SWITCHING PROCEDURES FOR GRID RESTORATION

1. CHECK VOLTAGE AVAILABILITY ON BOTH IRINGA


AND KIDATU LINES
2. CHECK STATUS OF UNITS WHICH WERE
CONNECTED TO GRID
3. CHECK AVAILABILITY OF AUXILLIARY SUPPLY (DG
SET)
4. OPEN IRINGA AND KIDATU CIRCUIT BREAKER
5. OPEN 33KV FEEDERS
6. TAKE NOTE OF TRIPPING INDICATIONS AND RESET
BOTH ON VDU AND LOCAL CONTROL ROOM
7. START MACHINES TO ENERGIZE BUSBAR AND
RESTORE AUXILLIARY SUPPLY FROM MACHINES.
8. COMMUNICATE WITH NGCC AND WAIT FOR
INSTRUCTION
9. CLOSE 33KV FEEDERS
10. CLOSE 220KV LINES ACCORDING TO NGCC
INSTRUCTIONS