5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
Proper cleaning required and gasket shall be fixed on inner
6 windows and ventilator installation
face for waterproofing
7 Door frames Cleaning & polish final coat required
15 Electrical Wiring, Telephone cable and TV cable wirin Minor repairs & tests required
16 Electrical switch board and lights installation Minor connection settings required
Galss is brocken need to be fixed, All connection need to
17 Electrical DB be checked & Tags must be palced on each breaker plus
testing required
26 External hard lanscaping and plinth protection Crackes in palster and concrete shall be repaired properly
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
1 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (RESTAURANT)
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
2 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (GUEST HOUSE)
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
Proper cleaning required and gasket shall be
6 windows and ventilator installation
fixed on inner face for waterproofing
7 Door frames Cleaning & polish final coat required
13 Electrical Wiring, Telephone cable and TV cable wiring Minor repairs & tests required
24 Bottom khurra below rain water pipe Shall be constructed as per drawing
25 Construction of man holes and gully traps Covers shall be fixed properly
Crackes in palster and concrete shall be repaired
26 External hard lanscaping and plinth protection
properly
27 Valve on toilet supply line Gate valve shall be installed on Hot & Cold lines
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 3 / 16 CONTRACTOR: M/S MALIK M YOUNUS
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (GUEST HOUSE)
DESANG APPROVAL
SR. NoBY:
ISSUED DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
4 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (STAFF QUARTERS 1 & 2)
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
21 Bottom khurra below rain water pipe Shall be constructed as per drawing
22 Construction of man holes and gully traps Covers shall be fixed properly
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
5 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (PUBLIC TOILETS)
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
11 Electrical switch board, lights & other fixtures installation Shall be fixed properly
13 External plumbing works Gate valve shall be installed on Hot & Cold lines
15 External hard lanscaping and plinth protection Concrete on edges of Paver areas
20 Bottom khurra below rain water pipe Shall be constructed as per drawing
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
6 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (CYCLE STORE)
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
6 Electrical wiring, switch board & Fixture installation To be completed as per directions
12 Bottom khurra below rain water pipe Shall be constructed as per drawing
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
7 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (BOARDWALK)
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
4 Pebble fixing
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
8 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST (EXTERNAL DEVELOPMENTS & WORKS)
DESANG APPROVAL
SR. No POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
A EXTERNAL DEVELOPEMNTS (CIVIL WORKS)
1 Pathways ( Sandstone finishing) Reapir of cracked areas
Brocken pavers shall be replaced and sand
2 Pathways ( Paver finishing)
filling remaining
3 Bonfire
4 Sitting areas Cleaning required
ISSUED BY:
RESIDENT ENGINEER CONSULTANTS: RECEIVING:
THE URBAN UNIT G3 CONTRACTOR: M/S MALIK M YOUNUS
9 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
A RESTAURANT
5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
10 Wooden carving sections 15" x 15" on external façade Polish final coat required
15 Electrical Wiring, Telephone cable and TV cable wiring Minor repairs & tests required
16 Electrical switch board and lights installation Minor connection settings required
22 Roof treatment
10 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
11 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
B GUEST HOUSE
1 External Graffi Minor repairs required
2 Internal Graffi Minor repairs required
3 Internal flooring (Floor Tiles) Shall be cleaned properly
4 Toilets and kitchen area tile work Shall be cleaned properly
5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
Proper cleaning required and gasket shall be fixed
6 windows and ventilator installation
on inner face for waterproofing
7 Door frames Cleaning & polish final coat required
8 Door Shutters Cleaning & polish final coat required
12 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
C STAFF QUARTER-1 & 2
1 External Graffi Repair of damaged areas
2 Internal Graffi Repair of damaged areas
Shall be cleaned properly & in some areas motives
3 Internal flooring (Floor Tiles)
are missing which shall be fixed
Joint filling to be done properly & proper cleaning
4 Toilets and kitchen area tile work
required
5 Marble for Kitchen slab and door steps/threshold Edges shall be round properly and polished
Proper cleaning required and gasket shall be fixed
