubungan genteng beton lokal 4,500 buah
8 Genteng beton pres klas tinggi 7,500 buah
9 Bubungan genteng beton pres klas tinggi 12,000 buah
10 Sirap 950 lbr
11 Roof Light Fiberglas (180 x 80 ) 75,000 lbr
12 Asbes gel (180 x 80) 16,000 lbr
13 Nog asbes 80 cm 18,000 lbr
14 Seng gel besar BJLS = 18 39,000 lbr L = 180 cm
15 Seng gel besar BJLS = 18 53,000 lbr L = 240 cm
16 Seng plat BJLS 18, L = 50 cm 9,500 m'
17 Talang karet 12,500 m'
18 Nog Steel 3"x 6" BJLS 28 25,000 m'
19 Talang PVC 8,000 m'
Bahan Besi

1 Besi beton 12,000 kg


2 Kawat Beton 21,000 kg
3 Besi beton dia 16 mm 150,000 lj
4 Besi beton dia 14 mm 134,000 lj
5 Besi Beton dia. 12 mm 105,000 lj
6 Besi Beton dia. 10 mm 70,000 lj
7 Besi Beton dia. 8 mm 40,000 lj
8 Besi Beton dia. 6 mm 22,500 lj
9 Paku (panjang 1-3 cm) 20,000 kg
10 Paku (panjang 4-6 cm) 17,000 kg
11 Paku (panjang 7-12 cm) 15,000 kg
12 Paku seng 24,000 kg
13 Paku sekrup 27,000 kg
14 Beugel U plat 32,000 buah
15 Beugel plat kopel 32,000 buah
16 Beugel U bulat (beugel ujung) 32,000 buah
17 Baut mur dia 12 ( 15 cm ) 4,500 buah
18 Baut mur dia 12 ( 25 cm ) 8,000 buah
19 Baut mur dia 12 ( 35 cm ) 9,000 buah
20 Angker kusen 1,000 buah
21 Besi siku L40.40.2 25,000 m'
Bahan Pengunci

1 Kunci pintu 2 slaag klas menengah 100,000 buah


2 Engsel pintu klas menengah 10,000 pasang
3 Engsel jendela klas menengah 10,000 pasang
4 Hak jendela biasa 7,000 buah
5 Hak jendela kuningan 15,000 buah
6 Grendel jendela 5,000 buah
7 Grendel pintu 5,000 buah
8 Expanolet pintu 65,000 pasang
9 Door closer 25,000 buah
10 Pegangan pintu / door handle 75,000 buah
11 List kaca 1,500 m'
12 Jendela nako 50,000 buah
13 Rolling Door 275,000 m2
14 Besi strip 12,000 kg
15 Kaca polos 3 mm 75,000 m2
16 Kaca polos 5 mm 90,000 m2
17 Kaca ryben 3mm 80,000 m2
18 Glass block 17,500 buah

Bahan Lantai / Dinding


1 Keramik dinding bermotif klas menengah (20/25) 45,000 m2 arwana
2 Keramik dinding polos klas menengah (20/25) 45,000 m2 arwana
3 Keramik lantai relief klas menengah ( 20/20) 45,000 m2 arwana
4 Keramik lantai polos klas menengah (30/30) 50,000 m2 arwana
5 Keramik lantai warna / motif klas menengah (30/30) 60,000 m2 arwana
6 Keramik lantai warna / motif klas menengah (40/40) 50,000 m2 arwana
7 Marmer (40/60) 65,000 m2
8 Plint Keramik 15 x 30 cm 60,000 m2
9 Parquet jati 185,000 m2
10 Carpet 17,500 m2
HARGA
NO. URAIAN SATUAN KET.
(Rp.)
11 Lem Vinyl 100,000 kg
HARGA
NO. URAIAN SATUAN KET.
(Rp.)
Bahan Pengecatan
1 Amplas 2,000 lbr
2 Tinner A 12,500 ltr
3 Dempul kayu klas menengah 24,000 kg
4 Meni kayu klas menengah 12,500 kg
5 Meni besi klas menengah 16,500 kg
6 Lem kayu 14,000 kg
7 Cat kayu klas menengah 55,000 kg Emco
8 Cat besi 45,000 kg
9 Teak oil 26,000 ltr
10 Volitur 42,500 ltr
11 Plamir tembok klas menengah 9,250 kg aga
12 Cat tembok klas menengah 18,750 kg decolith/avian
Cat tembok klas menengah 8,750 kg astex
Cat genteng klas menengah 28,750 kg aga
13 Teer 6,500 ltr

Bahan Listrik

1 Arde 250,000 titik


2 Pipa listrik (conduit) 1,000 m
3 Klem kabel 1,500 kotak
4 Kabel NYY 3x2,5 mm2 9,000 m
5 Kabel NYM 3x2,5 mm2 7,500 m
6 Kabel NYM 2x2,5 mm2 6,500 m
7 MCB 34,500 buah
8 Rel MCB 4,600 buah
9 MCCB 165,000 buah
10 Bus bar 30,000 buah
11 Sisir MCB 15,000 buah
12 Boks Panel 25 x 25 cm 82,000 buah
13 Boks Sekring 17,000 buah
14 Saklar Ganda + Lasdop 15,000 buah
15 Saklar tunggal + Lasdop 14,000 buah
16 Stop kontak + lasdop 15,000 buah
17 Fitting Segi 7,500 buah
18 Kapasitor (20 watt) 4,750 buah
19 Down light 75,000 buah
20 Armatur lampu + kap (2x20w) 85,000 set
21 Armatur lampu + kap (1x20w) 51,000 set
22 Armatur lampu dL Helles 932 60,000 buah
23 Terminal 5,000 buah
24 Bola lampu SL 18 watt 26,000 buah
25 Bola lampu SL 20 watt 29,000 buah
26 Tabung Lampu TL 20 watt 7,500 buah

Bahan Sanitasi

1 Pipa PVC 4" 31,250 m'


2 Pipa PVC 3" 22,500 m'
3 Pipa PVC 2" 7,500 m'
4 Pipa PVC 1" 4,375 m'
5 Pipa GI 2" 28,000 m'
6 Kran 1/2" 22,500 buah
7 Seal tape 5,000 buah
8 Closed duduk 950,000 buah
9 Closed jongkok porselin 75,000 buah
10 Urinoir 450,000 buah
11 Washtafle 600,000 buah
12 Bak cuci stainles steel 200,000 buah
13 Badkip 900,000 buah
14 Bak mandi fiberglass kapasitas 0,3 m3 275,000 buah
15 Tempat sabun porselen 37,000 buah
16 Saringan air stainless 35,000 buah
17 Water drain 35,000 buah
HARGA
NO. URAIAN SATUAN KET.
(Rp.)
Bahan Lainnya

1 Las 7,500 titik

Alat bantu

1 Ember cor 8,000 buah


2 Kuas cat 3,500 buah
3 Rool cat 13,000 buah
4 Sekop 35,000 buah
5 Cangkul 35,000 buah
6 Gerobak dorong 200,000 buah
7 Gergaji besi 12,000 buah
8 Alat bantu tukang 15,000 ls
9 Pemotong keramik 150,000 buah

Alat Berat

10 Sewa stamper 25,000 jam


11 Sewa steger work 15,000 hari
12 Sewa mollen 150,000 hari
13 Sewa dump truk 117,000 jam
14 Sewa alat gilas (stome walles) 235,000 jam 8 ton
15 Sewa exavator 418,000 jam kap. bucket 0,8 m3
16 Sewa buldozer D6D 468,000 jam besar
17 Sewa buldozer D3G 393,000 jam kecil
18 Mob/demob alat berat 6,000,000 unit
PROGRAM NASIONAL PENGEMBANGAN MASYARAKAT - MANDIRI PEDESAAN
TAHUN ANGGARAN 2011

PROVINSI : : NTB
KABUPATEN : : LOMBOK TENGAH
KECAMATAN : : PUJUT
DESA : : BANGKET PARAK
LOKASI :

KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


VOLUME : 1 UNIT

PjOK :

FT :
FK :
TPK :
PROGRAM NASIONAL
PEMBERDAYAAN MASYARAKAT MANDIRI PERDESAAN
PNPM - MP

KEGIATAN : GEDUNG POLINDES

DANA : Rp. 196,813,200.00


Kegiatan : Rp. 196,813,200.00
Ops. UPK : Rp. -
Ops. TPK : Rp. -

KECAMATAN KAYANGAN
LOMBOK UTARA
DESA DANGIANG

2013
TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Persiapan
No. RAB : 01

DIMENSI KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Usuk (m3) Begisting (m3) Paku (kg)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

Luas Bangunan
a Polindes
Ruang periksa 5.00 x 3.00 - 2.25 x 1 12.75
Ruang nifas 5.00 x 4.50 x x 1 22.5
Teras 3.00 x 2.00 x x 1 6
KM/WC 2.00 x 1.50 x x 1 3
Luas a 44.25 M2
b Rumah Bidan
R Tamu 4.50 x 3.00 + 2.25 x 1 15.75
KTU 3.00 x 3.00 x x 1 9
KTA 3.00 x 2.50 x x 1 7.5
Dapur 2.00 x 2.00 x x 1 4
Teras 3.00 x 2.00 x x 1 6
KM/WC 2.00 x 1.50 x x 1 3
Luas b 45.25 M2
Luas Total (a+b) 89.5 M2

