You are on page 1of 1

DETALLE MIXER ZUBLIN 07/08/2017 TURNO B

Nº HR. INGR MTS. CUB. CARGA DESTINO PROCEDENCIA


1 23:32 3.5 SHOTCRETE C/F MB SUR M1
2 23:32 3.5 SHOTCRETE C/F MB SUR M1
3 1:06 3.5 SHOTCRETE C/F MB SUR CALAMA
4 1:10 3.5 SHOTCRETE C/F MB SUR CALAMA
5 1:30 3.5 SHOTCRETE BIN M1
6 1:38 3.5 SHOTCRETE BIN M1
7 2:18 3.5 SHOTCRETE BIN M1
8 4:30 3.5 SHOTCRETE MB M1
9 4:30 3.5 SHOTCRETE MB M1
10 4:46 3.5 SHOTCRETE C/F BIN CALAMA
11 4:49 3.5 SHOTCRETE C/F BIN CALAMA
12 5:08 3.5 SHOTCRETE C/F BIN CALAMA
13
14

TOTAL SHOTCRETE 24.5

17.5
TOTAL SHOTCRETE C/FIBRA
TOTAL HORMIGON 0

DETALLE MIXER ZUBLIN X BANCO 2040 A GAEBIN

SHOTCRETE X 2040 A GAEBIN 0


SHOTCRETE X 2040 A GAEBIN C/F 0
HORMIGON H35 X 2040 A GAEBIN 0