You are on page 1of 43
Essel Walajahpet Poonamallee Toll Roads Private Limited Site Office: Flat No 136, Casa Grande Futura, Chengelpattu Road, Sriperumbudur ~ 602105. EWPTRPL/IE-ARTEFACT/F-14/2015/262 Date: 09/07/2015, To The Acting Team Leader, M/s. Artefact Projects Limited, No.55 Kamachi Nagar, Thimmasamudram, Kanchipuram ~ 631502. ‘@: 044 - 27277550 Kind Attention: Mr. Ramesh Babu, Acting Team Leader [Sub 77] Sicianing of nica fom Walajshpe to Poonam (km 106%800 tok 13+800,Approanat | Length of 93 Km) in the State of Tamilnadu under NHDP Phase-V to be executed as DBFOT | (Toll) Project - DBM & BC Mx Design & Work Method Statement fr D8M — Reg. stat tay EEE Se eee si Dear Sir, We are herewith submitting the following reports for your review and concurrence — 1 Mix Design for Dense Bituminous Macadam (Grade |) using VG30 Bitumen from IOCL and aggregates from Madhur Crusher conducted at third party laboratory 2. Mix Design for Dense Bituminous Macadam (Grade I) using VG30 Bitumen from IOCL and ‘aggregates from Madhur Crusher conducted at third party laboratory 3. Mix Design for Bituminous Concrete (Grade Il) using CRMB 55 from HINCOL and aggregates from Madhur Crusher conducted at third party laboratory 4, Work Method Statement for Dense Bituminous Macadam This is for your kind information and necessary review at the earliest. Thanking you and assuring of our best services always. For Essel Walajahpet Poonamallee Toll Roads Pvt Ltd., Po (Ravindranath P) General Manager (Roads) Encl: As above Cc: The Project Director, NHAI, PIU. Krishnagiri Corp Office : 513/A, Sth Floor, Kohinoor City, Kirol Road, Off L. 8. S. Marg, Kurla (w), Mumbai - 400 070 Tol.: 491 22 66012323 + Fax : +91 22 66012300 + Website : www. esselinfraprojects.com SROUp Regd Office : Essel House, B-10, Lawrence Road, Industrial Area, New Delhi - 110035, INDIA ‘QUALITY MANAGEMENT SYSTEM_| ESSEL WALAJAHPET METHOD STATEMENT a POONAMALLE TOLL ROADS GROUP PVTLTD MS/ BITUMEN WORK / Rev. | Date Description of Change Review Date by No. Manager QAQC METHOD STATEMENT FOR CONSTRUCTION OF BITUMINOUS LAYERS (DBM) Prepared &Reviewed Approved by By QMC SITE Project INCHARGE NAME Y.ANJI REDDY RAVINDRANATH.P- TE SIGNATURE oe Ww ae R \ ae T ‘QUALITY MANAGEMENT SYSTEM ESSEL WALAJAHPET METHOD STATEMENT POONAMALLE TOLL ROADS 55 PVT LTD MS/BITUMEN WORK WPI GROUP zo7m oo 9 DB P CONTENTS OBJECTIVE REFERENCES PLANT AND EQUIPMENTS TOOLS MATERIALS. MIX DESIGN CONSTRUCTION OF TRIAL STRETCH PRODUCTION & TRANSPORTATION OF BITUMINOUS MIX |. ROLES & RESPONSIBILITIES DETAIL PAVING PROCEDURE FOR DBM LAYER QUALITY CONTROL AND QUALITY ASSURANCE IN CONSTRUCTION SAFETY ENVIORNMENTAL CONTROL

You might also like