You are on page 1of 40

Tabel Isian

( Ruas Jalan Tol Pemata

Tahun 2016
SPP Tanggal
No Jumlah Luas UGK Pencairan
No SPP Tanggal SPP (BUJT)
Bidang (m2) (Rp)
1
2
3
4
5
6

Total
Tabel Isian Dana Talangan
Tol Pematang Panggang - Kayuagung )

Retur Realisasi
Jumlah Luas Nominal Tanggal Jumlah Luas UGK
Bidang (m2) (Rp) Retur Bidang (m2) (Rp)
Provinsi
Tanggal Pembayaran
Tahun 2017

PPK I
SPP
No Jumlah Luas
No SPP Tanggal SPP
Bidang (m2)
1 TN.02.06/440357/046-157 29 Desember 2016 61 520,986
2 TN.02.06/440357/BS-081 15 Maret 2017 3 268,755
3 TN.02.06/015415/BS-139 29 Mei 2017 7 38,036
4 TN.02.06/015415/BS-143 02 Juni 2017 114 875736
5 TN.02.06/015415/BS-199 31 Juli 2017 32 157,057
6 TN.02.06/015415/BS-199.1 31 Juli 2017 13 63,073
7 TN.02.06/015415/BS-201.1 02 Agustus 2017 42 317,030
8 TN.02.06/015415/BS-201.2 02 Agustus 2017 7 86,440
9 TN.02.06/015415/BS-203 04 Agustus 2017 1 1,840
10 TN.02.06/015415/BS-203.1 04 Agustus 2017 2 178,316
11 TN.02.06/015415/BS-206 07 Agustus 2017 119 558,180
12 TN.02.06/015415/BS-234 04 September 2017 1 647,299
13 TN,02,06/015415/BS-238 06 September 2017 177 747,821
14 TN.02.06/015415/BS-266 06 Oktober 2017 2 10,634
15 TN.02.06/015415/BS-266.1 06 Oktober 2017 2 16,363
16 TN.02.06/015415/BS-280 20 Oktober 2017 18 103,804
17 TN.02.06/015415/BS-280.1 20 Oktober 2017 17 69,900
18 TN.02.06/015415/BS-280.2 20 Oktober 2017 3 2,134
19 TN.02.06/015415/BS-280.3 20 Oktober 2017 6 16,330
20 TN.02.06/015415/BS-297 06 November 2017 2 426,430
Total 629 5,106,164

PPK II
SPP
No Jumlah Luas
No SPP Tanggal SPP
Bidang (m2)
1 TN.02.06/440357/047-075 08 Februari 2017 53 538,612

2 TN.02.06/015415/BT-348 04 Mei 2017 2 41,765

3 TN.02.06/015415/BT-407 23 Mei 2017 26 1,097,015


4 TN.02.06/015415/BT-409 23 Mei 2017 57 293,972
5 TN.02.06/015415/BT-457 05 Juni 2017 15 268,215
6 TN.02.06/015415/BT-458 05 Juni 2017 28 228,202
7 TN.02.06/015415/BT-519 14 Juni 2017 31 34,041
8 TN.02.06/015415/BT-520 14 Juni 2017 80 109,983
9 TN.02.06/015415/BT-521 14 Juni 2017 39 196,315
10 TN.02.06/015415/BT-609 07 Juli 2017 1 4
11 TN.02.06/015415/BT-610 07 Juli 2017 2 22,759
12 TN.02.06/015415/BT-611 07 Juli 2017 3 8,264
13 TN.02.06/015415/BT-612 07 Juli 2017 2 92,067
14 TN.02.06/015415/BT-628 13 Juli 2017 4 3,596
15 TN.02.06/015415/BT-660 20 Juli 2017 5 14,991
16 TN.02.06/015415/BT-628.1 31 Juli 2017 16 93,959
17 TN.02.06/015415/BT-762 10 Agustus 2017 1 104,323
18 TN.02.06/015415/BT-849 30 Agustus 2017 1 102,240
19 TN.02.06/015415/BT-1179 03 November 2017 1 196
20 TN.02.06/015415/BT-1198 08 November 2017 1 400
21 TN.02.06/015415/BT-1216 14 November 2017 62 167,249
22 TN.02.06/015415/BT-1261.4 29 November 2017 3 1,751
23 TN.02.06/015415/BT-1295.2 04 Desember 2017 2 12,358
Total 431 3,317,083

Total 1,495 11,855,524


Tabel Isian Dana Talangan
( Ruas Jalan Tol Pematang Panggang - Kayuagung )

Retur
UGK Tanggal Pencairan (BUJT) Jumlah Luas Nominal Tanggal Jumlah
(Rp) Bidang (m2) (Rp) Retur Bidang
20,479,849,933 23 Februari 2017 61
14,670,422,757 04 April 2017 3
1,858,941,959 10 Agustus 2017 7
32,736,734,595 10 Agustus 2017 114
13,557,292,240 30 Agustus 2017 32
2,987,356,489 30 Agustus 2017 13
11,625,664,916 30 Agustus 2017 42
6,845,749,100 30 Agustus 2017 7
81,411,411 18 September 2017 1
7,425,211,566 18 September 2017 2
47,382,185,884 30 Agustus 2017 119
41,641,677,646 28 September 2017 1
53,603,250,652 05 Oktober 2017 177
459,258,076 26 Oktober 2017 2
698,938,973 26 Oktober 2017 2
4,127,590,005 10 November 2017 18
3,152,786,879 10 November 2017 17
80,955,220 10 November 2017 3
1,309,804,542 10 November 2017 6
4,194,535,771 23 November 2017 2
268,919,618,614 - - - - 629

Retur
UGK Tanggal Pencairan (BUJT) Jumlah Luas Nominal Tanggal Jumlah
(Rp) Bidang (m2) (Rp) Retur Bidang
22,910,242,335 53
1,664,590,130 20 Juni 2017 2
44,829,030,394 20 Juni 2017 26
15,338,775,930 20 Juni 2017 56 289,618 9,001,631,540 57
13,313,885,135 13 Juli 2017 15
21,117,911,294 13 Juli 2017 28
7,752,869,345 10 Agustus 2017 1 196 43,197,008 31
20,661,573,795 10 Agustus 2017 80
41,756,539,757 10 Agustus 2017 39
881,572 21 Juli 2017 1
2,614,722,812 10 Agustus 2017 2
1,884,791,456 10 Agustus 2017 3
4,987,226,545 21 Agustus 2017 2
682,605,964 21 Agustus 2017 4
1,031,950,777 21 Agustus 2017 5
10,783,907,125 23 Agustus 2017 16
3,242,468,379 12 September 2017 1
3,174,548,825 29 September 2017
43,197,008 28 November 2017 1
29,667,590 08 Desember 2017
28,002,657,595 08 Desember 2017 62
276,371,608 15 Desember 2017 3
383,715,516 27 Desember 2017
246,440,933,879 57 289,814 9,044,828,548 431

