INSTITUTE OF TECHNOLOGY, MADRAS 60 036 DEC. 27-20,
09
Losses in Distribution Transformers and
Benefits in Restructuring
with Amorphous Core Technology
V.V. Kamaraj, B. Jayadey
Abstract“Uhe study chiefly emphasizes on the losses in
distribution Transformers due to their ageing and out
dated, ergo technology. The subsequent cost benefits, If
adopt the latest technology, that is is amorphous core
transformers in a phased manner. The study reveals
that losses are reduced to 68 percent, if existi
transformers are replaced with amorphous core.
paper also discusses the technical feasibility and
financial viability of implementing amorphous core
transformers in the Distribution Network and scope of
its implementation.
Keywords: Aging, Amorphous materials, Costs,
jon, Losses, Transformers, Transformer Core,
1. INTRODUCTION
cla power generated in Andhra Pras Sate i
"T2s6s2 nega anim) in Then tl and wind
Gove the over generated bil bet HRV level
andisboowed up o220K or 100K ands tasted
Ton dances before reaching theta consume. They
we
1 Primary Tansson
2. Secotary Tans
3. Primary Disibuton
£:Sccnay Dsbution
The ata power wil a be ized due to ansmison
anddstibuton loses. There va igh power las in adi
The le a adn poser lisa ish computed to
ilematosl standard What sore during th in
tree wend of tose
According to 1999-2000 statistics the “Transmission &
Distribution losses was found to be 43 percent in Andhra
Pradesh,
The losses ean be categorized as line losses, equipment
losses and losses due to pilferage. In equipment, the loss
due to transmission transformers that is the power trans.
EA. Author is studying MuceNsecond semester) at University of
Jodhpur c-naitkamarahearsareiffinail om
'SB.Author is working asa Assstnt Divisional Engineer for East
power Distribution company of Andhra Pradesh Limite.
formers is major and is negligible. When compared to the
number of distribution transformers. Sines
distribution transformers is very large in any state through
‘out the country and hence a small increase in loss due to
distribution transformers multiples the total losses and the
net power loss in T&D system inereases enormously. The
‘worldwide studies at present chiefly concentrate to reduce
losses.
the number of
New thoughts and researches are going on in_ various as-
peets like power equipment, conductor technology.
The new development in transformer design is _amor-
phous core transformer
IL FACTORS RESPONSIBLE FOR HIGH DISTRIBUTION
Losses
According to a study conducted by world bank energy
experts in 1982 two principal reasons account for high dis
tribution losses in developing counties like India,
1. First the selling price of electricity has failed to keep
pace with rate of increase in cost of supply
2. Reason for high distribution losses is that power utili-
ties designed their distribution networks with high
percentage voltage regulation and coupled with low
power factor, will suffer high percentage loss. We are
all awate of simple formula that percentage power
Joss is equal to percentage voltage regulation at unity
power factor.
Statistics says that one unit saved is 1.25 unit produced.
Hence the very purpose of this paper is to emphasize on the
actual power loss occurring in distribution transformers,
which helps in Energy Auditing.
AP. Transco in recent years incorporated the technology
of amorphous core transformers, in the distribution ne
works. Their implementation in place of conventional
CRGO steel brings down, the no load losses in transform=
ers reducing to 68 percent, Out ofthe total transformers ex-
isting today, the share of amorphous core transformers. is
about 4.4 percent. Presently, any state electricity board in
India is trying to decrease their T&D losses, which is the
chief cause for decrease in their efficiency. Statistics of
T&D losses of various states are given in table 170
[NATIONAL POWER SYSTEMS CONFERENCE. NPSC 2004
TL AMORPHOUS CORE TECHNOLOGY
Amorphous metals are alloys having composition of Iron,
Boron and Silicon elements, these metals have no atomic
‘order. They lack symmetrical structure or form, Their
amorphous nature has given them the name, metallic
glasses, yet their unusual atomic order sets them apart from
‘conventional metallic materials. Rapid cooting of molten
‘metals prevents crystallization and leaves a vitrified solid
‘with structure in form of thin strips-a perfect energy saving
substitute for ergo.
