Whose signature authorizes the project?

Project manager

Initiator or Sponsor
The PMBOK® Guide lists the initiator as the person whose signature authorizes the project.

Scrum master

Portfolio manager

Q
The ________ is created as a result of market demand, legal requirements and
ecological impacts.
cost-benefit analysis

business case
Cost-benefit and business need are often part of the business case. project charter is created as part of
the project initiation phase.

business need

project charter

Q
When we document steps that must be taken during execution to bring the expected
future performance of project work in line with the project management plan, that is
called _________.
performance corrective guidance

preventive action

defect repair

corrective action

Q
Decomposing tasks should continue until_______.
the point at which cost can be estimated and managed

the point at which activity durations can be estimated and managed

Neither of these

Both of these
Decomposing tasks should continue until cost and activity durations for the work can be reliably
estimated and managed.