761,844,683,380 114 579,628 18,089,657,096 1,491


Realisasi
Luas UGK Provinsi
Tanggal Pembayaran
(m2) (Rp)
520,986 20,479,849,933 08 Maret 2017 SUMSEL
268,755 14,670,422,757 04 Mei 2017 SUMSEL
38,036 1,858,941,959 30 Agustus 2017 SUMSEL
875736 32,736,734,595 30 Agustus 2017 SUMSEL
157,057 13,557,292,240 03 Oktober 2017 SUMSEL
63,073 2,987,356,489 31 Agustus 2017 SUMSEL
317,030 11,625,664,916 12 September 2017 SUMSEL
86,440 6,845,749,100 03 Oktober 2017 SUMSEL
1,840 81,411,411 17 Oktober 2017 SUMSEL
178,316 7,425,211,566 17 Oktober 2017 SUMSEL
558,180 47,382,185,884 12 September 2017 SUMSEL
647,299 41,641,677,646 12 Oktober 2017 SUMSEL
747,821 53,603,250,652 17 Oktober 2017 SUMSEL
10,634 459,258,076 02 November 2017 SUMSEL
16,363 698,938,973 02 November 2017 SUMSEL
103,804 4,127,590,005 28 November 2017 SUMSEL
69,900 3,152,786,879 28 November 2017 SUMSEL
2,134 80,955,220 27 November 2017 SUMSEL
16,330 1,309,804,542 28 November 2017 SUMSEL
426,430 4,194,535,771 22 Desember 2017 SUMSEL
5,106,164 268,919,618,614

Realisasi
Luas UGK Provinsi
Tanggal Pembayaran
(m2) (Rp)
538,612 22,910,242,335 06 April 2017 SUMSEL
41,765 1,664,590,130 21 Juni 2017
SUMSEL
1,097,015 44,829,030,394 21 Juni 2017 SUMSEL
4,354 6,337,144,390 19 Juli 2017 SUMSEL
268,215 13,313,885,135 31 Juli 2017 SUMSEL
228,202 21,117,911,294 31 Juli 2017 SUMSEL
33,855 7,752,869,345 22 Agustus 2017 SUMSEL
109,983 20,661,573,795 23 Agustus 2017 SUMSEL
196,315 41,756,539,757 22 Agustus 2017 SUMSEL
4 881,572 21 Juli 2017 SUMSEL
22,759 2,614,722,812 22 Agustus 2017 SUMSEL
8,264 1,884,791,456 22 Agustus 2017 SUMSEL
92,067 4,987,226,545 21 Agustus 2017 SUMSEL
3,596 682,605,964 21 Agustus 2017 SUMSEL
14,991 1,031,950,777 21 Agustus 2017 SUMSEL
93,959 10,783,907,125 23 Agustus 2017 SUMSEL
104,323 3,242,468,379 13 September 2017 SUMSEL
3,174,548,825 29 September 2017 SUMSEL
196 43,197,008 28 November 2017 SUMSEL
29,667,590 08 Desember 2017 SUMSEL
167,249 28,002,657,595 12 Desember 2017 SUMSEL
1,751 276,371,608 15 Desember 2017 SUMSEL
383,715,516 27 Desember 2017 SUMSEL
3,027,475 237,482,499,347

11,161,114 743,884,617,308
Ta
( Ruas Jalan T

Tahun 2018

PPK I
SPP
No Jumlah Luas UGK
No SPP Tanggal SPP
Bidang (m2) (Rp)
1 TN.02.06/015415/BS-033 2-Feb-18 4 77,625 1,413,669,524
2 TN.02.06/015415/BS-066 7-Mar-18 2 162,188 1,944,582,828
3 TN.02.06/015415/BS-119 4-May-18 3 65,640 791,630,164
Total 9 305,453 4,149,882,516

PPK II
SPP
No Jumlah Luas UGK
No SPP Tanggal SPP
Bidang (m2) (Rp)
1 TN.02.06/015415/BT-1368 28-Dec-17 56 289,618 9,001,631,540

2 TN.02.06/015415/BT-34 5-Jan-18 2 638,771 2,919,118,377

3 TN.02.06/015415/BT-291 22-Feb-18 27 45,858 7,815,157,072


4 TN.02.06/015415/BT-414.2 29-Mar-18 1 241 38,534,201
5 TN.02.06/015415/BT-418 29-Mar-18 1 1,151 206,481,285
6 TN.02.06/015415/BT-460 23-Apr-18 23 35,603 6,074,376,244
7 TN.02.06/015415/BT-466 28-Apr-18 51 124,537 22,037,628,206
8 TN.02.06/015415/BT-511 4-May-18 8 13,482 2,417,006,243
9 TN.02.06/015415/BT-515 4-May-18 1 458 72,755,411
10 TN.02.06/015415/BT-581 31-May-18 1 2,382 373,270,303
11 TN.02.06/015415/BT-704 4-Jul-18 3 5,329 934,916,550
Total 116 229,041 42,889,243,892

TOTAL KESELURUHAN

TOTAL 2017 + 2018


Tabel Isian Dana Talangan
( Ruas Jalan Tol Pematang Panggang - Kayuagung )

Retur Realisasi
Tanggal Pencairan
(BUJT) Jumlah Luas Nominal Tanggal Jumlah Luas
Bidang (m2) (Rp) Retur Bidang (m2)
23 Februari 2018 3 65,640 791,630,164 1 11,985
26 Maret 2018 2 162,188
25 Mei 2018 3 65,640
3 65,640 791,630,164 - 6 239,813

Retur Realisasi
Tanggal Pencairan
(BUJT) Jumlah Luas Nominal Tanggal Jumlah Luas
Bidang (m2) (Rp) Retur Bidang (m2)
15 Januari 2018 289,618
31 Januari 2018

13 Maret 2018 27 45,858


26 April 2018 1 241
26 April 2018 1 1,151
16 Mei 2018 23 35,603
16 Mei 2018 51 124,537
25 Mei 2018 8 13,482
25 Mei 2018 1 458
28 Juni 2018 1 2,382
23 Juli 2018 3 5,329
- - - 116 518,659

758,472

11,919,586
Realisasi
UGK Provinsi
Tanggal Pembayaran
(Rp)
622,039,360 15-Mar-18 SUMSEL
1,944,582,828 10-Apr-18 SUMSEL
791,630,164 25-May-18 SUMSEL
3,358,252,352

Realisasi
UGK Provinsi
Tanggal Pembayaran
(Rp)
9,001,631,540 15-Jan-18 SUMSEL

2,919,118,377 31-Jan-18 SUMSEL

7,815,157,072 20-Mar-18 SUMSEL


38,534,201 26-Apr-18 SUMSEL
206,481,285 26-Apr-18 SUMSEL
6,074,376,244 16-May-18 SUMSEL
22,037,628,206 16-May-18 SUMSEL
2,417,006,243 25-May-18 SUMSEL
72,755,411 25-May-18 SUMSEL
373,270,303 28-Jun-18 SUMSEL
934,916,550 24-Jul-18 SUMSEL
51,890,875,432
Tabel Isian Dana Talangan
( Ruas Jalan Tol Pematang Panggang - Kayuagung )

Tahun 2017
PPK I
PANJANG SPP
No STA Jumlah Luas UGK Tanggal Pencairan (BUJT) Tanggal Pembayaran Keterangan
No SPP Tanggal SPP
Bidang (m2) (Rp)
1 - TN.02.06/440357/046-157 29 Desember 2016 61 520,986 20,479,849,933 23 Februari 2017 08 Maret 2017

2 138+850 - 141+100 2,250 TN.02.06/440357/BS-081 15 Maret 2017 3 268,755 14,670,422,757 04 April 2017 04 Mei 2017