1 Bouwplank 11.00 + 9.5 x x 2 41 M' 0.10 4 0.10 4.00 - - 0.01 0.39 0.01 0.23 0.02 0.82 - - - - - - - - - -

Total 4.00 4.00 - 0.39 0.23 0.82 - - - - -

TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Pondasi
No. RAB : 02

DIMENSI KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Tnh Urug (M3) Semen(sak) Batu (m3) Pasir (M3)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

PEKERJAAN GALIAN & URUGAN


1. Galian tanah biasa 83.00 x 0.80 x 0.6 x 39.84 M3 0.40 16.00 - - - - - - - - - - - - - - - - - -
2. Urugan kembali 9.96 M3 0.19 2.00
3. Urugan Peninggian Pondasi 89.50 x 0.4 x 35.8 M3 0.30 11.00 1.20 43.00
4. Urugan bawah pondasi 83.00 x 0.80 x 0.1 x 6.64 M3 0.30 2.00 1.20 8.00

Total 31.00 - - 51.00 - - - - - - -

PEKERJAAN PAS. BATU

30

80

20

70

5. Pas. batu kosong 83.00 x 0.80 x 0.2 x 13.28 M3 0.62 8.00 0.39 5.00 - - - 0.43 6.00 - 1.10 15.00 - - - - - - -
6. Pondasi batu kali/pecah 1 Pc : 5 Ps 83.00 x 0.5 x 0.8 33.2 M3 1.20 40.00 0.60 20.00 - - 2.45 81.00 1.10 37.00 0.54 18.00
Total 110 25 - 102 6.00 81.00 52.00 18.00 - - -
TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Beton Bertulang
No. RAB : 03

DIMENSI KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN jmlh Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Semen(sak) Pasir (m3) Kerikil (m3) Begisting (m3) Usuk (m3) Paku (kg) Besi (lj) Kawat (kg)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

4 D10
z z
z z Begel D6 - 15

0.20 m
z z
z z
0.15 m

1. Sloof (15/20)
a. Beton 1 pc : 2 ps : 3 kr 83.00 x 0.15 x 0.2 2.49 M3
b. Begisting 83.00 x 0.4 x 33.20 M2
c. Pembesian
- Tul utama 4 D10 83.10 x 4 332.40 M'
206.09 KG
- Sengkang D6 - 15 cm 0.70 x 416 291.20 M'
65.00 KG

2. Kolom Expose (40/15)

Begel D6 - 15

8 D12

z z
z z 0.40 m
z z
z z
0.15
m
a. Beton 1 pc : 2 ps : 3 kr 3.50 x 0.15 x 0.4 2 0.42 M3
b. Begisting 3.50 x 1.1 x 2 7.70 M2
c. Pembesian
- Tul utama 4 D12 3.60 x 8 2 57.60 M'
51.43 KG
- Sengkang D6 - 15 cm 1.10 x 19 2 41.80 M'
9.33 KG

3. Kolom praktis (10/10)

Begel D6 - 15

4 D10

z z
z z 0.10 m
z z
z z
0.10
m

a. Beton 1 pc : 2 ps : 3 kr 3.50 x 0.1 x 0.1 19 0.67 M3


b. Begisting 3.50 x 0.2 x 19 13.30 M2
c. Pembesian
- Tul utama 4 D10 3.60 x 4 19 273.60 M'
244.27 KG
- Sengkang D6 - 15 cm 0.40 x 19 19 144.40 M'
32.23 KG
4. Balok gantung/latai (15/20)

4 D10
z z
z z Begel D6 - 15

0.25 m
z z
z z
0.15 m

a. Beton 1 pc : 2 ps : 3 kr 14.00 x 0.15 x 0.25 1 0.53 M3


b. Begisting 14.00 x 0.65 x 1 9.10 M2
c. Pembesian
- Tul utama 4 D12 14.10 x 4 1 56.40 M'
50.35 KG
- Sengkang D6 - 15 cm 0.80 x 71 1 56.80 M'
12.68 KG

5. Ringgalok (10/12)
Begel D6 - 15

4 D10

z z
z z 0.10 m
z z
z z
0.12
m

a. Beton 1 pc : 2 ps : 3 kr 83.00 x 0.1 x 0.12 1.00 M3


b. Begisting 83.00 x 0.24 x 19.92 M2
c. Pembesian
- Tul utama 4 D10 83.10 x 4 332.40 M'
296.77 KG
- Sengkang D6 - 15 cm 0.44 x 416 183.04 M'
40.85 KG

Ringgalok gevel (10/12)

Begel D6 - 15

4 D10

z z
z z 0.10 m
z z
z z
0.12
m

a. Beton 1 pc : 2 ps : 3 kr 13.00 x 0.1 x 0.12 2 0.31 M3


b. Begisting 13.00 x 0.24 x 2 6.24 M2
c. Pembesian
- Tul utama 4 D10 13.10 x 4 2 104.80 M'
93.57 KG
- Sengkang D6 - 15 cm 0.44 x 66 2 58.08 M'
12.96 KG

6. Plat canopy
a. Beton 1 pc : 2 ps : 3 kr 17.00 x 0.5 x 0.07 1 0.60 M3
b. Begisting 17.00 x 0.64 x 1 10.88 M2
c. Pembesian
- Tul utama arah X, D10 - 15 cm x 0.5 x 113 1 56.50 M'
35.03 KG
- Tul utama arah Y, D10 - 20 cm 17.00 x 3 1 51.00 M'
31.62 KG

TOTAL PEK. BETON


a. Beton 1 pc : 2 ps : 3 kr 6.00 M3 6.350 38.00 3.325 20.00 - 6.72 40.00 0.54 3.00 0.81 5.00 - - - -
b. Begisting 100.34 M2 0.02 2.21 - 0.40 40.00
c. Pembesian 1182.17 KG 0.02 18.00
- Besi 12 114.00 M' 1.05 11.00
- Besi 10 1150.70 M' 1.05 110
- Besi 6 775.32 M' 1.05 74.00

T o t a l beton 38.00 20.00 40.00 3.00 5.00 2.21 40.00 18.00


TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Dinding
No. RAB : 04

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Semen(sak) Pasir (m3) Batako (bh) Roster motif (bh) Ventilasi (bh)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1. Pasangan batako 1 Pc : 5 Ps
a. Pasangan tembok
- Luas kotor = 83.00 x x 3.5 x 290.50 M2
- Luas bersih = L kotor - L bukaan 290.50 - 42.00 - 15.68 232.83 M2
b. Pasangan gewel 6.00 x x 1.5 x 4 36.00 M2
c. Pasangan tempat duduk 3.00 x x 0.6 x 0.00 M2
d. Pas. Diatas balok gantung 12.00 x x 0.6 x 1 7.20 M2
e. Pasangan (r.tunggu) x x 1 x 0.00 M2
Total Pas bata 276.03 M2 0.32 88.00 0.10 28.00 0.19 53.00 0.05 12.00 24.4 6,735 - - - - - - - -

2. Roster motif (15 x 15 cm) x x 0.00 0.000 M2 0.30 - 0.10 - 0.26 - 0.05 - - 36 - - - - -
3. Roster ventilasi ( 20 x 30 cm) 10.000 BH 0.01 - 0.00 - 0.01 - 0.00 - - - 1.00 10.00 - - -

Total 88.00 28.00 - 53.00 12.00 6,735 - 10.00 - - -


TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Pintu & Jendela
No. RAB : 03

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Kayu (m3) Papan k.II (m3) Paku (kg)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.

1. Pekerjaan Kusen Pintu & Jendela


J-1
- Luasan kusen : 0.60 x 1.20 x 3.00 2.16 M2
- Panjang kayu kusen : 5.30 x 3.00 15.90 M'
- Volume Kusen : 15.90 x 0.15 x 0.06 0.14 M3

J-2
- Luasan kusen : 1.30 x 1.20 x 1.00 1.56 M2
- Panjang kayu kusen : 6.70 x 1.00 6.70 M'
- Volume Kusen : 6.70 x 0.15 x 0.06 0.06 M3

PJ-1
- Luasan kusen : 2.50 x 1.90 x 1.00 4.75 M2
- Panjang kayu kusen : 7.20 x 1.00 7.20 M'
- Volume Kusen : 7.20 x 0.15 x 0.06 0.06 M3

PJ-2
- Luasan kusen : 2.15 x 1.90 x 1.00 4.09 M2
- Panjang kayu kusen : 6.50 x 1.00 6.50 M'
- Volume Kusen : 6.50 x 0.15 x 0.06 0.06 M3

P-2 (WC)
- Luasan kusen : 1.95 x 0.80 x 2.00 3.12 M2
- Panjang kayu kusen : 5.00 x 2.00 10.00 M'
- Volume Kusen : 10.00 x 0.15 x 0.06 0.09 M3

BV1
- Luasan kusen : 1.35 x 0.60 x 0.00 0.00 M2
- Panjang kayu kusen : 5.00 x 0.00 0.00 M'
- Volume Kusen : 0.00 x 0.14 x 0.05 0.00 M3

Total :
- Luasan kusen : 15.68 M2
- Panjang kayu kusen : 46.30 M'
- Volume kusen : 0.42 M3 6.00 3.00 20.0 8.00 - - 1.10 0.46 - - 6.20 3.00 - - - - - - - - - -

