Professional Documents
Culture Documents
• One large open pit but with two distinct zones (East & West)
• Bulk mining approach – simple ore body, simple mining operation
Pit Design Reserves (Revenue Factor 0.84)
Initial Pushback Concept (FS Study)
Case Study: Main Drivers to Pit Sequence
• Grade of East Pit is significantly higher than West Pit Pit (1.33 vs 1.04)
• Strip ratio for East Pit is higher than West Pit (4.6 vs 3.6)
• East Pit dips to the east at around 35 degrees, which results in a
moderate increase in strip ratio with depth.
• West Pit is a relatively flat lying orebody with a less defined structure
• West Pit has been mined previously near surface, consequently has a
low initial stripping ratio.
• Oxide from the East Pit will be stockpiled for future use
• High grading policy to be used to maximise initial revenue
Case Study: Schedule Summary
Initial 15 Mt pre-strip
The approach adopted by SimSched DBS is to solve the schedule optimisation problem in a single
step and hence produce more realistic solutions. This removes the need to generate suboptimal
stage designs (pushbacks) or post process the schedule to optimise the cut-off grade strategy.
As per seen previously , there are a number of features in DBS that are significant (not discussed in
detail in this study) such as;
• Surface Base Algorithm – Avoids slope errors
• Applying geometric constraints
• Applying operational constraints, such as blending
By comparing the results from NPVS and DBS in terms of project value (NPVS) and practicality of the
mining sequence it is hoped that the value the integrated approach adopted by DBS can be
assessed.
500
NPVS Results
NPVS Results – Base Case with 9 Bench Sinking Rate and 50m Cut-width
1,000 Pit Limit
Ore Waste NPV @ 8% selected at a
450 900
Revenue factor
400 800
of 0.84
350 700
Total Rock tonnes (millions )
300 600
NPV
250 500
200 400
150 300
100 200
50 100
0 -
Revenue Factor
NPVS Sensitivity Analysis – Stages & Sink Limit
Bench Optimisation Results Percentage Gain/Loss
Max Sinking Cut-Back LG PB SCH MFO
Case Pushbacks Limit Width NPV8 NPV8 NPV8 NPV8 PB % SCH % MFO %
No Solution Found
Conclusions from NPVS Runs
• The formation of the pushbacks (stages) reduces the theoretical maximum NPV from the LG
Solution by 18 to 20 %. Note that the pushbacks are valued by assuming just in time mining.
• Scheduling of the pushbacks with the sinking rate constraint in the Scheduler (SCH) typically
reduces the NPV by a further 2 to 4%. Other scheduling constraints (objectives), such as strip
ratio, can also be defined if required. The Objective function can be NPV or one of the specified
Objectives.
• Optimising the cut-off grade in MFO (ie using stockpiles) can increase the NPV by 2 to 10%.
Highest gains are seen with more pushbacks and a smaller cut-back width.
• For the Base Case (9 bench sinking limit and 50m cut-width) the maximum NPV was 727. By
increasing the number of pushbacks to 11, and increasing the sinking rate to 13 benches/year, it
is possible to raise the NPV to 749.
• NOTE: Increasing the number of pushbacks can have a negative impact on NPV due to the
influence of the sinking rate limit. There is no advantage in increasing the number of pushbacks
beyond 13 with a 50m cut-width
Conclusions from NPVS Runs (continued)
• Reducing the cut-width to 30m means that with a 9 bench sinking limit solutions cannot
be found unless there are 13 or more pushbacks. This clearly indicates that the sinking
rate constraint is dominating the solution and in fact in some cases the production
target cannot be met and a no solution found will be found.
• The maximum NPV of 783 was achieved with 11 pushbacks and a sinking rate of 13
benches/year. This NPV is still approximately 100 less than the LG solution but
demonstrates the principles behind the constraints of sinking rate and cut-width.
Comparative Results Using SimSchedDBS
Bench Optimisation Results Gain/Loss NPVS Gain/Loss
Sinking Cut-Back Pit Base No Stocks Stocks
DBS Scenario Limit Width Width NPV8 NPV8 % NPV8 %
8/4 9 50 50 710 749 5% 727 3%
10/6 11 50 50 723 757 5% 746 1%
11/7 13 50 50 734 766 4% 749 2%
2 1
1
2
3
3 4
2
Comparison of Mining Sequences
DBS
NPVS
DBS Schedule
NPVS Schedule
Conclusions
• The overall pit size is very similar between NPVS and DBS. The DBS pit is however slightly
smaller with the pit depth reduced due to controls on pit base size.
• The evaluated project value at an 8% discount factor was within 3% when you compare
schedules. Note that you have to be careful when comparing due to how discounting is
applied in NPVS and there was also an issue at the time with reclaiming stockpiles in DBS
where they were only reclaimed after the mine was depleted.
• DBS Schedule allows the West Pit to be mined earlier which reduces the initial pre-strip
by around 10 Mt and also reduces the amount of material that is stockpiled.
• Both solutions require further manual adjustment due to isolated “fragments” that are
not practical to mine.
What Value Does DBS Add?
• The step wise solution of Whittle and NPVS can result in a significant loss in value due
to sub-optimal expansion stages (pushbacks) and excessive stockpiling after the
application of cut-off grade optimisation.
• These issues are resolved when using DBS by circumnavigating the need to design
stages and the inclusion of the time value of money and stockpiling in the Direct Block
Scheduling logic.
• DBS provides additional constraints at the pit optimisation stage such as minimum pit
bottom dimensions and blending. These will necessarily lead to alternative scheduling
solutions that are likely to increase project value.
• Running DBS alongside other solutions (Whittle, NPVS etc) provides a check method
and may highlight opportunities where there are differences.
Vision for DBS
• Simple import tools for model setup (regularised or sub-cell models)
• Intuitive interactive tools for data manipulation
• Semi-automated/intelligent tools for clean-up of DBS period stages
• Reverse engineering of mining stages
• Built in tools to deal with modelling dilution
• Integration with ramp optimisation tools (eg Minemap)
• Seamless integration with downstream scheduling tools