3 151+450 - 152+300 850 TN.02.06/015415/BS-139 29 Mei 2017 7 38,036 1,858,941,959 10 Agustus 2017 30 Agustus 2017

4 131+150 - 138+850 7,700 TN.02.06/015415/BS-143 02 Juni 2017 114 875736 32,736,734,595 10 Agustus 2017 30 Agustus 2017

5 121+400 - 122+950 1,550 TN.02.06/015415/BS-199 31 Juli 2017 32 157,057 13,557,292,240 30 Agustus 2017 03 Oktober 2017

6 - - TN.02.06/015415/BS-199.1 31 Juli 2017 13 63,073 2,987,356,489 30 Agustus 2017 31 Agustus 2017

7 122+950 - 125+500 2,550 TN.02.06/015415/BS-201.1 02 Agustus 2017 42 317,030 11,625,664,916 30 Agustus 2017 12 September 2017

8 112+400 - 113+200 800 TN.02.06/015415/BS-201.2 02 Agustus 2017 7 86,440 6,845,749,100 30 Agustus 2017 03 Oktober 2017

9 114+700 - 114+750 50 TN.02.06/015415/BS-203 04 Agustus 2017 1 1,840 81,411,411 18 September 2017 17 Oktober 2017

10 113+200 - 114+700 1,500 TN.02.06/015415/BS-203.1 04 Agustus 2017 2 178,316 7,425,211,566 18 September 2017 17 Oktober 2017

11 125+500 - 131+150 5,650 TN.02.06/015415/BS-206 07 Agustus 2017 119 558,180 47,382,185,884 30 Agustus 2017 12 September 2017

12 145+650 - 151+450 5,800 TN.02.06/015415/BS-234 04 September 2017 1 647,299 41,641,677,646 28 September 2017 12 Oktober 2017

13 114+750 - 121+400 6,650 TN,02,06/015415/BS-238 06 September 2017 177 747,821 53,603,250,652 05 Oktober 2017 17 Oktober 2017

14 - - TN.02.06/015415/BS-266 06 Oktober 2017 2 10,634 459,258,076 26 Oktober 2017 02 November 2017

15 - - TN.02.06/015415/BS-266.1 06 Oktober 2017 2 16,363 698,938,973 26 Oktober 2017 02 November 2017

16 - - TN.02.06/015415/BS-280 20 Oktober 2017 18 103,804 4,127,590,005 10 November 2017 28 November 2017

17 - - TN.02.06/015415/BS-280.1 20 Oktober 2017 17 69,900 3,152,786,879 10 November 2017 28 November 2017

18 - - TN.02.06/015415/BS-280.2 20 Oktober 2017 3 2,134 80,955,220 10 November 2017 27 November 2017

19 - - TN.02.06/015415/BS-280.3 20 Oktober 2017 6 16,330 1,309,804,542 10 November 2017 28 November 2017

20 - - TN.02.06/015415/BS-297 06 November 2017 2 426,430 4,194,535,771 23 November 2017 22 Desember 2017

Total 629 5,106,164 268,919,618,614

PPK II
SPP
No Jumlah Luas UGK Tanggal Pencairan (BUJT) Tanggal Pembayaran Keterangan
No SPP Tanggal SPP
Bidang (m2) (Rp)
1 TN.02.06/440357/047-075 08 Februari 2017 53 538,612 22,910,242,335 06 April 2017
2 TN.02.06/015415/BT-348 04 Mei 2017 2 41,765 1,664,590,130 20 Juni 2017 21 Juni 2017
3 TN.02.06/015415/BT-407 23 Mei 2017 26 1,097,015 44,829,030,394 20 Juni 2017 21 Juni 2017
Retur 56 Bdg
4 TN.02.06/015415/BT-409 23 Mei 2017 57 293,972 15,338,775,930 20 Juni 2017 19 Juli 2017 Luas 289.618 m2
Rp 9.001.631.540,-
5 TN.02.06/015415/BT-457 05 Juni 2017 15 268,215 13,313,885,135 13 Juli 2017 31 Juli 2017
6 TN.02.06/015415/BT-458 05 Juni 2017 28 228,202 21,117,911,294 13 Juli 2017 31 Juli 2017
Retur 1 Bidang
7 TN.02.06/015415/BT-519 14 Juni 2017 31 34,041 7,752,869,345 10 Agustus 2017 22 Agustus 2017 Luas 196 m2
Rp 43.197.008,-
8 TN.02.06/015415/BT-520 14 Juni 2017 80 109,983 20,661,573,795 10 Agustus 2017 23 Agustus 2017
9 TN.02.06/015415/BT-521 14 Juni 2017 39 196,315 41,756,539,757 10 Agustus 2017 22 Agustus 2017
10 TN.02.06/015415/BT-609 07 Juli 2017 1 4 881,572 21 Juli 2017 21 Juli 2017
11 TN.02.06/015415/BT-610 07 Juli 2017 2 22,759 2,614,722,812 10 Agustus 2017 22 Agustus 2017
12 TN.02.06/015415/BT-611 07 Juli 2017 3 8,264 1,884,791,456 10 Agustus 2017 22 Agustus 2017
13 TN.02.06/015415/BT-612 07 Juli 2017 2 92,067 4,987,226,545 21 Agustus 2017 21 Agustus 2017
14 TN.02.06/015415/BT-628 13 Juli 2017 4 3,596 682,605,964 21 Agustus 2017 21 Agustus 2017
15 TN.02.06/015415/BT-660 20 Juli 2017 5 14,991 1,031,950,777 21 Agustus 2017 21 Agustus 2017
16 TN.02.06/015415/BT-628.1 31 Juli 2017 16 93,959 10,783,907,125 23 Agustus 2017 23 Agustus 2017
17 TN.02.06/015415/BT-762 10 Agustus 2017 1 104,323 3,242,468,379 12 September 2017 13 September 2017
18 TN.02.06/015415/BT-849 30 Agustus 2017 1 102,240 3,174,548,825 29 September 2017 29 September 2017
19 TN.02.06/015415/BT-1179 03 November 2017 1 196 43,197,008 28 November 2017 28 November 2017
20 TN.02.06/015415/BT-1198 08 November 2017 1 400 29,667,590 08 Desember 2017 08 Desember 2017
21 TN.02.06/015415/BT-1216 14 November 2017 62 167,249 28,002,657,595 08 Desember 2017 12 Desember 2017
22 TN.02.06/015415/BT-1261.4 29 November 2017 3 1,751 276,371,608 15 Desember 2017 15 Desember 2017
23 TN.02.06/015415/BT-1295.2 04 Desember 2017 2 12,358 383,715,516 27 Desember 2017 27 Desember 2017
Total 431 3,317,083 246,440,933,879

Total 1,495 11,855,524 761,844,683,380

Tahun 2018
PPK I
SPP
No Jumlah Luas UGK Tanggal Pencairan (BUJT) Tanggal Pembayaran Keterangan
No SPP Tanggal SPP
Bidang (m2) (Rp)
Retur 3 Bidang
1 TN.02.06/015415/BS-033 2-Feb-18 4 77,625 1,413,669,524 23 Februari 2018 15-Mar-18 Luas 65.640 m2
Rp 791.630.164
2 TN.02.06/015415/BS-066 7-Mar-18 2 162,188 1,944,582,828 26 Maret 2018 10-Apr-18
3 TN.02.06/015415/BS-119 4-May-18 3 65,640 791,630,164 25 Mei 2018 25-May-18
Total 9 305,453 4,149,882,516