Total 3.00 8.00 - 0.46 - 3.00 - - - - -

2 Daun pintu panel 120 x 190 cm 2 BH


3 Daun pintu panel 80 x 190 cm 4 BH
4 Daun pintu KM/WC 2 BH
5 Ram jendela 60 x 150 cm 2 BH
6 Ram jendela 60 x 100 cm 5 BH
7 Kaca mati 3 mm bening 1.50 x 0.45 x 2.00 1.350 M2

Total - - - - - - - - - - -

TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Plesteran
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Semen (sak) Pasir (m3) Mild (sak)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)
1 Plesteran dinding 1 pc : 5 ps + Acian x x 207.02 2 414.04 M2 0.20 83.00 0.15 62.00 0.09 39.00 0.03 12.00 0.26 106.00 -

2 Plesteran pondasi & beton 1 pc : 3 ps + Acian


- pondasi 83.00 x 0.5 1 41.50
- kolom expose 3.50 x 1.1 2 7.70
- plat canopy 17.00 x 0.5 1 8.50
57.70 M2 0.26 15.00 0.20 12.00 0.14 8.00 0.02 1.20

Total ( 1 + 2 ) 98 74.00 47.00 13.20 106.00 -


TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Atap
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Kayu (m3) Usuk (m3) Reng (m3) Papan (m3) Paku (kg) Genteng (bh) Bubungan (bh) Semen (sak)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1. Rangka Kuda2
a. Balok Tekan (8/12) 2.75 x 0.08 x 0.12 0.000 M3
b. Balok Tarik (8/12) 5.20 x 0.08 x 0.12 0.000 M3
c. Balok Sekur (8/12) 1.10 x 0.08 x 0.12 0.000 M3
d. Tiang Kuda2 (8/12) 1.50 x 0.08 x 0.12 0.000 M3
e. Balok Gantung (8/12) 1.00 x 0.08 x 0.12 0.000 M3
f. Bantalan tiang kuda2 (8/12) 1.00 x 0.08 x 0.12 0.000 M3
g. Balok Gapit (5/10) 3.00 x 0.05 x 0.10 0.000 M3

Gording (8/12) 11.00 x 0.08 x 0.12 0.000 M3


Murplat (8/12) 11.00 x 0.08 x 0.12 0.000 M3
Nok (8/12) 11.00 x 0.08 x 0.12 0.000 M3
Makelar gewel (8/12) 1.00 x 0.08 x 0.12 0.000 M3
Sekur nog (8/12) 1.00 x 0.08 x 0.12 0.000 M3
Kait silang (5/10) 4.00 x 0.05 x 0.10 0.000 M3
Konsol (8/12) 3.00 x 0.08 x 0.12 0.000 M3
0.000 M3 4.00 - 12.00 - 1.10 - 2.52 -
Penyambung
Begel U ujung BH - -
Begel U plat BH - -
Begel plat kopel BH - -
Baut 15 cm BH - -
Baut 30 cm (penyambung kuda2) BH - -
Baut 30 cm (konsol) BH - -

Total - - - - - - - - - - -

2. Lisplank
List plank datar ( 3/20 ) 9.50 x x 2 19.000 M"
List plank miring( 3/20 ) 13.00 x x 2 26.000 M"

Total 45.000 M' 0.10 4.50 0.20 9.00 - - - - 0.005 0.22 0.10 5.00 - - -

3. Penutup atap
Rangka 11.50 x 6 1 69.00 M2
11.50 x 7 1 80.50 M2
Teras 3.00 x 1 4 12.00 M2
161.50 M2 0.10 16.15 0.10 16.15 0.01 1.55 0.004 0.64 0.20 31.00
Penutup atap genteng x 161.50 M2 0.15 24.23 0.08 12.11 25 4,038
Bubungan
pada nog 11.50 x x 11.50
pada lisplank x 12 x 0.00
11.50 M' 0.40 4.60 0.20 2.30 5.00 58.00 0.16 1.80

Total 44.98 30.56 - - 1.55 0.64 - 31.00 4,038 58.00 1.80


TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Lantai & Plafond
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Keramik (m2) Semen (sak) Semen warna (kg) Pasir (m3) Usuk (m3) Paku (kg) Kalsiboard (lbr) List (m)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1. Keramik
Keramik lantai (30/30) 1 89.500
Plint lantai (ban trasram) 83.00 x 0.15 x 0.000
Luas keramik 89.500 M2 0.43 39.00 0.25 22.00 1.05 94 0.23 20.00 0.53 47.00 0.04 3.76

Keramik KM/WC
a. Keramik lantai mozaik (20 x 20) 1.50 x 1.5 x 2 4.500 M2 0.43 2.00 0.25 1.00 1.05 5.00 0.23 1.00 0.53 2.00 0.04 0.19
b. Keramik dinding 5.00 x x 1.50 2 15.000 M2 0.48 7.00 0.36 5.00 1.05 16.00 0.19 3.00 0.53 8.00 0.02 0.27

2. Plafond
a. Ruangan 1 89.500
b. Tritisan 11.00 x 1.3 x 0.000
4.30 x 1 x 0.000
Total 89.500 M2 0.27 24.00 0.40 36.00 0.01 0.83 0.12 11.00 0.36 33.00

Lis plafond 83.00 x x 2 166.000 M' 0.02 3.00 0.03 5.00 0.01 2.00 1.05 ###
TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Polindes


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Pengecatan
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Cat dinding (kg) Plamir (kg) Cat kayu (kg) Meni (kg) Dempul (kg) Myk.cat (ltr) Teer (kg) Cat genteng (kg)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1 Pengecatan dinding 414.04 - -


2 Pengecatan plafond 89.50

Total 503.54 M2 0.02 10.00 0.06 32.00 0.26 131 0.16 81.00 - - - - -

3 Pengecatan kayu - - - - - -
Kusen 46.30 x 0.36 x 16.67 M2
Pintu panel 1.90 x 0.80 x 1 1.52 M2
Pintu KM/WC 1.90 x 0.70 x 1 1.33 M2
Daun jendela 3.40 x 0.18 x 2 1.22 M2
List plank 9.50 x 0.30 x 2.85 M2
4.30 x 0.40 x 1.72 M2

Total cat kayu 25.31 M2 0.07 2.00 0.01 - - - 0.17 4.00 0.20 5.00 0.08 2.00 0.10 3.00

4 Pengetiran
a. Kuda-kuda
- Balok Tekan (8/12) 2.00 x 0.40 0 0.00 M2
- Balok Tarik (8/12) 5.30 x 0.40 0 0.00 M2
- Balok Sekur (8/12) 1.50 x 0.40 0 0.00 M2
- Tiang Kuda2 (8/12) 1.50 x 0.40 0 0.00 M2
- Balok Gantung (8/12) 1.00 x 0.40 0 0.00 M2
- Balok Gapit (5/10) 2.50 x 0.40 0 0.00 M2
- Bantalan tiang kuda2 (8/12) 0.80 x 0.40 0 0.00 M2
b. Gording 8.00 x 0.40 0 0.00 M2
c. Nok (8/12) 8.00 x 0.40 0 0.00 M2
d. Morplat (6/12) 8.00 x 0.36 0 0.00 M2
f. Makkelar gewel 1.50 x 0.40 0 0.00 M2
g. Sekur nog 1.00 x 0.40 0 0.00 M2
h. Kait silang (5/10) 4.00 x 0.30 0 0.00 M2
f. Usuk (5/7) 3.50 x 0.24 0 0.00 M2
g. Reng (3/4) 8.00 x 0.14 0 0.00 M2

Total teer 0.00 M2 0.10 - - 0.35 -

5 Cat genteng 0.00 M2 0.03 - 0.04 - 0.30 -


TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Posyandu


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Kelistrikan
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1 Penyambungan listrik PLN LS - - - - - -


2 Titik lampu 7.00 BH - - - - - -
3 Saklar tunggal 3.00 BH - -
4 Saklar ganda 2.00 BH - -
5 Stop kontak 3.00 BH - -
6 MCB+Box panel 0.00 BH - -

Total 15.000 0.37 0.11 - - - - -

TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Posyandu


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Sanitasi
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) semen (sak) pasir (m3) kerikil (m3) bata (bh) begisting (m3) besi (lj) kawat (kg)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1 Penyediaan air bersih 1.00 UNIT - - - - - -


2 Closed jongkok 1.00 BH - - - - - -
3 Bak air 1.00 BH - -
4 Saringan air 1.00 BH - -
5 Kran air 1.00 BH
6 Pipa PVC 1/2" 6.00 M'
7 Pipa PVC 3" 3.00 M'
8 Pipa PVC 4" 3.00 M'
16.00 UNIT
11 Septictank + peresapan 1.00 UNIT
- galian 2.00 x 1 x 1.5 1 3.00 M3 0.40 1.20
- pas bata 6.00 x x 1.5 1 9.00 M2 0.32 2.88 0.10 0.90 0.19 2.00 0.05 0.41 80 720.00
- beton penutup (t=8 cm) 2.10 x 1.1 x 0.08 1 0.18 M3 1.65 0.30 0.25 0.05 4.36 1.00 0.52 0.10 0.87 0.16
- pembesian
memanjang D10 - 15 cm 2.10 x 6 1 6.00
melintang D10 - 15 cm 1.10 x 11 1 11.00
17.00 M 1.05 2.00
10.47 KG 0.01 0.07 0.01 0.07 0.02 0.16
- begisting 2.00 x 1 1 2.00 M2 0.30 0.60 0.33 0.66 0.02 0.04
Total septiktank 5.00 2.00 3.00 1.00 0.16 720.00 0.04 2.00 0.16
TAKE OF SHEET

Kabupaten : LOMBOK TENGAH Jenis Prasarana : Balai Posyandu


Kecamatan : PUJUT Lokasi :
Desa : BANGKET PARAK Jenis Pekerjaan : Lingkungan
No. RAB : 05

URAIAN KEBUTUHAN BAHAN DAN TENAGA KERJA


ITEM PEKERJAAN Ʃ VOLUME
P (M) L (M) T (M) Pekerja (Hok) Tukang (Hok) Mandor (Hok) Semen (sak) Pasir (m3) Kerikil (m3) batu (kg) batako (bh) Besi (lj) kawat (kg) begisting (m3)
1 2 3 4 6 7 = (2x3x4x5) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef. (7xkoef.) koef (7xkoef.) koef (7xkoef.) koef (7xkoef.)