6 windows and ventilator installation
on inner face for waterproofing
7 Door frames Cleaning & Polish required
8 Door Shutters Cleaning & Polish required
10 Wooden carving sections 18" x 60" on external façade Polish final coat required
11 Paint work 1 Coat required
12 MS Wicket door in lawn Paint final coat required
Minor repairs & tests required & Plastic cover sheets
13 Electrical Wiring, Telephone cable and TV cable wiring
shall be fixed on all extra points
Tv sockets to be checked & 5 pin sockets shall be
14 Electrical switch board, lights & other fixtures installation
installed 1 in each room
All connection need to be checked & Tags must be
15 Electrical DB
palced on each breaker
All fixtures shall be cleaned properly & Testing
16 Internal Plumbing work in toilets and Kitchen
required
17 External plumbing works Testing required
18 Rain water pipes To be fixed properly
19 Gas pipe line Testing required
20 Roof treatment
21 Construction of man holes and gully traps Covers shall be fixed properly
22 External hard lanscaping and plinth protection Reapir of cracked areas
23 Valve on toilet supply line Shall be installed outside each toilet
13 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
D PUBLIC TOILET BLOCK
1 External Graffi Minor repairs required
Shall be cleaned properly & Joint filling to be done
2 Internal flooring (Floor Tiles)
properly
Shall be cleaned properly & Joint filling to be done
3 Internal (Wall Tiles)
properly
4 MS Grill Ventilator installation Cleaning required
5 Wire mesh (Galvanized) in ventilators Shall be fixed
6 Door frames Cleaning & Polish required
7 Door Shutters Cleaning & Polish required
8 Paint work 1 Coat required
9 Front parda wall
10 Electrical Wiring, All connection need to be checked
11 Electrical switch board, lights & other fixtures installation Shall be fixed properly
12 Internal Plumbing work in toilets Testing required
13 External plumbing works Gate valve shall be installed on Hot & Cold lines
14 Precast roof slab & Roof treatment
15 External hard lanscaping and plinth protection
16 Toilet signage plates To be fixed properly
17 Valve on toilet water supply line To be installed
18 Rain water pipes To be fixed properly
14 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
E EXTERNAL DEVELOPEMNTS (CIVIL WORKS)
1 Pathways ( Sandstone finishing) Reapir of cracked areas
Brocken pavers shall be replaced and sand filling
2 Pathways ( Paver finishing)
remaining
3 Bonfire
4 Sitting areas Cleaning required
15 / 16
DEVELOPMENT OF TOURISM FACILITIES AT KHABEKI LAKE SOON VALLEY
SNAG LIST
DESANG APPROVAL
SR. No DESCRIPTION POINTS
CONTRACTOR CONSULTANTS URBAN UNIT
G EXTERNAL ELECTRICAL WORKS
1 External Wall lights Shall be cleaned
2 External Flood lights Testing required
1: Silicone around glass shall be filled
3 External Garden pole lights
2: Graffi on concrete columns shall be done
4 Earthing To be completed as per BOQ & Drawing
5 Transformer/Meter to Main Pannel Cable laiyng Cable joints shall be done as directed
6 Main DB / Pannel with provision of 2 Connections from wapda Proper taging must be done
7 External DB for lighting,Public toilets, Store room etc Proper taging must be done
8 Main telephone DB with 50 pair connection strip Connections & Testing required
9 Main CATV DB with Cable booster & Spliters Testing required
H EXTERNAL PLUMBING WORKS
1 Sewerage line Shall be cleaned & Test required
Electrical switch must be shifted in Staff quarter near
2 Boring & installation of submersible pump
the boring
Gate valves shall be installed on Hot & Cold pipe
3 Water supply Connection to each building
lines out side of each toilet
4 Gas line piping & Connection to each kitchen & for gyser Testing required
5 Drinking Water supply piping from R.O plant to Each kitchen Testing required
6 Submersible Sluge pump & 400 feet waste pipe
I R.O PLANT
1 Concrete pad for R.O plant
2 Installation of R.O Plant Delivered at site Installation remaining
3 O.H tank (As per BOQ) Required to be installed
J BOARDWALK
Some portions specially on both end required to be
1 Toe walls
redone due to settlement cracks
Concrete at the edges required at some portions &
2 Paver laying
Cleaning required
3 Pebble fixing
4 Sitting area concrete Pads Reapir of cracked areas reuired
5 Concrete patterns on walking track Repair on edges required
6 Storm water Drain Plater repair required at some areas
7 Levelling dressing on lake side Some portions required to be redone
Required to be fixed properly with MS angle & rawal
8 Fixing of concrete benches with floor
bolts
9 Installtion of Dustbins Some Dustins missing
Removal & refixing of tuff pavers on the pathway from guest house
10 Sand filling in gaps required
to boardwalk'
All kiosks shall be connected properly with electrical
11 Wiring for Electrical poles & Kiosks
DB
12 External DB installation MS Grill shall be fixed for safety
13 Garden light poles Silicone around glass shall be filled
14 Sumpits & uPVC pipe installation Required to be done at designated places
K ENTRANCE BOARD
1 Sandstone cladding Replace the broken tiles
2 Paint in engraved writting
3 Pad arround the Signage Concrete around shall be laid properly
16 / 16