PPK II
SPP
No Jumlah Luas UGK Tanggal Pencairan (BUJT) Tanggal Pembayaran Keterangan
No SPP Tanggal SPP
Bidang (m2) (Rp)
TN.02.06/015415/BT-1368 56 289,618 9,001,631,540 15 Januari 2018 konsinyasi (retur) untuk bidang
1 28-Dec-17 15-Jan-18 include di SPP No.409

Pengajuan SPP Pajak untuk Bidang


2 TN.02.06/015415/BT-34 5-Jan-18 2 638,771 2,919,118,377 31 Januari 2018 31-Jan-18 dan Luas Include di SPP No.407

3 TN.02.06/015415/BT-291 22-Feb-18 27 45,858 7,815,157,072 13 Maret 2018 20-Mar-18


4 TN.02.06/015415/BT-414.2 29-Mar-18 1 241 38,534,201 26 April 2018 26-Apr-18
5 TN.02.06/015415/BT-418 29-Mar-18 1 1,151 206,481,285 26 April 2018 26-Apr-18
6 TN.02.06/015415/BT-460 23-Apr-18 23 35,603 6,074,376,244 16 Mei 2018 16-May-18
7 TN.02.06/015415/BT-466 28-Apr-18 51 124,537 22,037,628,206 16 Mei 2018 16-May-18
8 TN.02.06/015415/BT-511 4-May-18 8 13,482 2,417,006,243 25 Mei 2018 25-May-18
9 TN.02.06/015415/BT-515 4-May-18 1 458 72,755,411 25 Mei 2018 25-May-18
10 TN.02.06/015415/BT-581 31-May-18 1 2,382 373,270,303 28 Juni 2018 28-Jun-18
11 TN.02.06/015415/BT-704 4-Jul-18 3 5,329 934,916,550 23 Juli 2018 24-Jul-18
Total 116 229,041 42,889,243,892

TOTAL KESELURUHAN
R
Rua

YANG BELUM DIVERIFIKASI BPKP 1 APRIL 2018 S.D. 5 DESEMBER 2018

SPP
No Jumlah Luas
No SPP Tanggal SPP
Bidang (m2)
1 TN.02.06/015415/BS-119 4-May-18 3 65,640
Total 3 65,640
Rekonsiliasi Data Dana Talangan Tahun 2018
Ruas Jalan Tol Pematang Panggang - Kayuagung I

ESEMBER 2018

Retur
UGK Tanggal Pencairan (BUJT) Jumla Luas Nominal
h
(Rp) Bidang (m2) (Rp)
791,630,164 25 Mei 2018
791,630,164 - - -
Realisasi
Tanggal Jumlah Luas UGK Tanggal Provinsi
Pembayara
Retur Bidang (m2) (Rp) n
3 65,640 791,630,164 25-May-18 SUMSEL
- 3 65,640 791,630,164
Rek
Ruas

YANG BELUM DIVERIFIKASI BPKP 1 APRIL 2018 S.D. 5 DESEMBER 2018


SPP
No Jumlah Luas
No SPP Tanggal SPP
Bidang (m2)
1 TN.02.06/015415/BT-414.2 29-Mar-18 1 241
2 TN.02.06/015415/BT-418 29-Mar-18 1 1,151
3 TN.02.06/015415/BT-460 23-Apr-18 23 35,603
4 TN.02.06/015415/BT-466 28-Apr-18 51 124,537
5 TN.02.06/015415/BT-511 4-May-18 8 13,482
6 TN.02.06/015415/BT-515 4-May-18 1 458
7 TN.02.06/015415/BT-581 31-May-18 1 2,382
8 TN.02.06/015415/BT-704 4-Jul-18 3 5,329
Total 89 183,183
Rekonsiliasi Data Dana Talangan Tahun 2018
Ruas Jalan Tol Pematang Panggang - Kayuagung II

ESEMBER 2018
Retur
UGK Tanggal Pencairan (BUJT) Jumla Luas Nominal
h
(Rp) (m2) (Rp)
Bidang
38,534,201 26 April 2018
206,481,285 26 April 2018
6,074,376,244 16 Mei 2018
22,037,628,206 16 Mei 2018
2,417,006,243 25 Mei 2018
72,755,411 25 Mei 2018
373,270,303 28 Juni 2018
934,916,550 23 Juli 2018
32,154,968,443 - - -
Realisasi
Tanggal Provinsi
Tanggal Jumlah Luas UGK
Pembayara
Retur Bidang (m2) (Rp)
n
1 241 38,534,201 26-Apr-18 SUMSEL
1 1,151 206,481,285 26-Apr-18 SUMSEL
23 35,603 6,074,376,244 16-May-18 SUMSEL
51 124,537 22,037,628,206 16-May-18 SUMSEL
8 13,482 2,417,006,243 25-May-18 SUMSEL
1 458 72,755,411 25-May-18 SUMSEL
1 2,382 373,270,303 28-Jun-18 SUMSEL
3 5,329 934,916,550 24-Jul-18 SUMSEL
89 183,183 32,154,968,443
Luas (m2) Bobot (%)

Total Lahan (exc Tambahan ROW dan RA) 11,978,440.00


Sudah Bebas (incl Konsinyasi) 11,919,586.00 97.293
Plasma Nuftah (blm bebas) 58,854.00 0.480
Konsinyasi (Bebas) 541,490.00 4.420
Sudah Bebas ( Excl Konsinyasi) 11,378,096.00 92.873
Tambahan ROW dan RA 272,779.09 2.227

Total Luas Lahan + Tambahan ROW dan RA 12,251,219.09


Luas Lahan PPK I 5,581,967
luas fasum 235,990
Luas tanpa fasum 5,345,977
Total Bebas + Fasum 5,581,967
Total Bebas non fasum 5,345,977
Total Tambahan Luas ROW 172,640

Luas Lahan PPK II 3,661,390


Luas fasum 56,402
Luas tanpa fasum 3,604,988
Luas Belum Bebas (Plasma) 58,854
Total Bebas + Fasum 3,602,536
Total Bebas non fasum 3,546,134 9,184,503
Total Tambahan luas ROW 100,139 272,779.09

Total Luasan tambahan ROW 9,516,136


Total Luasan non tambahan ROW 9,243,357 2.8664899552
Total Luasan Tanpa Fasum 8,950,965
Total Luasan Konsinyasi 541,490

Bobot Bebas + fasum 0.99363 99.382


Bobot Bebas - fasum 0.99342
96.515
Bobot Bebas + fasum + tambahan ROW 96.51504
Bobot Bebas - fasum + tambahan ROW 93.44245

9,457,282.09

Bobot bebas diluar Konsinyasi 90.825


bobot Tambahan ROW (belum bebas) 2.866
Bobot Konsinyasi 5.690 96.515
Plasma (belum bebas) 0.618
100.000
PEMBAYARAN DANA TALANGAN TANAH
Ruas Pematang Panggang - Kayu Agung
Sampai tanggal : 22 Februari 2018
#REF!
PPK PENGADAAN TANAH JALAN TOL PEMATANG PANGGANG - KAYUAGUNG I

No. Nama Desa SPP No. Tanggal SPP UGR (Rp.) M2 Jumlah Pencairan Realisasi
Bidang BUJT ke warga