1 Rabat keliling 28.00 x 0.8 x 0.1 0.00 M3 1.65 - 0.25 - 4.36 - 0.52 - 0.87 - -

3 Pagar halaman 0.00 M'


- galian 0.00 x 0.5 x 0.5 0.00 M3 0.40 -
- pondasi batu 0.00 x 0.4 x 0.5 0.00 M3 1.20 - 0.60 - 2.45 - 0.05 - 1.10 -
- pas batako 0.00 x 1 0.00 M2 0.35 - 0.15 - 0.12 - 0.05 - 14.5 -
- sloof
beton 1 : 2 : 3 0.00 x 0.15 x 0.2 0.00 M3 1.65 - 0.25 - 6.64 - 0.52 - 0.78 -
begisting 0.00 x 0.2 x 50% 0.00 M2 0.30 - 0.33 - 0.02 -
tul utama 4D10 0.00 x x 4 0.00 M' 1.05 -
0.00 KG 0.01 - 0.01 - 0.02 -
sengkang D6 - 20 cm 0.70 1 0.00 M' 1.05 -
0.00 KG 0.01 - 0.01 - 0.02 -

- kolom 0.00 BH
beton 1 : 2 : 3 1.00 x 0.15 x 0.15 0.00 0.00 M3 1.65 - 0.25 - 2.45 - 0.05 - 0.78 -
begisting 1.00 x 0.2 x 50% 0.00 0.00 M2 0.30 - 0.33 - 0.12 - 0.05 - 0.02 -
tul utama 4D10 1.00 x x 4 0.00 0.00 M' 1.05 -
0.00 KG 0.01 - 0.01 - 0.02 -
sengkang D6 - 20 cm 0.60 1 0.00 0.00 M' 1.05 -
0.00 KG 0.01 - 0.01 - 0.02 -

Total pagar - - - - - - - - - -

3 Pintu gerbang 0.00 BH - -


REKAPITULASI RENCANA ANGGARAN BIAYA

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH VOLUME : 1 UNIT
KECAMATAN : PUJUT
DESA : BANGKET PARAK

Kegiatan : Persiapan Kegiatan : Pek Pondasi


Bobot % Bobot %
NO. URAIAN Ukuran : Ukuran
Jumlah :1 Jumlah :1
No. RAB : 01 No. RAB : 02
PNPM-MP Swadaya PNPM-MP Swadaya
I. BAHAN - 1,221,780 50 23,922,700 500,000 79.99
II. PERALATAN 700,000 - 29 160,000 - 0.52
III. UPAH - 520,000 21 4,400,000 1,550,000 19.49

JUMLAH (Pembulatan) 700,000 1,741,780 100 28,482,700 2,050,000 100

JUMLAH TOTAL 700,000 1,741,780 28,482,700 2,050,000

JUMLAH BIAYA UPAH - 520,000 4,400,000 1,550,000

JUMLAH HOK KONSTRUKSI - 8.00 73.00 31.00

Kegiatan : Pek Beton Kegiatan : Pas. Dinding


Bobot % Bobot %
NO. URAIAN Ukuran : Ukuran :
Jumlah :1 Jumlah :1
No. RAB : 05 No. RAB : 03
PNPM-MP Swadaya PNPM-MP Swadaya
I. BAHAN 20,434,900 - 85 19,848,000 - 75
II. PERALATAN 12,000 - 0 55,000 - 0
III. UPAH 3,500,000 - 15 6,640,000 - 25

JUMLAH (Pembulatan) 23,946,900 - 100 26,543,000 - 100

JUMLAH TOTAL 23,946,900 - 26,543,000 -

JUMLAH BIAYA UPAH 3,500,000 - 6,640,000 -

JUMLAH HOK KONSTRUKSI 58.00 - 116.00 -


: Pek Pintu
Kegiatan Kegiatan : Plesteran
Jendela
Bobot % Bobot %
NO. URAIAN Ukuran : Ukuran
Jumlah :1 Jumlah :1
No. RAB : 04 No. RAB : 06
PNPM-MP Swadaya PNPM-MP Swadaya
I. BAHAN 13,989,200 - 85 7,513,000 - 41
II. PERALATAN - - - 15,000 - 0
III. UPAH 2,540,000 - 15 10,820,000 - 59

JUMLAH (Pembulatan) 16,529,200 - 100 18,348,000 - 100

JUMLAH TOTAL 16,529,200 - 18,348,000 -

JUMLAH BIAYA UPAH 2,540,000 - 10,820,000 -

JUMLAH HOK KONSTRUKSI 37.00 - 172.00 -

: Pek Lantai &


Kegiatan : Pek Atap Kegiatan
Plafond
Bobot % Bobot %
NO. URAIAN Ukuran Ukuran
Jumlah :1 Jumlah :1
No. RAB : 07 No. RAB : 08
PNPM-MP Swadaya PNPM-MP Swadaya
I. BAHAN 43,805,000 - 100 22,450,200 - 83
II. PERALATAN - - - - - -
III. UPAH - - - 4,640,000 - 17

JUMLAH (Pembulatan) 43,805,000 - 100 27,090,200 - 100

JUMLAH TOTAL 43,805,000 - 27,090,200 -

JUMLAH BIAYA UPAH - - 4,640,000 -

JUMLAH HOK KONSTRUKSI - - 76.00 -

Kegiatan : Pek Pengecatan Bobot % Kegiatan : Pek Listrik Bobot %


Ukuran : Ukuran
NO. URAIAN Jumlah :1 Jumlah :1
No. RAB : 10 No. RAB : 11
PNPM-MP Swadaya PNPM-MP Swadaya
I. BAHAN 3,573,400 - 53 1,644,500 - 73

II. PERALATAN 39,000 - 1 - - -

III. UPAH 3,160,000 - 47 610,000 - 27

JUMLAH (Pembulatan) 6,772,400 - 100 2,254,500 - 100


IV. OPERASIONAL UPK (2%)
V. OPERASIONAL TPK (3%)
JUMLAH TOTAL 6,772,400 - 2,254,500 -
JUMLAH BIAYA UPAH 3,160,000 - 610,000 -
JUMLAH HOK KONSTRUKSI 44.00 - 8.00 -
Kegiatan : Pek Sanitasi Bobot % JUMLAH TOTAL Bobot %
Ukuran :
NO. URAIAN Jumlah :1
No. RAB : 12
PNPM-MP Swadaya PNPM-MP Swadaya
I. BAHAN 1,931,300 - 82 159,112,200 1,721,780 80.17

II. PERALATAN - - - 981,000 - 0.49

III. UPAH 410,000 - 18 36,720,000 2,070,000 19.34

JUMLAH (Pembulatan) 2,341,300 - 100 196,813,200 3,791,780 100

JUMLAH TOTAL 2,341,300 - 196,813,200 3,791,780

JUMLAH BIAYA UPAH 410,000 -

JUMLAH HOK KONSTRUKSI 7.00 - 591.00 39.00

Disetujui Oleh : Dibuat oleh :


Kepala Desa Kader
RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : PERSIAPAN
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 01

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH PNPM-MP SWADAYA SATUAN PNPM-MP SWADAYA JUMLAH

1. Pendukung 1.000 ls
a. Bahan
Air kerja ls 1.00 0.00 1.00 0 - - -
- - -
b. Peralatan
Papan proyek bh 1.00 1.00 0.00 100,000 100,000 - 100,000
Prasasti bh 1.00 1.00 0.00 600,000 600,000 - 600,000
700,000 - 700,000
c. Tenaga
Pekerja hok - - - 50,000 - - -
Tukang hok - - - 80,000 - - -
Mandor hok - - - - - -
- - -

Jumlah Biaya (a+b+c) 700,000 - 600,000

2. Pengukuran dan pemasangan bowplang 41.000 M'


a. Bahan
Kayu Kaso 4 / 6 kls III m3 0.39 0.00 0.39 1,900,000 - 747,840 747,840
Paku Biasa 2" - 5" Kg 0.82 0.00 0.82 17,000 - 13,940 13,940
Kayu Papan 2 / 20 kls III m3 0.23 0.00 0.23 2,000,000 - 460,000 460,000
- 1,221,780 1,221,780
b. Peralatan
Alat bantu m 1.00 1.00 0.00 0 - - -
- - -
c. Tenaga
Pekerja hok 4.00 0.00 4.00 50,000 - 200,000 200,000
Tukang hok 4.00 0.00 4.00 80,000 - 320,000 320,000
Mandor hok 0.00 0.00 0 - - -
- 520,000 520,000

