Feb '07 Mar '07 Apr '07 May '07 Jun '07 Jul '07 Aug '07 Sep '07 Oct '07 Nov '07 Dec '07 Jan '08 Feb '08 Mar '08 Apr '08 May '08 Jun '08 Jul '08 Aug '08 Sep '08 Oct '08 Nov '08 Dec '08 Jan '09 Feb '09 Mar '09 Apr '09 May '09
1081 Instrument Installation 21 days 11 Aug '08 03 Sep '08
21 days Instrument Installation
1082 Implse Tube Inslattation 30 days 10 Sep '08 14 Oct '08
30 days Implse Tube Inslattation
1083 Implse Tube Pressur Test 7 days 15 Oct '08 22 Oct '08
7 days Implse Tube Pressur Test
1084 LP Steam System (ST#11) 77 days 30 Jun '08 26 Sep '08
1092 North Side Fence Area 12 days 08 Aug '08 21 Aug '08
12 days North Side Fence Area
1093 West Side Fence Area 15 days 25 Aug '08 10 Sep '08
15 days West Side Fence Area
1094 South Side Fence Area 12 days 04 Sep '08 17 Sep '08
12 days South Side Fence Area
1095 Existing Area 10 days 03 Oct '08 14 Oct '08
10 days Existing Area
1096 Cabling Work 64 days 30 Aug '08 12 Nov '08
1097 CCR / NER Internal Cable 21 days 13 Oct '08 05 Nov '08
21 days CCR / NER Internal Cable
1098 GT / HRSG Area 35 days 06 Sep '08 16 Oct '08
35 days GT / HRSG Area
1099 North Side Fence Area 37 days 30 Aug '08 11 Oct '08
37 days North Side Fence Area
1100 West Side Fence Area 27 days 17 Sep '08 17 Oct '08
27 days West Side Fence Area
1101 South Side Fence Area 30 days 20 Sep '08 24 Oct '08
30 days South Side Fence Area
1102 Existing Area 21 days 20 Oct '08 12 Nov '08
21 days Existing Area
1103 Commissioning 36 days 04 Nov '08 15 Dec '08
Page 21