1
Sedyo Mulyo TN.02.06/440357/046-157 29/12/2016 20,479,849,933 520,986 61 23/02/2017 08/03/2017
2 Gedung Rejo & Sedyo Mulyo TN.02.06/440357/BS-081 15/03/2017 14,670,422,757 268,755 3 04/04/2017 04/05/2017
3 Tanjung Sari II TN.02.06/015415/BS-139 29/05/2017 1,858,941,959 38,036 7 10/08/2017 30/08/2017
32,736,734,595
Gedung Rejo 02/06/2017 17,327,558,555 421,057 63
4 TN.02.06/015415/BS-143 02/06/2017
Kemang Indah 9,666,485,325 286,337 30 10/08/2017 30/08/2017
Rotan Mulya 02/06/2017 5,742,690,715 168,342 21
5 Mekar Wangi TN.02.06/015415/BS-199 31/07/2017 13,557,292,240 157,057 32 30/08/2017 03/10/2017
6 Tanjung Sari II TN.02.06/015415/BS-199.1 31/7/2017 2,987,356,489 63,073 13 30/08/2017 31/08/2017
7 Balian Makmur TN.02.06/015415/BS-201.1 02/08/2017 11,625,664,916 317,030 42 30/08/2017 12/09/2017
8 Sungai Sodong TN.02.06/015415/BS-201.2 02/08/2017 6,845,749,100 86,440 7 30/08/2017 03/10/2017
9 Suka Mukt TN.02.06/015415/BS-203 04/08/2017 81,411,411 1,840 1 18/09/2017 17/10/2017
10 Sungai Sodong TN.02.06/015415/BS-203.1 04/08/2017 7,425,211,566 178,316 2 18/09/2017 17/10/2017
11 Mataram Jaya TN.02.06/015415/BS-206 07/08/2017 47,382,185,884 558,180 119 30/08/2017 12/09/2017
12 Tanjung Sari II TN.02.06/015415/BS-234 04/09/2017 41,641,677,646 647,299 1 28/09/2017 12/10/2017
13 Suka Mukt TN,02,06/015415/BS-238 06/09/2017 53,603,250,652 747,821 177 05/10/2017 17/10/2017
14 Suka Mukt TN.02.06/015415/BS-266 06/10/2017 459,258,076 10,634 2 02/11/2017 02/11/2017
15 Mataram Jaya TN.02.06/015415/BS-266.1 06/10/2017 698,938,973 16,363 2 02/11/2017 02/11/2017
16 20/10/2017
Sungai Sodong TN.02.06/015415/BS-280 4,127,590,005 103,804 18 09/11/2017 28/11/2017
17 Mataram Jaya TN.02.06/015415/BS-280.1 20/10/2017 3,152,786,879 69,900 17 09/11/2017 28/11/2017
18 Suka Mukt TN.02.06/015415/BS-280.2 20/10/2017 80,955,220 2,134 3 09/11/2017 27/11/2017
19 Suka Mukt TN.02.06/015415/BS-280.3 20/10/2017 1,309,804,542 16,330 6 09/11/2017 28/11/2017
20 09/11/2017
Tanjung Sari II TN.02.06/015415/BS-297 4,194,535,771 426,430 2 23/11/2017 Proses
21 Sungai Sodong TN.02.06/015415/BS-033 02/02/2018 1,413,669,524 77,625 4 23/02/2018
22 Sungai Sodong TN.02.06/015415/BS-066 07/03/2018 1,944,582,828 162,188 2 26/03/2018
23 TN.02.06/015415/BS-119 04/05/2018 791,630,164 65,640 3 25/5/2018 25/05/2018
TOTAL SPP 272,277,870,966 5,345,977 635
TOTAL PEMBAYARAN 272,277,870,966 5,345,977 635
17,821,105,888 34051
PPK PENGADAAN TANAH JALAN TOL PEMATANG PANGGANG - KAYUAGUNG II

No. Nama Desa SPP No. Tanggal SPP UGR (Rp.) M2 Jumlah Pencairan Realisasi
Bidang BUJT ke warga

1 Cinta Jaya TN.02.06/440357/047-075 08/02/2017 22,910,242,335 538,612 53 06/04/2017


2 Cinta Jaya TN.02.06/015415/BT-348 04/05/2017 1,664,590,130 41,765 2 20/06/2017 21/06/2017
Cinta Jaya / Kedaton 44,829,030,394
3 Cinta Jaya TN.02.06/015415/BT-407 23/05/2017 39,273,094,289 973,848 19 20/06/2017 21/06/2017
Kedaton 5,555,936,105 123,167 7
4 Cinta Jaya TN.02.06/015415/BT-409 23/05/2017 15,338,775,930 293,972 57 20/06/2017 19/07/2017 JUMLAH TOTAL
5 Cinta Jaya TN.02.06/015415/BT-457 05/06/2017 13,313,885,135 268,215 15 13/07/2017 31/07/2017
6 Kedaton TN.02.06/015415/BT-458 05/06/2017 21,117,911,294 228,202 28 13/07/2017 31/07/2017
7 Kutaraya TN.02.06/015415/BT-519 14/06/2017 7,752,869,345 33,855 31 10/08/2017 22/08/2017
8 Perigi TN.02.06/015415/BT-520 14/06/2017 20,661,573,795 109,983 80 10/08/2017 23/08/2017
9 Kayu Agung TN.02.06/015415/BT-521 14/06/2017 41,756,539,757 196,315 39 10/08/2017 22/08/2017
10 Kayu Agung TN.02.06/015415/BT-609 07/07/2017 881,572 4 1 21/07/2017
11 Kedaton TN.02.06/015415/BT-610 07/07/2017 2,614,722,812 22,759 2 10/08/2017 22/08/2017
12 Perigi TN.02.06/015415/BT-611 07/07/2017 1,884,791,456 8,264 3 10/08/2017 22/08/2017
13 Cinta Jaya TN.02.06/015415/BT-612 07/07/2017 4,987,226,545 92,067 2 21/08/2017
682,605,964
14 Perigi 504,583,894 3,196 3 21/08/2017 Konsinyasi
TN.02.06/015415/BT-628 13/7/2017
Kayuagung 178,022,070 400 1 Konsinyasi
10,783,907,125
Cinta Jaya 914,963,950 29,438 1 Konsinyasi
15 Kutaraya 318,801,155 2,012 2 Konsinyasi
TN.02.06/015415/BT-628.1 31/7/2017 23/08/2017
Perigi 6,735,341,246 44,065 8 Konsinyasi
Kayuagung 2,814,800,774 18,444 5 Konsinyasi
1,031,950,777
Kedaton 374,540,853 11,441 1
16
Perigi TN.02.06/015415/BT-660 20/7/2017 80,861,559 259 2 21/08/2017
Kayuagung 576,548,365 3,291 2
17 Kedaton TN.02.06/015415/BT-762 10/08/2017 3,242,468,379 104,323 1 12/09/2017 13/09/2017
Konsinyasi (Pembayaran
18 Cinta Jaya TN.02.06/015415/BT-849 30/08/2017 3,174,548,825 102,240 1 Kekurangan nilai UGK ) untuk
29/09/2017 bidang dan luas include di SPP
No.407

19 Kutaraya TN.02.06/015415/BT-1179 03/11/2017 43,197,008 196 1 28/11/2017 konsinyasi (retur)

Konsinyasi (kekurangan UGK)