Jumlah Biaya (a+b+c) - 1,741,780 1,741,780

SUB TOTAL I 700,000 1,741,780 2,341,780


DARI PNPM-MP 700,000
SUMBER DANA SWADAYA 1,741,780
TOTAL BIAYA 2,441,780.00

Disetujui Oleh : Dibuat Oleh :


PJOK FT

0 0.00
0
RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : PONDASI
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 2

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

I. PEKERJAAN TANAH/PASIR
1. Galian dan urugan 35.80 M3
a. Bahan
Tanah urug m3 51.00 43.00 8.00 62,500 2,687,500 500,000 3,187,500

2,687,500 500,000 3,187,500


b. Peralatan
Alat bantu (bawa sendiri) ls 0.00 0.00 0.00 0 - - -
- - -
c. Tenaga
Pekerja hok 31.00 - 31.00 50,000 - 1,550,000 1,550,000
Mandor hok - - - - - -
- 1,550,000 1,550,000

Jumlah Biaya (a+b+c) 2,687,500 2,050,000 4,737,500

II. PEKERJAAN PASANGAN BATU


2. Pondasi batu kosong 13.28 M3
a. Bahan
Batu Belah m3 15.00 15.00 - 216,600 3,249,000 - 3,249,000
Pasir urug m3 6.00 6.00 - 75,000 450,000 - 450,000
3,699,000 - 3,699,000
b. Peralatan
Alat bantu kerja ls 0.00 0.00 0.00 0 - - -
- - -
c. Tenaga
Pekerja hok 8.00 8.00 - 50,000 400,000 - 400,000
Tukang hok 5.00 5.00 - 80,000 400,000 - 400,000
Mandor hok - - - - - -
800,000 - 800,000

Jumlah Biaya (a+b+c) 4,499,000 - 4,499,000


VOL SAT VOLUME HARGA BIAYA (Rp.)
NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH
3. Pondasi batu kali/pecah 1 Pc : 5 Ps 33.20 M3
a. Bahan
Batu Belah m3 37.00 37.00 - 216,600 8,014,200 - 8,014,200
Pasir pasang m3 18.00 18.00 - 214,000 3,852,000 - 3,852,000
Semen sak 81.00 81.00 - 70,000 5,670,000 - 5,670,000
17,536,200 - 17,536,200
b. Peralatan
Ember bh 20.00 20.00 0.00 8,000 160,000 - 160,000
160,000 - 160,000
c. Tenaga
Pekerja hok 40.00 40.00 - 50,000 2,000,000 - 2,000,000
Tukang hok 20.00 20.00 - 80,000 1,600,000 - 1,600,000
Mandor hok - - - - - -
3,600,000 - 3,600,000

Jumlah Biaya (a+b+c) 21,296,200 - 21,296,200

SUB TOTAL II 28,482,700 2,050,000 30,532,700


DARI ADD 28,482,700
SUMBER DANA SWADAYA 2,050,000
TOTAL BIAYA 30,532,700

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI: NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPAT: LOMBOK TENGAH PEKERJAAN : BETON
KECAMAT: PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 3

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

Beton bertulang 6.00 M3


a. Bahan
Papan begisting kls III m3 2.21 2.21 - 2,000,000 4,414,900 - 4,414,900
Paku Biasa 2" - 5" kg 40.00 40.00 - 17,000 680,000 - 680,000
Besi Beton 12 mm lj 11.00 11.00 - 105,000 1,155,000 - 1,155,000
Besi Beton 10 mm lj 110.00 110.00 - 70,000 7,700,000 - 7,700,000
Besi Beton 6 mm lj 74.00 74.00 - 22,500 1,665,000 - 1,665,000
Kawat Beton kg 18.00 18.00 - 21,000 378,000 - 378,000
Semen sak 40.00 40.00 - 70,000 2,800,000 - 2,800,000
Pasir cor m3 3.00 3.00 - 214,000 642,000 - 642,000
Kerikil m3 5.00 5.00 - 200,000 1,000,000 - 1,000,000
20,434,900 - 20,434,900
b. Peralatan
Gergaji besi bh 1 1 - 12,000 12,000 - 12,000
12,000 - 12,000
c. Tenaga
Pekerja hok 38.00 38.00 - 50,000 1,900,000.00 - 1,900,000.00
Tukang hok 20.00 20.00 - 80,000 1,600,000.00 - 1,600,000.00
Mandor hok - - - - - - -
3,500,000.00 0.00 3,500,000.00

Jumlah Biaya (a+b+c) 23,946,900 - 23,946,900

SUB TOTAL V 23,946,900 - 23,946,900


23,946,900
SUMBER DANA SWADAYA -
TOTAL BIAYA 23,946,900

Disetujui Oleh : Dibuat Oleh :

0
RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : DINDING
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 4

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

I. PEK. PASANGAN DINDING


1. Pasangan 1/2 bata 1 Pc : 5 Ps 276.025 M2
a. Bahan
Batako bh 6,735 6,735 - 2,000 13,470,000 - 13,470,000
Semen Portland sak 53 53 - 70,000 3,710,000 - 3,710,000
Pasir Pasang m3 12 12 - 214,000 2,568,000 - 2,568,000
Roster motif (15 x 15 cm) bh - - - 20,000 - - -
Roster polos (15 x 25 cm) bh 10 10 - 10,000 100,000 - 100,000
19,848,000 - 19,848,000
b. Peralatan
Ember cor bh 5 5 0 8,000 40,000 - 40,000
Ayakan bh 1 1 0 15,000 15,000 - 15,000
Alat bantu kerja ls 1 1 0 0 - - -
55,000 - 55,000
c. Tenaga
Perkerja hok 88.00 88.00 - 50,000 4,400,000 - 4,400,000
Tukang hok 28.00 28.00 - 80,000 2,240,000 - 2,240,000
Mandor hok - - - - - -
6,640,000 - 6,640,000

Jumlah Biaya (a+b+c) 26,543,000 - 26,543,000

SUB TOTAL III 26,543,000 - 26,543,000


26,543,000
SUMBER DANA SWADAYA -
TOTAL BIAYA 26,543,000

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATE: LOMBOK TENGAH PEKERJAAN : PINTU DAN JENDELA
KECAMATA: PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 5

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

VII. PEKERJAAN PINTU DAN JENDELA


1. Pekerjaan Kusen 0.417 M3
a. Bahan
Balok Kayu 6/14 m3 0.46 0.46 - 3,500,000 1,604,200 - 1,604,200
Paku kg 3.00 3.00 - 15,000 45,000 - 45,000
1,649,200 - 1,649,200
b. Peralatan
Alat bantu kerja ls 1.00 0.00 1.00 - - - -
- - -
c. Tenaga
Perkerja hok 3.00 3.00 - 50,000 150,000 - 150,000
Tukang hok 8.00 8.00 - 80,000 640,000 - 640,000
Mandor hok - - - - - -
790,000 - 790,000

Jumlah Biaya (a+b+c) 2,439,200 - 2,439,200


2. Daun Pintu BH
a. Bahan
Panil 120 x 190 bh 2.00 2.00 - 1,250,000 2,500,000 - 2,500,000
Panil 80 x 190 bh 4.00 4.00 - 750,000 3,000,000 - 3,000,000
Panil 70 x 190 lapis seng (WC) bh 2.00 2.00 - 750,000 1,500,000 - 1,500,000
Kunci Tanam 2 slag bh 8.00 8.00 - 200,000 1,600,000 - 1,600,000
Engsel psng 8.00 8.00 - 25,000 200,000 - 200,000
Grendel bh 8.00 8.00 - 15,000 120,000 - 120,000
8,920,000 - 8,920,000
b. Peralatan
Alat bantu kerja ls 1.00 0.00 1.00 - - - -
- - -
c. Tenaga
Perkerja hok 6.00 6.00 - 50,000 300,000 - 300,000
Tukang hok 8.00 8.00 - 80,000 640,000 - 640,000
Mandor hok - - - - - -
940,000 - 940,000

Jumlah Biaya (a+b+c) 9,860,000 - 9,860,000


VOL SAT VOLUME HARGA BIAYA (Rp.)
NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH
3 Daun Jendela
a. Bahan
Ram 60 x 150 + kaca 3 mm bh 2.00 2.00 - 500,000 1,000,000 - 1,000,000
Ram 60 x 100 + kaca 3 mm bh 5.00 5.00 - 400,000 2,000,000 - 2,000,000
Engsel jendela psng 7.00 7.00 - 20,000 140,000 - 140,000
Grendel jendela bh 7.00 7.00 - 10,000 70,000 - 70,000
Haag angin kuningan bh 14.00 14.00 - 15,000 210,000 - 210,000
3,420,000 - 3,420,000
b. Peralatan
Alat bantu kerja ls 1.00 0.00 1.00 - - - -
- - -
c. Tenaga
Perkerja hok 5.00 5.00 - 50,000 250,000 - 250,000
Tukang hok 7.00 7.00 - 80,000 560,000 - 560,000
Mandor hok - - - - - -
810,000 - 810,000

Jumlah Biaya (a+b+c) 4,230,000 - 4,230,000

SUB TOTAL VII 16,529,200 - 16,529,200


16,529,200
SUMBER DANA SWADAYA 0.00
TOTAL BIAYA 16,529,200

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : PLESTERAN
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 6

