069 069 Tunel "Cortanovc

i"
20/09/2017 Eur=119.00
Rezija = Y

UKUPNI TROSKOVI
P O Z I C I J E

601 RADOVI U OTVORENOM


------------------------
6001 Iskop 2-3kat u otvorenom m3 2390.00 7.86 18,778
6002 Iskop 2-3 kat portal m3 780.00 7.86 6,128
6003 Podnoz beton 10cm C16/20 m3 240.00 75.98 18,234
6004 Temelj C25/30 m3 2892.00 98.67 285,350
6005 Tunelska konstruk C25/30 m3 3743.00 120.02 449,231
6052 Armatura temelji kg 381830.00 0.96 365,209
6006 Armatura konstrukcija kg 258500.00 0.96 247,248
6007 Beton oko tunela C25/30 m3 1095.00 93.40 102,268
6008 Pesacke staze C25/30 m3 411.00 111.11 45,666
6009 Nasipanje iznad tunela m3 16700.00 4.13 68,967
Svega: 1,607,079
602 DRENAZA I HIDROIZOLACIJA
------------------------
6010 Drenaza cev PVC 200 m1 507.00 20.32 10,303
6011 Izolacija tunela spolja m2 6410.00 13.71 87,896
6012 Zastita hidroizol C25/30 m3 620.00 160.14 99,286
6013 Drenaza PVC 150 m1 387.00 8.76 3,389
Svega: 200,874
603 MONTAZNI ELEMENTI
------------------------
6014 Montazne kanelete tip A m1 254.00 33.27 8,450
6015 Montazne kanelete tip B m1 254.00 55.10 13,996
6016 Montazni poklopci C35/40 kom 507.00 10.99 5,574
Svega: 28,020
604 TUNELSKI IASKOP
------------------------
6047 Kartiranje sum 1.00 109250.00 109,250
6017 Iskop tunela m3 185920.00 19.84 3,688,278
6018 Rusenje betonskih sipova m3 545.00 65.39 35,637
Svega: 3,833,165
605 OSIGURANJE ISKOPA-PRIMAR
------------------------
6019 Prskani beton d20 C25/30 m3 10785.00 174.85 1,885,762
6020 Prskani beton d30 C25/30 m3 22941.00 174.85 4,011,243
6021 Armatura kg 1728295.00 0.96 1,653,063
6022 Celicni lukovi tip 50 kg 239632.00 1.41 337,116
6023 Celicni lukovi IPB160 kg 4322931.00 1.41 6,081,528
6024 Prskani beton d10 C25/30 m3 18086.00 174.85 3,162,345
6025 Armatura kg 511545.00 0.96 489,278
6027 Sidra od fiberglasa 32mm m1 74256.00 7.64 567,678
6028 Kisobran fi 114 l=12m m1 148176.00 50.02 7,411,676
6026 Ankeri 32 4m kom 294.00 77.79 22,869
6048 Ankeri 32 6m samobuseci kom 34437.00 79.90 2,751,583
6049 Ankeri 32 4m samobuseci kom 178.00 59.63 10,613
6050 Mikrosipovi 38mm 5m kom 21818.00 79.90 1,743,300
6051 Zast iskopa koloid silik m1 11400.00 97.75 1,114,350
6029 Rastvor silike lit 152000.00 1.84 279,680
Svega: 31,522,085
606 DRENAZA I HIDROIZOLACIJA
------------------------
6030 Drenaza PVC 200 m1 4105.00 29.62 121,574
6031 Unutrasnja hidroizolac m2 50694.00 13.71 695,130
Svega: 816,704
607 SEKUNDARNA KONSTRUKCIJA
------------------------
6032 Unutr obloga 30cm C25/30 m3 17492.00 120.02 2,099,371
6033 Temelj obloge C25/30 m3 11532.00 98.67 1,137,850
6034 Armatura za konstrukciju kg 1146097.00 0.96 1,096,208
6035 Armatura temelji kg 1054863.00 0.96 1,008,945
6036 Celicni lukovi tip 100 kg 1173456.00 1.62 1,902,182
6037 Podnozni svod C25/30 m3 9132.00 98.67 901,044
6038 Pesacke staze C25/30 m3 3568.00 126.21 450,318
Svega: 8,595,918
608 MONITORING
------------------------
6039 Monitornig sum 1.00 120750.00 120,750
Svega: 120,750
609 MONTAZNI ELEMENTI
------------------------
6040 Montazne kanelete tip A m1 2025.00 33.27 67,366
6041 Montazne kznalete tip B m1 2025.00 55.10 111,583
6042 Poklopci za hidrant cevi kom 4050.00 12.27 49,694
6043 Poklop nisa 94x50 C35/45 kom 164.00 12.27 2,012
6044 Poklop niza 114x70C35/45 kom 30.00 12.27 368
6045 Poklop ploce prola 46x50 kom 106.00 12.27 1,301
Svega: 232,324
610 RAZNI RADOVI
------------------------
6046 Nadzor projektanski sum 1.00 402.50 403
Svega 403

Ukupno 46,957,322