Comparison of properties of amorphous metal and CRGO.
steel is given in table 2
ILL, PROPERTIES THAT MAKE
MANUFACTURING PROCESS OF AMORPHOUS METALS
DIFFERENT FROM CRGO STE! CORE.
1. Amorphous metals are harder. The Amorphous Core
‘Transformers are thus stronger, more-corrosion resis-
tant and. long lasting.
2. Unlike CRGO, Amorphous metals are thin,
3. Amorphous metals require magnetic field annealing
4,After annealing process material becomes less due-
tile.
TV, PLUS POINTS ON PERFORMANCE
By keeping performance parameters like load loss, im-
pedance and temperature rise constant. Amorphous core
‘transformers have 32 pereent of core loss. When compared
to that of, 68 percent in ergo transformer. A Comparative
no load loss specification list of ergo and amorphous core
‘on basis of kilo Volt Ampere (kwva) rating is given in
table}
1. Much lower noise level and reduced operating tem
perature leading to long. economic life of transformer
are benefits of amorphous core distribution trans-
formers.
2. ‘The required lower excitation current, which reduces
xkvar demand, also reducing further generating capac-
ity, leads to reduction in ine losses.
3. Rate of rise of temperature for the amorphous trans-
former is very low. When compared to ergo trans-
formers.
4. Failure rate ofthese transformer is 0.2 percent, out of
ten thousand transformers, as reported by Orissa
GRIDCO state electricity board,
‘There are however certain limitations like requirement of
special tools for cutting. Because of high hardness of mate-
rial, low saturation flux density and availability in only
small seetions (thickness and width) and requirement of
‘magnetic field annealing, These limitations restrict the use
‘of amorphous cores only to distribution transformers.
Amorphous raw material is imported from USA and the
quantity of metal, required for manufacturing any rating of
distribution transformer, is considerably, larger than that of
CRGO silicon steel core transformer itis because of these
reasons the cost is about 25percent higher than that of con-
ventional CRGO transformer. Although, the high initial
cost may appear to be a damper in first instance, the cost
benefit analysis study has revealed that the break even pe-
riod for extra expenditure vis-a-vis energy saved is within a
period of about 7 years and thereafter there is a perpetual
energy saving. Thus, there is an urgent need for gradual in-
duction of these distribution transformers, in the power
distribution networks,
\V. COST BENEFITS EVALUATED BY REPLACEMENT
OF AMORPHOUS TRANSFORMERS
Losses in distribution system should be valued at long run
marginal cost (LRMC) for bulk supply. This is the key
point in economic analysis, in other words, we treat it ex-
actly ike incremental load andlor it will reduce the cost of
future bulk supply. LRMC is basicaly isthe economic cost
of producing electricity at a bulk supply level and it has @
structure. What we look at is the need for decreased losses,
because the reduction in losses will increase the ability to
serve more ineremental load at improved reliability, With
this saving, we do not have to build, many installations to
‘meet the bulk supply requirements in future. As our distri-
bution loses have been reduced.
Ifwe can estimate the value of losses through the structure
of long run marginal costs of bulk supply we ean have peak
kilowatt cost, peak energy cost and off peak energy cost
‘This isa fairly a simple breakdown. There are other types of
structuring that are possible, which are more sophisticated.
‘But the important point is thatthe losses at peak are going
to be very large.