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

IV. PEKERJAAN PLESTERAN


1. Plesteran 1 Pc : 5 Ps tebal 15 mm + Acian 414.04 M2
a. Bahan
Semen Portland sak 39.00 39.00 - 70,000 2,730,000 - 2,730,000
Pasir Pasang m3 12.00 12.00 - 214,000 2,568,000 - 2,568,000
Mild Stone sak 106.00 106.00 - 12,500 1,325,000 - 1,325,000
6,623,000 - 6,623,000
b. Peralatan
Ayakan ls 1.00 1.00 0.00 15,000 15,000 - 15,000
15,000 - 15,000
c. Tenaga
Pekerja hok 83.00 83.00 - 50,000 4,150,000 - 4,150,000
Tukang hok 62.00 62.00 - 80,000 4,960,000 - 4,960,000
Mandor hok - - - - - -
9,110,000 - 9,110,000

Jumlah Biaya (a+b+c) 15,748,000 - 15,748,000


2. Plesteran Pondasi&Beton Expose, 1 pc : 3 ps + Acian 57.70 M2
a. Bahan
Semen Portland sak 8.00 8.00 - 70,000 560,000.00 - 560,000.00
Pasir Pasang m3 1.20 1.20 - 275,000 330,000.00 - 330,000.00
890,000.00 - 890,000.00
b. Peralatan
Alat bantu kerja ls 0.00 0.00 0.00 5,000 - - -
- - -
c. Tenaga
Pekerja hok 15.00 15.00 - 50,000 750,000.00 - 750,000.00
Tukang hok 12.00 12.00 - 80,000 960,000.00 - 960,000.00
Mandor hok - - - - - -
1,710,000.00 0.00 1,710,000.00

Jumlah Biaya (a+b+c) 2,600,000 - 2,600,000

SUB TOTAL IV 18,348,000.0 0.00 18,348,000.00


18,348,000.00
SUMBER DANA SWADAYA 0.00
TOTAL BIAYA 18,348,000.00

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : KONSTRUKSI ATAP
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB :

VOL SATUAN VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

1 Rangka Baja + Penutup Atap 161.500 M2


a. Bahan
Rangka baja ringan C75 m2 161.50 161.50 0.00 180,000 29,070,000 - 29,070,000
Genteng Metal 0,25 mm m2 161.50 161.50 0.00 65,000 10,497,500 - 10,497,500
Nog metal m 11.50 11.50 0.00 75,000 862,500 - 862,500
Kalsi plank + rangka m 45.00 45.00 0.00 75,000 3,375,000 - 3,375,000
43,805,000 - 43,805,000
b. Peralatan
Alat bantu kerja ls 0.00 0.00 0.00 - - - -
- - -
c. Tenaga

- - -

Jumlah Biaya (a+b+c) 43,805,000 - 43,805,000

SUB TOTAL VI 43,805,000 - 43,805,000


43,805,000
SUMBER DANA SWADAYA -
TOTAL BIAYA 43,805,000

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : LANTAI DAN PLAFOND
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 8

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

A PEKERJAAN PENUTUP LANTAI


1. Lantai keramik + Ban Trasram 30/30 89.500 M2
a. Bahan
Keramik 30 x 30 cm m2 94.00 94.00 - 60,000 5,640,000 - 5,640,000
Semen Portland sak 20.00 20.00 - 70,000 1,400,000 - 1,400,000
Pasir Pasang m3 3.76 3.76 - 214,000 804,600 - 804,600
Semen Warna kg 47.00 47.00 - 10,000 470,000 - 470,000
8,314,600 - 8,314,600
b. Peralatan
alat bantu pemotong keramik (bawa sendiri) ls 0.00 0.00 0.00 - - - -
- - -
c. Tenaga
Perkerja hok 39.00 39.00 - 50,000 1,950,000 - 1,950,000
Tukang Batu hok 22.00 22.00 - 80,000 1,760,000 - 1,760,000
Mandor hok - - - - -
3,710,000 - 3,710,000

Jumlah Biaya (a+b+c) 12,024,600 - 12,024,600


VOL SAT VOLUME HARGA BIAYA (Rp.)
NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH
2. Lantai keramik KM/WC 20/20 cm 4.500 M2
a. Bahan
Keramik 20 x 20 cm (relief) m2 5.00 5.00 - 45,000 225,000 - 225,000
Semen Portland sak 1.00 1.00 - 70,000 70,000 - 70,000
Pasir Pasang m3 0.19 0.19 - 214,000 40,400 - 40,400
Semen Warna kg 8.00 8.00 - 10,000 80,000 - 80,000
415,400 - 415,400
b. Peralatan
alat bantu pemotong keramik (bawa sendiri) ls 1.00 0.00 1.00 - - -
- - -
c. Tenaga
Perkerja hok 2.00 2.00 - 50,000 100,000 - 100,000
Tukang Batu hok 1.00 1.00 - 80,000 80,000 - 80,000
Mandor hok - - - - - -
180,000 - 180,000

Jumlah Biaya (a+b+c) 595,400 - 595,400


4. Dinding keramik KM/WC 20/25 cm klas menengah 15.000 M2
a. Bahan
Keramik 20 x 25 cm (polos) m2 16.00 16.00 - 45,000 720,000 - 720,000
Semen Portland sak 3.00 3.00 - 70,000 210,000 - 210,000
Pasir Pasang m3 0.27 0.27 - 214,000 57,700 - 57,700
Semen Warna kg 8.00 8.00 - 10,000 80,000 - 80,000
1,067,700 - 1,067,700
b. Peralatan
alat bantu pemotong keramik (bawa sendiri) ls 1.00 0.00 1.00 - - - -
- - -
c. Tenaga
Perkerja hok 7.00 7.00 - 50,000 350,000 - 350,000
Tukang Batu hok 5.00 5.00 - 80,000 400,000 - 400,000
Mandor hok - - - - - -
750,000 - 750,000

Jumlah Biaya (a+b+c) 1,817,700 - 1,817,700


VOL SAT VOLUME HARGA BIAYA (Rp.)
NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

B. PEKERJAAN PLAFOND
1 Plafond Kalsiboard + Rangka 89.500 M2
a. Bahan
Kalsiboard + Rangka m2 89.50 89.50 - 95,000 8,502,500 - 8,502,500
List gypsum kg 166.00 166.00 - 25,000 4,150,000 - 4,150,000
12,652,500 - 12,652,500
b. Peralatan
ls - - - - - - -
- - -
c. Tenaga
Perkerja hok 0.00 - - 50,000 - - -
Tukang Kayu hok 0.00 - - 80,000 - - -
Mandor hok - - - - - -
- - -

Jumlah Biaya (a+b+c) 12,652,500 - 12,652,500

SUB TOTAL VIII 27,090,200.0 0.00 27,090,200.0


27,090,200.0
SUMBER DANA SWADAYA 0.00
TOTAL BIAYA 27,090,200.0

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : PENGECATAN
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 9

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

X. PEKERJAAN PENGECATAN
1. Pengecatan Kayu 25.312 M2
a. Bahan
Cat Meni Kg 5.00 5.00 - 12,500 62,500 - 62,500
Dempul Kg 2.00 2.00 - 24,000 48,000 - 48,000
Cat Kayu Kg 4.00 4.00 - 55,000 220,000 - 220,000
Minyak Cat Ltr 3.00 3.00 - 12,500 37,500 - 37,500
368,000 - 368,000
b. Peralatan
Amplas lbr 3 3 - 2,000 6,000 - 6,000
Kuas 1' - 3' bh 2 2 - 3,500 7,000 - 7,000
13,000 - 13,000
c. Tenaga
Perkerja hok 2.00 2.00 - 50,000 100,000 - 100,000
Tukang Cat hok 0.00 - - 80,000 - - -
Mandor hok - - - - - -
100,000 - 100,000

Jumlah Biaya (a+b+c) 481,000 - 481,000


VOL SAT VOLUME HARGA BIAYA (Rp.)
NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH
2. Cat Plafond+tembok baru (1 lapis plamir, 3 lapis cat) 503.538 M2
a. Bahan
Plamir Kg 81.00 81.00 - 9,250 749,200 - 749,200
Cat Tembok Kg 131.00 131.00 - 18,750 2,456,200 - 2,456,200
3,205,400 - 3,205,400
b. Peralatan
Roll cat bh 2.00 2 - 13,000 26,000 - 26,000
26,000 - 26,000
c. Tenaga
Perkerja hok 10.00 10.00 - 50,000 500,000 - 500,000
Tukang Cat hok 32.00 32.00 - 80,000 2,560,000 - 2,560,000
Mandor hok - - - - - -
3,060,000 - 3,060,000

Jumlah Biaya (a+b+c) 6,291,400 - 6,291,400

SUB TOTAL X 6,772,400.00 0.00 6,772,400.00


ADD 6,772,400.00
SUMBER DANA SWADAYA 0.00
TOTAL BIAYA 6,772,400.00

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA
( DETAIL )

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : INSTALASI LISTRIK
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 10