20 Kayuagung TN.02.06/015415/BT-1198 08/11/2017 29,667,590 400 1 08/12/2017 untuk bidang dan luas include di
SPP No.628
21 Arisan Buntal TN.02.06/015415/BT-1216 14/11/2017 28,002,657,595 167,249 62 08/12/2017 12/12/2017
22 Arisan Buntal TN.02.06/015415/BT-1261.4 29/11/2017 276,371,608 1,751 3 15/12/2017 15/12/2017
23 Cinta Jaya TN.02.06/015415/BT-1295.2 04/12/2017 383,715,516 12,358 2 27/12/2017 UGK pada 27/12/17 include di
SPP No.407

24 Cinta Jaya TN.02.06/015415/BT-1368 28/12/2017 9,001,631,540 289,618 56 15/01/2018 konsinyasi (retur) untuk bidang
include di SPP No.409
Pengajuan SPP Pajak untuk
25 Cinta Jaya TN.02.06/015415/BT-34 05/01/2018 2,919,118,377 638,771 2 31/01/2018 Bidang dan Luas Include di SPP
No.407
26 Arisan Buntal TN.02.06/015415/BT-291 22/02/2018 7,815,157,072 45,858 27 13/03/2018
6,074,376,244 35,607 23
29 Arisan Buntal TN.02.06/015415/BT-460 23/04/2018 5,247,432,045 30,939 21 16/05/2018
Kijang Ulu 826,944,199 4,668 2
30 Cinta Jaya TN.02.06/015415/BT-34 05/01/2018 2,919,118,377 638,771 2 23/02/2018 31/01/2018
32 Arisan Buntal TN.02.06/015415/BT-291 22/02/2018 7,815,157,072 45,858 27 13/03/2018 13/03/2018
34 Arisan Buntal TN.02.06/015415/BT-414.2 29/03/2018 38,534,201 241 1 26/04/2018 26/04/2018
35 Arisan Buntal TN.02.06/015415/BT-418 29/03/2018 206,481,285 1,151 1 26/04/2018 26/04/2018
37 Arisan Buntal & Kijang ulu TN.02.06/015415/BT-466 28/04/2018 22,037,628,206 124,537 51 16/05/2018 16/05/2018
Bidang Tanggal
Luas Total Total Luas Fasum Luas Konsinyasi Bobot
No KELURAHAN / DESA Sta Bidang Bidang Konsinyasi Konsinyasi
(m2) Luas Realisasi Fasum (m2) (m2) (%)
Total Realisasi (m2) Bobot (%) STA Bebas

A. Kecamatan Mesuji
1 Ds. Sungi Sodong 108+600 114+700 724,484 51 51 608,373 100 18 116,111 3 65640 9.06 108+600 sd 110+150 ???
110+150 sd 111+550 28 Maret 2018
111+550 sd 112+400 09 November 2017
112+400 sd 113+200 30 Agustus 2017
113+200 sd 114+700 18 September 2017
2 Ds. Suka Mukt 114+700 121+400 798,997 208 208 778,759 100 19 20,238 3 2134 0.27 114+700 sd 114+750 18 September 2017
114+750 sd 121+400 05 oktober 2017
3 Ds. Mekar Wangi 121+400 122+950 160,766 35 35 157,057 100 3 3,709 121+400 sd 122+950 30 Agustus 2017
B. Kecamatan Mesuji Raya
1 Ds. Balian Makmur 122+950 125+550 326,959 52 52 317,030 100 10 9,929 122+950 sd 125+500 30 Agustus 2017
2 Ds. Mataram Jaya 125+550 131+150 667,646 159 159 644,443 100 21 23,203 125+500 sd 131+500 30 Agustus 2017
3 Ds. Kemang Indah 131+150 133+550 293,491 39 39 286,337 100 9 7,154 131+500 sd 133+550 10 Agustus 2017
4 Ds. Rotan Mulya 133+550 135+100 177,822 26 26 168,342 100 5 9,480 133+550 sd 135+100 10 Agustus 2017
5 Ds. Gedung Rejo 135+100 139+850 556,628 82 82 533,279 100 18 23,349 135+100 sd 139+850 10 Agustus 2017
6 Ds. Sedyo Mulyo 139+850 145+650 700,336 79 79 677,519 100 16 22,817 139+850 sd 141+100 04 April 2017
141+100 sd 145+650 23 Februari 2017
C. Kecamatan Lempuing Jaya
1 Ds. Tanjung Sari II 145+650 155+500 1,174,838 23 23 1,174,838 100 - - 13 63,073 5.37 145+650 sd 151+450 28 September 2017
151+450 sd 152+300 10 Agustus 2017
152+300 sd 155+500 23 November 2017

SUB TOTAL 5,581,967 754 754 5,345,977 100 119 235,990 19 130,847 2.34

Bidang
Total Bobot
Bobot thd Luas Konsinyasi
No KELURAHAN / DESA Sta Luas Total Bidang Luas Fasum Bidang Konsinyasi
(m2)
Konsinyasi
Total Realisasi Luas Ri Luas fasum (%)
%
A. Kecamatan Pedamaran

1 Ds. Cinta Jaya 155+500 174+064 1,022,544 186 186 998,912 100.0 24 23,632 65 386,777 37.82 155+500 sd 158+700 20 Juni 2017
158+700 sd 164+100 06 April 2017
164+100 sd 164+890 13 Juli 2017
164+890 sd 165+100 20 Juni 2017
165+100 sd 166+400 13 Juli 2017

166+400 sd 167+200 21 Agustus 2017


167+200 sd 174+064 20 Juni 2017

B. Kecamatan Pedamaran +
Kayuagung

Desa Cintajaya, Suka Damai,


1 Seinant 1,245,000 1,239,005 100.0 13 5,995

2 Kel. Kedaton 174+064 178+821 551,719 46 45 489,892 89.3 5 2,973 1 466 0.08 174+064 sd 174+400 20 Juni 2017
174+400 sd 174+850 Menunggu Lahan Pengganti
174+850 sd 175+650 20 Juni 2017
175+650 sd 176+350 13 Juli 2017
176+350 sd 177+310 12 September 2017
177+310 sd 177+450 20 Juni 2017
177+450 sd 177+850 13 Juli 2017
177+850 sd 178+000 10 Agustus 2017
178+000 sd 178+821 13 Juli 2017
C. Kecamatan Kayuagung

1 Kel. Kutaraya 178+821 179+132 36,063 34 34 36,063 100.0 - - 1 196 0.54 178+821 sd 178+920 13 Juli 2017
178+920 sd 179+132 10 Agustus 2017
2 Kel. Perigi 179+132 180+591 169,185 100 100 165,767 100.0 4 3,418 2 130 0.08 179+132 sd 179+840 10 Agustus 2017
179+840 sd 180+000 23 Agustus 2017
180+000 sd 180+591 10 Agustus 2017
3 Kel. Kayuagung 180+591 182+500 221,525 53 53 218,454 100.0 5 3,071 5 19,595 8.85 18+591 sd 182+500 10 Agustus 2017
D. Kecamatan Kayuagung