As per the manufactures guaranteed technical specifica-
tions the no load loss ofa 100 kilo volt ampere (kva), amor-
phous core transformer is 60 watts and no load loss of a
100. kilo volt ampere (kva), ergo core transformer is. 185
watts
Energy saving of no load loss, when 100 no's of 100 kilo
volt Ampere (kva) ergo transformers replaced with amor-
phous core:
(185-60)
CSC -100=00125 mega watt (MW)
‘The effective amount of generation capacity saved at the
distribution transformer terminals. considering, T&D loss
in power system is 30 percent (as per the 1999-2000 statis
fics T&D loss of most power utilities in more than this).INDIAN INSTITUTE OF TECHNOLOGY, MADRAS 600 036 DEC. 27-30
on
012s
BOTS _ (017857 mega watt (MW) 1
oF -ga watt (MW) a
Saving of energy in KW
= 17.857 0 I8kW 2
Saving of energy for one complete day is
18x24 = 432kilo watt-hour (kwh). 8)
Cost of energy for one day assuming LRMC @ 3Rs per
kilo watt hour (kWh) is 432x3=Rs 1296. a
Cost of energy per annun
196x365 =473040 (5)
Cost of installing a generating capacity of IMega Watt
(mv) is 5 crores approximately
IMegawatt Serores
For 0.01785 Mega Watt = Rs 892500 (6)
Using (5) we caleulated
the total saving = 892500~473040
= Rs 13,65,540
Cost of an amorphous core transformer is Rs 98,489,
Cost of 100 numbers of 100 Kilo Volt- Ampere (kva) amor-
phous core transformer is. Rs 9848900,
‘The return of investment spent for replacement of 100
numbers of 100 Kilo Volt-Ampere (kva) transformer
would be in 7 years approximately.
‘The above is only a conservative estimate, The cost of in-
stalling a generating capacity in only taken, But, after in-
cluding the cost of transmitting and distributing. This
break-even period would come down, For maintaining the
transformer in proper operating c ws thought the
year, all power uilties are incur crores of rupees of expen-
dditure every year. This is not taken into account, Once @
new transformer is purchased, the manufacturer gives a
guarantee on it for a period of 5 years from date of pur-
chase.
IV.ACase Srupy
‘A. study has been done in operation circle of
visakhapatnam by taking the installed capacity of trans
formers and conducting a sample study on 5 percent of
transformers of installed capacity.
‘The study mainly focuses on the no load losses in distribu.
tion transformers, For instance in operation circle of
visakhapatnam of Andhra pradesh. There are about4985
transformers the details of the installed capacity are given
in tabled,
Based on the statistics available the details of the installed
capacity as on 17-10-89 given in tableS were taken into the
account of ageing.
Transformers installed prior to 1980 are repeatedly failing
and the repairs involve huge expenditure. After testing for
no load losses an abnormal deviation from manufactures
specification of about 20-25percent was observed
‘VIL EFFECT OF AGEING
In older transformers ageing of core plates taken place.
‘This is due to the material of laminations and results in in-
creased iron loss and rising temperature ofthe transformer.
This may eventually lead to partial or complete destruction
of the coil, insulation and sludging of the oil
Selecting a random sampling size of approximately
‘percent in the installed capacity of capacity kilo volt am-
pere (kya) of distribution transformers in operation circle
Visakhapatnam. As per the manufactures guaranteed tech-
nical specifications the maximum permissible no load loss
(of 100 kilo volt ampere (kva) ergo core transformers is 260
Watts
Maximum permissible no load loss of 63 kilo volt ampere
(kva) ergo core transformer is 140Watts
Whether are the deviation from maximum permissible
limits of guaranteed technical specification can be ob-
served from table 6and table?
As per the sample test conducted the no load loss of 100
Kilo volt ampere (kva) transformers for sample size230
transformers is found to be 250
‘As per the sample test conducted the average iron loss of
68 Kilo volt-ampere (KVA) transformers for sample size
67 transformers is found to be 175.
‘This may be true for 20 to 30percent of transformers in the
field as it may not be possible to test cach and every trans-
former-So replacement in phased manner is beneficial
VIII. REPLACEMENT OF TRANSFORMERS
IN PHASED MANNER AND REMEDIAL MEASURES
Some of the suggestions thought to be feasible are as fol-
ows
TPhase
1. All 100 kilovolt ampere (kva) transformers. very
badly affected with bulk loads and H.T, loads in city,
areas should be replaced with amorphous core trans~
formers for this study purpose,
I Phase
2. ‘The removed 100kilo volt ampere (kva) transformers
should replace 63 kilo volt ampere (kva) transformers,
that are in worst conditions in rural areas, where there
would be low load factor. In the latter case every