Jindal Power Ltd (4X600MW)

C&I Commissioning/Protocol/FSSS/13

C&I Plant Interlock & Protection


Unit#2 Boiler FSSS Purpose:- Purge Permissive Date:-

Purge Permissive
Parameter Reqd Status Set Simulation Status Remarks
Value By
All PA Fans OFF
LOTV Closed
All Elevation All LONV Closed
All Feeders OFF
All Hot Air Gates Closed
All Elevations Discr No Flame
Scanners
All Elevations Fireball No Flame
Scanners
All Auxiliary Air Modulating
Dampers
Total Air Flow > 30% 100% = Total Air Flow at MCR =
< 40% Tph
No Boiler Trip A,B&C True MFT condition not present (but MFT
Not reset)
MFT DPU not Forzen
NOTE: Purge Timer = 9 minutes, Post-Trip Purge Timer = 5 minutes.

Post Purge trip


Parameter Simulation By Status Remarks

Post Purge trip FD B As per logic sheet of FSSS purge


Post Purge trip ID B permissive
Remarks:-

BHEL Representative C&I Erection Mech Commissioning C&I Commissioning


Name:-
Sign:-
Date:-