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

XI. PEKERJAAN INSTALSI LISTRIK


1. Penyambungan Listrik PLN - ls 0.00 0.00 0.00 3,500,000.00 - - -

2. Intalasi Listrik 15.000 TITIK


a. Bahan
Fiting lampu bh 15.00 15.00 - 7,000 105,000 - 105,000
Saklar Tunggal bh 3.00 3.00 - 15,000 45,000 - 45,000
Saklar Ganda bh 2.00 2.00 - 15,000 30,000 - 30,000
Stop Kontak bh 3.00 3.00 - 15,000 45,000 - 45,000
Lasdop/kom bh 5.00 5.00 - 1,000 5,000 - 5,000
NYM 2 x 2.5 mm2 m¹ 150.00 150.00 - 6,500 975,000 - 975,000
Klem bh 3.00 3.00 - 1,500 4,500 - 4,500
Pipa instlasi m¹ 45.00 45.00 - 1,000 45,000 - 45,000
Lampu SL 18 watt bh 15.00 15.00 - 26,000 390,000 - 390,000
1,644,500 - 1,644,500
b. Peralatan
- bh 0.00 - - - - - -
- - -
c. Tenaga
Pekerja hok 6.00 6.00 - 50,000 300,000 - 300,000
Tukang listrik hok 2.00 2.00 - 80,000 160,000 - 160,000
Pembantu instalator hok 3.00 3.00 - 50,000 150,000 - 150,000
610,000 - 610,000

Jumlah Biaya (a+b+c) 2,254,500 - 2,254,500

SUB TOTAL XI 2,254,500.00 0.00 2,254,500.00


2,254,500.00
SUMBER DANA SWADAYA 0.00
TOTAL BIAYA 2,254,500.00

Disetujui Oleh : Dibuat Oleh :


RENCANA ANGGARAN BIAYA

PROVINSI : NTB KEGIATAN : PEMBANGUNAN GEDUNG POLINDES


KABUPATEN : LOMBOK TENGAH PEKERJAAN : INSTALASI AIR & SANITASI
KECAMATAN : PUJUT VOLUME : 1 UNIT
DESA : BANGKET PARAK NO RAB : 11

VOL SAT VOLUME HARGA BIAYA (Rp.)


NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH

XII. PEKERJAAN INSTALSI AIR & SANITASI


1. Pengadaan air bersih (PAM/Sumur)* UNIT 0.00 0.00 - 1,000,000 - - -
2. Plumbing
a. Bahan
Closed jongkok bh 1.00 1.00 - 75,000 75,000 - 75,000
Bak air bh 1.00 1.00 - 275,000 275,000 - 275,000
Saringan air bh 1.00 1.00 - 35,000 35,000 - 35,000
Kran air lj 1.00 1.00 - 22,500 22,500 - 22,500
Pipa PVC 3/4" lj 6.00 6.00 - 17,000 102,000 - 102,000
Pipa PVC 3" lj 3.00 3.00 - 37,000 111,000 - 111,000
Pipa PVC 4" lj 3.00 3.00 - 45,000 135,000 - 135,000
755,500 - 755,500
b. Peralatan
- bh 0.00 - - - - - -
- - -
c. Tenaga
Perkerja hok - - 50,000 - - -
Tukang hok - - 80,000 - - -
Mandor hok - - - - - -
- - -

Jumlah Biaya (a+b+c) 755,500 - 755,500


VOL SAT VOLUME HARGA BIAYA (Rp.)
NO. URAIAN
PEK JUMLAH ADD SWADAYA SATUAN ADD SWADAYA JUMLAH
10. Pembuatan Septiktank 1.000 unit
a. Bahan
bata merah bh 720.00 720.00 - 550 396,000 - 396,000
semen sak 3.00 3.00 - 70,000 210,000 - 210,000
pasir m3 1.00 1.00 - 214,000 214,000 - 214,000
kerikil m3 0.16 0.16 - 200,000 32,000 - 32,000
papan begisting m3 0.04 0.04 - 2,000,000 88,000 - 88,000
kayu usuk 5/7 m3 0.03 0.03 - 1,900,000 62,100 - 62,100
besi dia 10 kg 2.00 2.00 - 12,000 24,000 - 24,000
Pipa hawa GI Ø 2" M' 2.00 2.00 - 28,000 56,000 - 56,000
Pipa PVC Ø 4" M' 3.00 3.00 - 31,250 93,700 - 93,700
1,175,800 - 1,175,800
b. Peralatan
- unit 0.00 - - - - -
- - -
c. Tenaga
pekerja hok 5.00 5.00 - 50,000 250,000 - 250,000
Tukang hok 2.00 2.00 - 80,000 160,000 - 160,000
mandor hok - - - - - -
410,000 - 410,000

Jumlah Biaya (a+b+c) 1,585,800 - 1,585,800

SUB TOTAL XII 2,341,300.00 0.00 2,341,300.00


DARI ADD 2,341,300.00
SUMBER DANA SWADAYA 0.00
TOTAL BIAYA 2,341,300.00

Disetujui Oleh : Dibuat Oleh :


PNPM - MANDIRI PEDESAAN
TAHUN ANGGARAN 2013

JADWAL PELAKSANAAN (TIME SCHEDULE)


PROVINSI : : NTB
KABUPATEN : : LOMBOK TENGAH
KECAMATAN ; : PUJUT
DESA : : BANGKET PARAK

KEGIATAN : GEDUNG POSYANDU


VOLUME : 4 UNIT

RENCANA KERJA PELAKSANAAN (TIME SCHEDULE)


NO URAIAN PEKERJAAN NILAI BOBOT DURASI PROGRES RENCANA BULAN I BULAN II BULAN III BULAN IV PEMELIHARAAN
PEKERJAAN (Minggu) (Per/mg) REALISASI 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

I PERSIAPAN 700,000.00 #REF! 1.00 #REF! Rencana #REF!


Realisasi

II PONDASI 28,482,700.00 #REF! 2.00 #REF! Rencana #REF! #REF!


Realisasi

III BETON 23,946,900.00 #REF! 3.00 #REF! Rencana #REF! #REF! #REF!
Realisasi

IV DINDING 26,543,000.00 #REF! 2.00 #REF! Rencana #REF! #REF!


Realisasi

V PINTU DAN JENDELA 16,529,200.00 #REF! 2.00 #REF! Rencana #REF! #REF!
Realisasi

VI PLESTERAN 18,348,000.00 #REF! 1.00 #REF! Rencana #REF!


Realisasi

VII KONSTRUKSI ATAP 43,805,000.00 #REF! 2.00 #REF! Rencana #REF! #REF!
Realisasi

VIII LANTAI DAN PLAFOND 27,090,200.00 #REF! 2.00 #REF! Rencana #REF! #REF!
Realisasi

IX PENGECATAN 6,772,400.00 #REF! 1.00 #REF! Rencana #REF!


Realisasi

X INSTALASI LISTRIK 2,254,500.00 #REF! 1.00 #REF! Rencana #REF!


Realisasi

XI INSTALASI AIR & SANITASI 2,341,300.00 #REF! 1.00 #REF! Rencana #REF!
Realisasi

XII #REF! #REF! #REF! 1.00 #REF! Rencana #REF!


Realisasi

XIII #REF! #REF! #REF! 2.00 #REF! Rencana #REF! #REF!


Realisasi 0.00%

JUMLAH #REF! #REF!


RENCANA MINGGU INI 0.00% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.00%

RENCANA KOMULATIF MINGGU INI 0.00% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
REALISASI MINGGU INI 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REALISASI KOMULATIF MINGGU INI 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
DEVIASI MINGGU INI 0.00% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

Mengetahui Dibuat oleh :


Fasilitator Teknik Ketua TPK

0.00 0
TABEL PERHITUNGAN
KUANTITAS PEMBESIAN DALAM PEKERJAAN
UNTUK MENDUKUNG ANALISA HARGA SATUAN

Dimensi Panjang Diameter Tulangan Berat Tulangan Per-Meter Jrk begel


NO. JENIS BETON bxh Per - m3 Pokok Ekstra Begel Pokok Ekstra Begel Rata@
(CM) (M) (MM) (MM) (MM) (KG/M) (KG/M) (KG/M) (CM)

SLOOF

1 Sloof 15/20 15 x 20 33.33 10.00 - 7.00 0.617 0.000 0.302 15.00

KOLOM

1 Kolom 30/30 ( Ka ) 30 x 30 11.11 12.00 - 7.00 0.888 0.000 0.302 15.00


2 Kolom 20/20 ( Kp1 ) 20 x 20 25.00 12.00 - 7.00 0.888 0.000 0.302 20.00
3 Kolom praktis 12/12 ( Kp ) 12 x 12 69.44 10.00 - 7.00 0.617 0.000 0.302 20.00
5 Kolom 15/20 15 x 20 33.33 12.00 - 7.00 0.888 0.000 0.302 20.00

BALOK

1 Balok Latai 1 15/30 15 x 30 22.22 12.00 - 7.00 0.888 0.000 0.302 15.00
2 Balok Latai 2 15/25 15 x 25 26.67 12.00 - 7.00 0.888 0.000 0.302 15.00
3 Balok Praktis 12/12 12 x 12 69.44 10.00 - 7.00 0.617 0.000 0.302 30.00
4 Balok Ring 12/20 12 x 20 41.67 10.00 - 7.00 0.617 0.000 0.302 25.00
5 Balok Ring 15/30 (BR1) 15 x 30 22.22 12.00 - 7.00 0.888 0.000 0.302 15.00
6 Balok Ring 15/25 (BR2) 15 x 25 26.67 12.00 - 7.00 0.888 0.000 0.302 15.00
7 Balok Gantung 15/25 15 x 25 26.67 12.00 - 7.00 0.888 0.000 0.302 20.00
8 Beton Balok Gewel 12/15 12 x 15 55.56 10.00 - 7.00 0.617 0.000 0.302 20.00
PERHITUNGAN
N DALAM PEKERJAAN BETON
LISA HARGA SATUAN PEKERJAAN

