Electricity Operator

Current (A) KWH per unit Cost /hour Salary Bottles /month Cost / Bottle
15 3.3 50 PKR 165.00 PKR 20,000 16,400 PKR 1.22

Material
203
Cycle Time
Cycle (sec) No. of bottle/ hr
18 200.00

Monthly Production hour (Mini)


No. of Hour 10 2,000
PKR 1,650
Material
Weight (gm) Cost / Bottle
15 PKR 3.05

Electric PKR 0.83


Labour PKR 1.22
Total PKR 5.09
Cycle Time
Cycle (sec) No. of bottle/ hr
21 171.43

Monthly Production hour (Half)


No. of Hour 42 7,200
PKR 6,930
Material
Weight (gm) Cost / Bottle
41 PKR 8.32

Electric PKR 0.96


Labour PKR 1.22
Total PKR 10.51
Cycle Time
Cycle (sec) No. of bottle/ hr
30 120.00

Monthly Production hour (1 kg )


No. of Hour 60 7,200
PKR 9,900
Material
Weight (gm) Cost / Bottle
60 PKR 12.18

Electric PKR 1.38


Labour PKR 1.22
Total PKR 14.77