TIME SCHEDULE BARGING

NO BARGE : IV ( to PT VIT )
BARGE : Confirm
TUG BOAT : Confirm
LOADING POINT : JETTY PT.INTEGRA MINING NUSANTARA

NO TANGGAL JAM URAIAN KEGIATAN KETERANGAN

1 Sabtu, 22 Desember 2018 6:00:00 -


Barge Long Side to Jetty PT. INTEGRA MINING NUSANTARA
7:00:00 - Prepare to loading

Minggu, 23 Desember 2017 - Comenes Loading Barge


loading Estimed : 6500 MT
9:00:00 - Start Loading Barge
Source Cargo :
BCS-PIT 1 : OG/23-24 & BCS 06,BCS 07 - Jarak 1,0 - 2,0 Km
BCS-PIT 2 : E1 - Jarak 0,0 - 1,0 Km

3 Minggu, 23 Desember 2017 2:00:00 - Stop Loading-Day 1

8:00:00 - Continue Loading Barge - Day 2


Source Cargo :
BCS-PIT 1 : BCS 09,BCS 04 - Jarak 1,0 - 2,0 Km
BCS-PIT 2 : E1 , E2 - Jarak 0,0 - 1,0 Km

2:00:00 - Stop Loading-Day 2

4 Senin, 24 Desember 2017 - Continue Loading Barge - Day 3


Source Cargo :
8:00:00 - Until End

BCS-PIT 1 : BCS 04 - Jarak 1,0 - 2,0 Km


BCS-PIT 2 : E5 - Jarak 0,0 - 1,0 Km

Unit Alat Berat :


- Excavator Tipe PC 200 : 4 Unit
- Complete Loading Barge - Excavator Tipe PC 300 : 1 Unit
- Final Draft Barge ( Surveyor )
Unit Alat Angkut :
No Type Dump Truck
- Dump Truck FUSO / NISSAN Kapasitas 17 - 18 Ton : 8 Unit
4 Selasa, 04 Desember 2018 - Document Process
- Cash Off Barge
- Close Estimasi Ritasi 340 6500 MT

- Data Dome Terlampir

- Waktu merupakan estimasi,waktu di sesuai dengan situasi dan kondisi