Panjang Jumlah Tulangan Berat Total Tulangan Kebutuhan


Begel / bh Pokok Ekstra Begel Pokok Ekstra Begel Tulangan Beton Begisting
(M) (BH) (BH) (BH) (KG) (KG) (KG) (KG) (M3) (M2)

0.50 4.00 - 224.00 82.238 0.000 33.849 116.087 0.9852 13.3333

1.00 6.00 - 76.00 59.211 0.000 22.969 82.181 0.9895 13.3333


0.60 4.00 - 126.00 88.817 0.000 22.848 111.665 0.9858 20.0000
0.28 4.00 - 349.00 171.329 0.000 29.533 200.863 0.9744 33.3333
0.50 4.00 - 168.00 118.423 0.000 25.387 143.810 0.9817 20.0000

0.70 6.00 - 150.00 118.423 0.000 31.734 150.156 0.9809 13.3333


0.60 6.00 - 179.00 142.107 0.000 32.459 174.566 0.9778 13.3333
0.28 4.00 - 233.00 171.329 0.000 19.717 191.047 0.9757 16.6667
0.44 4.00 - 168.00 102.798 0.000 22.340 125.138 0.9841 16.6667
0.70 5.00 - 150.00 98.686 0.000 31.734 130.419 0.9834 13.3333
0.60 5.00 - 179.00 118.423 0.000 32.459 150.882 0.9808 13.3333
0.60 5.00 - 135.00 118.423 0.000 24.480 142.903 0.9818 13.3333
0.34 5.00 - 279.00 171.329 0.000 28.669 199.998 0.9745 16.6667
Dimensi Diameter Arah X Diameter Arah Y Berat Tul. Arah X
No. Jenis Beton bxh VOLUME Bawah Atas Bawah Atas Bawah Atas
(CM) (M3) (MM) (MM) (MM) (MM) (KG/M) (KG/M)
PLAT
1 Plat atas tangga tebal 12 cm 300 x 150 x 12 0.54 8 8 10 10 0.395 0.395
2 Plat tritisan tebal 10 cm 300 x 150 x 10 0.45 0 10 0 8 0.000 0.617
3 Plat kantilever/leufel 8 cm 100 x 100 x 8 0.08 0 10 0 8 0.000 0.617
4 Pondasi telapak tebal 20 cm 60 x 60 x 20 0.07 10 10 10 10 0.617 0.617
Berat Tul. Arah Y Jarak Tulangan Panjang Tul Arah X Panjang Tul Arah Y Jumlah tulangan Berat Tul. Arah X Berat Tul. Arah Y
Bawah Atas Arah X Arah Y Bawah Atas Bawah Atas Arah X Arah Y Bawah Atas Bawah Atas
(KG/M) (KG/M) (CM) (CM) (CM) (CM) (CM) (CM) (BH) (BH) (KG) (KG) (KG) (KG)

0.617 0.617 20.0 15.0 150 75 300 150 32 22 9.474 4.877 20.354 10.317
0.000 0.395 10.0 15.0 0 170 0 300 31 11 0.000 32.505 0.000 13.027
0.000 0.395 10.0 15.0 0 110 0 100 11 8 0.000 7.463 0.000 3.026
0.617 0.617 15.0 15.0 0 70 0 60 5 5 0.000 2.159 0.000 1.850
Kebutuhan
Tulangan Beton Begisting Perancah
(KG)/M3 (M3) (M2) (M2)

83.3734 0.9894 8.3333


101.1803 0.9871 10.0000
131.1184 0.9833 12.5000
55.6820 0.9929 0.0000
A PROGRAM NASIONAL
PEMBERDAYAAN
300 150 MASYARAKAT MANDIRI
PERDESAAN

150 * KASIH IBU *


WC/KM
DUSUN TAMPES PROPINSI : NTB
DESA KAYANGAN
KABUPATEN : LOMBOK UTARA
KECAMATAN : KAYANGAN
300 R. PERIKSA/OBAT
B
DESA KAYANGAN
150

JENIS PRASARANA :
POSYANDU

LOKASI :
-
300 -
300 R. TUNGGU/PELAYANAN
-
-
-
TAMPAK DEPAN POSYANDU -
-
JUDUL GAMBAR :
30

225 150 75 - DENAH POSYANDU


- TAMPAK DEPAN POSYANDU
- TAMPAK SAMPING POSYANDU
DENAH POSYANDU

Dibuat Oleh :
TPK,

( ABDURRAHIM JUMAIDI )

Diperiksa Oleh :
FT,

( DWI OKTOHARIONO,ST )

TAMPAK SAMPING POSYANDU


Lembar Ke Dari Lembar
PROGRAM NASIONAL
PEMBERDAYAAN
MASYARAKAT MANDIRI
PERDESAAN

PROPINSI : NTB
KABUPATEN : LOMBOK UTARA
KECAMATAN : KAYANGAN

DESA KAYANGAN

Nok 8/12
Genteng Pejaten JENIS PRASARANA :
Nok 8/12
Bubungan Genteng Pejaten POSYANDU
Gording 8/12

Usuk 5/7 Gording 8/12 LOKASI :


Listplank (3/20) -
Murplat 6/12 Murplat 6/12
-
-
Pas. bata geuvel
-
Plafond Kalsiboard Plafond Kalsiboard Roster Beton (20/20) -
-
-
Beton plat leufel JUDUL GAMBAR :
290

- POTONGAN MEMANJANG POSYANDU


- POTONGAN MELINTANG POSYANDU
Rabat beton (t = 5 cm)
Pasir urug (t = 10 cm)
Pas. Bata trastram
Lantai Keramik (30x30) (1pc:3ps)
Dibuat Oleh :
15
TPK,
Pas. Batu (1pc:5ps) Tanah urug 70

20
10
30 ( ABDURRAHIM JUMAIDI )
50

Diperiksa Oleh :
FT,
POT. MELINTANG POSYANDU (A-A) POT. MEMANJANG POSYANDU (B-B)

( DWI OKTOHARIONO,ST )

Lembar Ke Dari Lembar


PROGRAM NASIONAL
PEMBERDAYAAN
300 150 Pas. Bata trastram MASYARAKAT MANDIRI
PERDESAAN
Rabat beton (t = 5 cm)

Pasir urug (t = 10 cm)

150 Lantai Keramik (30x30)


5
10 PROPINSI : NTB
KABUPATEN : LOMBOK UTARA
15
KECAMATAN : KAYANGAN
300
10

DESA KAYANGAN
150 Tanah urug
60

JENIS PRASARANA :
POSYANDU
20

10
LOKASI :
30 -
300 50 -
300
-
-
-
4 Ø 10 4 Ø 10 -
15 12 -
JUDUL GAMBAR :
15 Ø 6 - 15 cm 12 Ø 6 - 15 cm

- RENCANA PONDASI
DENAH PONDASI Rencana Sloop Rencana Kolom Praktis

4 Ø 10 4 Ø 10
12
12 Dibuat Oleh :
4 Ø 10 TPK,
15 Ø 6 - 15 cm
15 Ø 6 - 15 cm
12
Rencana Reng Balok
Rencana Balok Geuvel
20 Ø 6 - 15 cm
Plat Leufel (t=6cm) ( ABDURRAHIM JUMAIDI )
Tembok
Ø 10 - 10 Rencana Balok Latai (Gantung)
Ø 10 - 10 cm

cm
Ø 10 - 10 Diperiksa Oleh :
cm FT,
50
Ø 10 - 10 6
cm 20 15
Balok latai/Gantung
12 50
450 ( DWI OKTOHARIONO,ST )

Rencana Plat Leufel


Lembar Ke Dari Lembar
PROGRAM NASIONAL
PEMBERDAYAAN
300 150 MASYARAKAT MANDIRI
PERDESAAN
5 80 5 70 5 5 70 5
5 5 5

P1

BV
WC/KM
PROPINSI : NTB
110 KABUPATEN : LOMBOK UTARA
J2

KECAMATAN : KAYANGAN
300 R. PERIKSA/OBAT
200 200
5 DESA KAYANGAN

JENIS PRASARANA :
POSYANDU
P1J1
P1J1 (1buah) P1 (1 buah) LOKASI :
-
-
300 R. TUNGGU/PELAYANAN
-
-
5
-
-
5
-
30 JUDUL GAMBAR :
110
5

225 150 75 5 50 5
- RENCANA KUSEN

5
5 70 70 5 BV (1buah)
DENAH KUSEN

J2 (1buah) Dibuat Oleh :


TPK,

20
( ABDURRAHIM JUMAIDI )

20
Diperiksa Oleh :
FT,
Roster Beton (11 buah)

( DWI OKTOHARIONO,ST )

Lembar Ke Dari Lembar


PROGRAM NASIONAL
PEMBERDAYAAN
MASYARAKAT MANDIRI
PERDESAAN

PROPINSI : NTB
KABUPATEN : LOMBOK UTARA
KECAMATAN : KAYANGAN

DESA KAYANGAN

JENIS PRASARANA :
POSYANDU

LOKASI :
-
-
-
-
-
-
-
JUDUL GAMBAR :

TAMPAK JADI POSYANDU

Dibuat Oleh :
TPK,

( ABDURRAHIM JUMAIDI )

Diperiksa Oleh :
FT,

TAMPAK JADI POSYANDU

( DWI OKTOHARIONO,ST )

Lembar Ke Dari Lembar