208
CHAPTER - 7
BRIDGES
7.1 TYPES
Reinforced concrete is particularly well suited for use in bridges of all kinds
because of its durability, rigidity, and economy, as well as the comparative ease with
which a pleasing appearance can be achieved
FIGURE 7.1
Precast prestressed voided slab bridge.
For very short spans, from about 10 to 25 ft, one-way slab bridges are
economical. Somewhat longer spans, up to about 50 ft, can be achieved with bridges
of this same general type by fofining longitudinal voids with fiberboard tubes, thereby
reducing dead load. Figure 7.1 shows a voided slab bridge using precast elements.
Asphalt wecring
_eCement grout in keywoy
FIGURE 7.2
Precast integral-deck bridge
units: (a) voided slab;
(b) channel slab
Lntermediote tronsverse diophragmns209
Typical cross sections are shown in Fig. 7.2. Such spans are often prestressed
by pretensioned strands, and may be laterally post-tensioned after the units are placed
side by side. Such construction offers low initial cost, as a result of standardized plant
production, and is characterized by fast, easy erection and low maintenance. For
highway spans, an asphalt-wearing surface is normally applied directly to the top face
of the concrete units (Refs. 7.1 and 7.2).
FIGURE 7.3
Cast-in-place deck-grider bridge.
Cast-in-place concrete girders such as shown in Fig. 7.3 may be used for spans
up to about 100 ff, although their use is less common now than before because of the
advantages of precasting for this range of spans. For cast-in-place bridges, the
monolithic concrete deck spans as a slab transversely and also provides a broad
cOmpression flange for the main girders. Such bridges may be single span and simply
supported as shown, or continuous over two or more spans.
FIGURE 7.4
Continuous bridge using cast-in-place concrete slab composite with welded
steel griders,210
Most highway bridges in the United States of medium length, from 60 to about
120 ft, make use either of composite steel-concrete construction or composite pre-
stressed concrete construction. A continuous composite structure is shown in Fig. 7.4.
The concrete deck is made to act integrally with the steel beams through use of shear
connectors welded to the top flange of the beams and embedded in the slab. Although
such a bridge is not strictly a reinforced concrete structure, the design will be presented
in some detail in this chapter because of its widespread use. Prestressed concrete
bridges frequenfly make use of composite action also. Commonly the beams are precast
and placed in position by a crane, eliminating the need for obstructing traffic with
falsework. The deck slab is then cast in place and locked to the precast units by
stirrups that project upward into the slab. Figure 7.5 illustrates construction of this type.
FIGURE 7.5
Standard AASHTO bridge girders, precast and pretensioned, composite
with cast-in-place slab.
Requiremonts for long spans have led to the development of segmentally cast
post-tensioned prestressed concrete box-girder bridaes of the tvoe shown in Fig. 7.6
In typical construction, the work proceeds in two directions from each pier, using the
balanced cantilever method shown, and is advanced using either cast-in-place or precast
conerete units. Each is post-tensioned to the previously completed construction after
placement. Very long spans have been achieved in this way, the longest presently
(1990) being close to 1000 ft.