1 Desa Arisan Buntal Tahap I 182+500 184+850 185,953 71 71 169,000 100.0 6 16,953 182+500 sd 184+075 08 Desember 2017

184+075 sd 184+675 13 Maret 2018

2 Desa Arisan Buntal Tahap II 49,992 31 31 49,632 100.0 1 360 2 3,479 6.96

158,474 76 76 158,474 100.0 - -

3 Desa Kijang Ulu 184+850 185+600 20,935 10 10 20,935 100.0 - -

SUB TOTAL 3,661,390 607 606 3,546,134 99.84 58 56,402 76 410,643 11.22

Penambahan Lahan ROW 272,799 - 0


Overpass dan Rest Area

JUMLAH TOTAL

Ruas Pematang Panggang -


Kayuagung 108+600 185+600 9,516,156 1,361 1,360 8,892,111 96.515 177 292,392 95 541,490 5.69
LOKASI LAHAN BEBAS S.D. 1 SEPTEMBER 2017

No STA PANJANG (M) TANGGAL PENCAIRAN BUJT NO SPP

1 108+600 - 111+000 2,400 kawasan hutan produksi


2 112+400 - 113+200 800 30 Agustus 2017 BS 201.2
3 121+400 - 122+950 1,550 30 Agustus 2017 BS 199

4 122+950 - 125+500 2,550 30 Agustus 2017 BS 201.1

5 125+500 - 126+650 1,150 30 Agustus 2017 BS 206


127+225 - 128+850 1,625 30 Agustus 2017 BS 206
129+800 - 131+150 1,350 30 Agustus 2017 BS 206
6 131+150 - 138+850 7,700 10 Agustus 2017 BS 143
7 138+850 - 141+100 2,250 04 April 2017 BS 081
8 141+100 - 145+650 4,550 23 Februari 2017 46-157
9 151+450 - 152+300 850 10 Agustus 2017 BS 139
10 155+500 158+050 2,550 20 Juni 2017 BT 409 (RETUR)

11 158+050 - 158+700 650 20 Juni 2017 BT 407


12 158+700 - 164+100 5,400 06 April 2017 047-075

13 164+100 - 164+890 790 13 Juli 2017 BT 457


14 164+890 - 165+100 210 20 Juni 2017 BT 407
15 165+100 - 166+400 1,300 13 Juli 2017 BT 457

16 166+400 - 167+200 800 21 Agustus 2017 BT 612


17 167+200 - 174+400 7,200 20 Juni 2017 BT 407
18 174+850 - 175+650 800 20 Juni 2017 BT 407
19 175+650 176+350 700 13 Juli 2017 BT 458
20 177+310 - 177+450 140 20 Juni 2017 BT 407
21 177+450 177+850 400 13 Juli 2017 BT 458
22 177+850 - 178+000 150 10 Agustus 2017 BT 610
23 178+000 178+920 920 13 Juli 2017 BT 458

24 178+920 - 179+025 105 10 Agustus 2017 BT 519


25 179+025 - 179+100 75 10 Agustus 2017 BT 611
26 179+100 - 179+355 255 10 Agustus 2017 BT 519&520
27 179+355 - 179+620 265 10 Agustus 2017 BT 520
28 179+620 - 179+840 220 10 Agustus 2017 BT 519
29 179+840 - 180+000 160 23 Agustus 2017 BT 628,1
30 180+000 - 180+600 600 10 Agustus 2017 BT 520
31 180+600 - 182+475 1,875 10 Agustus 2017 BT 521
TOTAL 52,340
BOBOT 67.97%
LOKASI LAHAN BELUM BEBAS S.D. 1 SEPTEMBER 2017

No STA PANJANG (M) TANGGAL PENCAIRAN BUJT NO SPP KETERANGAN

1 111+000 - 111+550 550 28 Maret 2018 BS 066 ###

2 111+550 - 112+400 850 09 November 2017 BS 280 ###


###
3 113+200 - 114+700 1,500 18 September 2017 BS 203.1 ###
4 114+700 - 114+750 50 18 September 2017 BS 203 ###
5 114+750 - 121+400 6,650 05 Oktober 2017 BS 238 ###
6 126+650 - 127+225 575 09 November 2017 BS 280.1 ###
7 128+850 - 129+800 950 02 November 2017 BS 266.1 ###
8 145+650 - 151+450 5,800 28 September 2017 BS 234 ###

###
9 152+300 - 155+500 3,200 23 November 2017 BS 297
10 174+400 - 174+850 450 MENUNGGU LAHAN PENGGANTI ###

###
10 176+350 - 177+310 960 12 September 2017 BT 762
11 182+475 - 182+700 225 08 Desember 2017 BT 1216 ###
12 182+700 - 184+075 1,375 08 Desember 2017 BT 1216 ###

###
13 184+075 - 184+675 600 13 Maret 2018 BT 1261,1
14 184+675 185+600 925 ###
TOTAL 24,660 ###
BOBOT 32.03% ###
###

LAHAN BELUM BEBAS UNTUK PEKERJAAN VAKUM & PRELOADING S.D. 1 SEPTEMBER 2017

No STA PANJANG (M) TANGGAL PENCAIRAN BUJT NO SPP SOIL IMPROVEMENT

1
2
3 111+000 - 111+550 550 28 Maret 2018 BS 066 VAKUM
4 111+550 - 111+950 400 09 November 2017 BS 280 VAKUM
5 118+700 - 119+550 850 05 Oktober 2017 BS 238 PRELOADING
6 120+000 - 120+400 400 05 Oktober 2017 BS 238 PRELOADING
7 120+441 - 120+500 59 05 Oktober 2017 BS 238 PRELOADING
8 120+600 - 120+875 275 05 Oktober 2017 BS 238 PRELOADING
9 148+600 - 151+450 2,850 28 September 2017 BS 234 VAKUM
10 152+300 - 155+500 3,200 23 November 2017 BS 297 VAKUM

11 160+650 - 160+875 225 konsinyasi 047-075 VAKUM


12 180+275 - 180+650 375 konsinyasi BT 520 VAKUM
13 183+530 - 184+075 545 8-Dec-17 BT 1216 VAKUM
14 184+075 - 184+675 600 13-Mar-18 BT 1261.4 VAKUM
15 184+675 - 185+099 424 SPP DAN VALIDASI VAKUM
###
TOTAL 10,753 ###
REKAPITULASI LOKASI PEMBEBASAN LAHAN BERDASARKAN TANGGAL UGK

No STA PANJANG (M) TANGGAL PENCAIRAN BUJT NO SPP

108+600 - 111+000 2,400 kawasan hutan produksi


1 0+000 ### 0+000 - 30 Desember 1899 0+000
2 109+675 - 110+150 475 3 Bidang Konsinyasi

3 110+150 - 111+550 1,400 28 Maret 2018 BS 066

4 111+550 - 112+400 850 09 November 2017 BS 280


5 112+400 - 113+200 800 30 Agustus 2017 BS 201.2
6 113+200 - 114+700 1,500 18 September 2017 BS 203.1
7 114+700 - 114+750 50 18 September 2017 BS 203
8 114+750 - 121+400 6,650 05 Oktober 2017 BS 238
9 121+400 - 122+950 1,550 30 Agustus 2017 BS 199
10 122+950 - 125+500 2,550 30 Agustus 2017 BS 201.1
11 125+500 - 131+150 5,650 30 Agustus 2017 BS 206

12 131+150 - 138+850 7,700 10 Agustus 2017 BS 143


13 138+850 - 141+100 2,250 04 April 2017 BS 081

14 141+100 - 145+650 4,550 23 Februari 2017 46-157


15 145+650 - 151+450 5,800 28 September 2017 BS 234
16 151+450 - 152+300 850 10 Agustus 2017 BS 139

17 152+300 - 155+500 3,200 23 November 2017 BS 297


18 155+500 - 158+050 2,550 20 Juni 2017 BT 409
19 158+050 - 158+700 650 20 Juni 2017 BT 407
20 158+700 - 164+100 5,400 06 April 2017 047-075
21 164+100 - 164+890 790 13 Juli 2017 BT 457
22 164+890 - 165+100 210 20 Juni 2017 BT 407
23 165+100 - 166+400 1,300 13 Juli 2017 BT 457
24 166+400 - 167+200 800 21 Agustus 2017 BT 612

25 167+200 - 174+400 7,200 20 Juni 2017 BT 407


26 174+400 - 174+850 450 Menunggu Lahan Penggant (Plasma Nutfah)
27 174+850 - 175+650 800 20 Juni 2017 BT 407
28 175+650 - 176+350 700 13 Juli 2017 BT 458
29 176+350 - 177+310 960 12 September 2017 BT 762
30 177+310 - 177+450 140 20 Juni 2017 BT 407
31 177+450 - 177+850 400 13 Juli 2017 BT 458
32 177+850 - 178+000 150 10 Agustus 2017 BT 610
33 178+000 - 178+920 920 13 Juli 2017 BT 458
34 178+920 - 179+025 105 10 Agustus 2017 BT 519
35 179+025 - 179+100 75 10 Agustus 2017 BT 611

36 179+100 - 179+355 255 10 Agustus 2017 BT 519&520


37 179+355 - 179+620 265 10 Agustus 2017 BT 520
38 179+620 - 179+840 220 10 Agustus 2017 BT 519
39 179+840 - 180+000 160 23 Agustus 2017 BT 628,1
40 180+000 - 180+600 600 10 Agustus 2017 BT 520
41 180+600 - 182+475 1,875 10 Agustus 2017 BT 521
42 182+475 - 185+600 3,125
TOTAL 78,325

BOBOT 101.72%
LAHAN BELUM BEBAS
Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
BIDANG BEBAS 1617
LUASAN BEBAS 12079236
KONSINYASI
(DI PENGADILAN)
Jan-18
No. STA Bangunan Terkait Desa Jumlah Bidang

1 114+649 Oprit Overpass S.Sodong


-
2 116+589 Oprit Overpass Suka Mukt
-
3 117+185 Oprit Overpass Suka Mukt
-
4 121+125 Oprit Overpass Suka Mukt
-
5 130+633 Oprit Overpass Mataram Jaya
-
6 132+290 Oprit Overpass Kemang Indah
-
7 134+433 Oprit Overpass Rotan Mulya
-
8 147+100 Oprit Overpass Tanjung Sari II
-
9 156+650 Oprit Overpass Cinta Jaya
-
10 159+775 Oprit Overpass Cinta Jaya
-
11 124+400 Rest Area tpe A sisi R Balian Makmur
-
12 133+000 Rest Area tpe A sisi L Kemang Indah
-
13 166+800 Rest Area Tipe A sisi L Cinta Jaya
-
14 166+850 Rest Area Tipe A sisi R Cinta Jaya
-
15 112+000 - 112+100 Main Road S.Sodong 3

16 155+500 - 158+450 Main Road Cinta Jaya 56

17 160+700 - 161+100 Main Road Cinta Jaya 1

18 161+600 - 161+800 Main Road Cinta Jaya 1

19 167+500 - 167+875 Main Road Cinta Jaya 1

20 168+775 - 168+825 Main Road Cinta Jaya 2

21 168+825 - 168+850 Main Road Cinta Jaya 1

22 168+850 - 168+900 Main Road Cinta Jaya 1


23 168+850 - 169+100 Main Road Cinta Jaya 2

24 169+300 - 169+350 Main Road Cinta Jaya 1

25 174+200 - 174+850 Main Road Kedaton 1

26 174+800 - 175+700 Main Road Kedaton 2

28 179+675 - 179+680 Main Road Perigi 1

29 179+700 - 179+710 Main Road Kutaraya 1

30 180+575 - 181+100 Main Road Kayuagung 2

31 184+275 - 184+300 Main Road Arisan Buntal 1

32 183+975 - 184+100 Main Road Arisan Buntal 1


Instansi Terkait
Luas (m²) Status saat ini Target dan Tindak Lanjut
PPK BPN

14,407.86 Feb-19
Pengajuan Lahan Overpasss
174,897.39 Feb-19
Pengajuan Lahan Overpasss
Feb-19
20,761.28 Pengajuan Lahan Overpasss
Feb-19
9,203.43 Pengajuan Lahan Overpasss
Feb-19
12,820.95 Pengajuan Lahan Overpasss
Feb-19
6,029.45 Pengajuan Lahan Overpasss
Feb-19
1,948.18 Pengajuan Lahan Overpasss
Feb-19
5,858.44 Pengajuan Lahan Overpasss
Feb-19
5,986.73 Pengajuan Lahan Overpasss
Feb-19
4,949.55 Pengajuan Lahan Overpasss
Feb-19
44,599.34 Pengajuan Lahan Overpasss
Feb-19
61,325.76 Pengajuan Lahan Overpasss
Feb-19
32,825.18 Pengajuan Lahan Overpasss
Feb-19
57,061.04 Pengajuan Lahan Overpasss
65,640.00 Proses di Pengadilan (menolak besarnya gant Oct-18
rugi) - Bisa Konstruksi

289,618.00 Tahap putusan di pengadilan - Bisa Konstruksi Oct-18

29,438.00 Tahap putusan di pengadilan - Bisa Konstruksi Oct-18

8,794.00 Proses di Pengadilan - Bisa Konstruksi Oct-18

34,639.00 di Pengadilan (Tahap Bacaan Gugatan) - Bisa


Konstruksi Oct-18

5,932.00 Proses di Pengadilan - Bisa Konstruksi Oct-18

601.00 No name (Tidak diketahui keberadaannya) - Oct-18


Bisa Konstruksi

2,611.00 PT Rambang (Proses Pengadilan) - Bisa Oct-18


Konstruksi
M.Jhoni Tharmos dkk (Sengketa di
15,144.00 Pengadilan) - - Diberhentkan warga (Sudah Oct-18
Full Slab)
742.00 Rambang Agro Jaya 2 (Tahap Mediasi Oct-18
Pengadilan) - Bisa Konstruksi

58,854.00 Plasma Nuftah (Menunggu lahan penggant) - Dec-18 V


Belum SPP - Bisa Konstruksi

107,381.00 Rambang Agro Jaya 2 (Tahap Putusan Oct-18


Pengadilan) - Bisa Konstruksi

130.00 proses di Pengadilan (tdak diketahui Oct-18


keberadaannya) - Bisa Konstruksi

196.00 Noname (Proses di Pengadilan) - Bisa Oct-18


Konstruksi

11,617.00 Proses di Pengadilan - Bisa Konstruksi Oct-18

1,609.00 Masturoh (Proses di pengadilan) - Bisa Oct-18


Konstruksi

2,328.00 a.n. Jali ( pengukuran ulang oleh BPN) - Oct-18


Proses Eksekusi
Instansi Terkait
PN HK

V
V

You might also like