You are on page 1of 4

IMPROVING THE PROTECTION OF EHV TEED FEEDERS USING LOCAL AGENTS

D V Coury1 J S Thorp2 K M Hopkinson2 K P Birman2


1
University of São Paulo, Brazil
2
Cornell University, USA

INTRODUCTION changing behavior, receiving updated parameter settings


from the owner or from other agents participating in the
The protection of multi-terminal lines is not as simple as same application. An agent can also learn from the
that of two-terminal lines. They usually experience environment; the term “intelligent” is sometimes applied
additional problems caused by the intermediate infeed to such agents, particularly if the learning method
from the third terminal, an outfeed, different line lengths involves artificial intelligence tools, or neural networks.
to the tee point, etc. The limitations of non-pilot distance Agents can be further subdivided based on their
relays for their protection have been acknowledged for mobility. Mobile agents can literally travel from one
decades. These limitations lead to the traditional location to another while maintaining their state and
distance relaying approach to experience severe functionality. One imagines such an agent as moving
underreach and overreach problems. The relay first zone through a network in search of certain data, or for
reach may not even extend beyond the tee point in some locations having certain attributes. In contrast, local
underreach cases (1),(2). agents are placed by the owner and then remain in the
An approach based on adaptive relaying to face such a same location throughout their computational lives.
situation and some fundamental concepts concerning it Both kinds of agents normally have the ability to
was presented by Rockefeller (3). Horowitz et al (4) communicate with one another making mobility a lesser
define adaptive relaying as a protection philosophy benefit than it might appear at first glance.
which permits and seeks to make adjustments to various In the present paper, we consider the simplest kinds of
protection functions in order to make them more attuned agents: local, non-intelligent ones. Our work seeks to
to prevailing power system conditions. An adaptive demonstrate advantages stemming from the rapid
setting concept for two and three terminal lines, which response time made possible by placing a computational
can respond to changes in the network conditions, was task close to the point where an action or measurement
proposed by Xia et al (5), (6). Stedall et al (7) also is needed, and the simplicity of the power systems
proposed an investigation into the use of adaptive architecture afforded by the ability to send code to
setting techniques for improved distance back-up general purpose computing platforms. The basic idea is
protection. that by doing so, new control paradigms can be
This paper discusses the adaptation of the settings of introduced and executed efficiently, without changing
distance relays for multi-terminal lines employing the basic computing architecture of the power systems
agents. Agents are software processes capable of network.
searching for information in networks, interacting with The use of agents raises security considerations that go
pieces of equipment and performing tasks on behalf of beyond those encountered in traditional software
their owners (relays). Moreover, they are autonomous systems. Among the issues that need to be considered
and cooperative. Very few publications concerning the are the mechanism for installing agents and for
application of agents in the protection field have been communicating parameter updates to them, the means by
reported in the literature. Tomita et al (8) proposed a which a computing platform or agent authenticates
cooperative protection system utilizing agents. Relay incoming messages, and the enforcement of agent
agents were constructed, and the cooperation of the resource restrictions, such as the use of scarce
main agents was simulated for primary, backup and computational cycles or space in databases and file
adaptive protection. systems. Prior to deploying agents in mission-critical
Results illustrating the improved performance of the settings, one would need satisfying answers on all of
adaptive method proposed compared to conventional these fronts. Preliminary work towards policies
fixed settings are presented in the following sections. addressing these issues can be found in (10).

AGENT TECHNOLOGY THE PROPOSED COMMUNICATION


STRUCTURE AND THE POWER SYSTEM
A software agent is a computer program that takes STUDIED
independent action based on events in the surrounding
environment (Genesereth (9)). Under the control of The communication structure (middleware)
some application that owns the agent, it is sent forth or
placed at some site within a network where it takes local The computing infrastructure in which our agent
actions on behalf of its owners. Agents are dynamic community will operate is a subject of active speculation
entities. For example, an agent can exhibit dynamically at the time of this writing. The existing power grid
communication infrastructure is composed of a
Terminal 30km
hodgepodge of equipment ranging from high-end fiber 1 100 km 100km
optic cables with large data bandwidth to crude systems
with limited data transfer capabilities to nothing at all. ~
~
Few utility communications lines are interconnected. TTerminal
1.0 /_0o 0.9 /_-8o
However, this picture will change as utilities deploy ever 2
more elaborate control mechanisms, demanding 400 kV
80km
increasingly rich communication frameworks, steps that
can easily be foreseen as part of the battle to improve
Terminal
operating efficiencies. 3
The relay scheme proposed here has modest network 1.0 /_ -5o
resource requirements compared to what we believe will ~
be available in the near future. It is expected that the
need for greater communication will result in a Utility
Intranet (UI) that would interconnect control areas and Figure 1 The three-ended system utilized for tests
their dependent entities using a relatively high capacity
network similar to the Internet but physically separate A 400 kV system with tee configuration is shown in Fig.
from it and dedicated to the power systems application. 1. The different line lengths are presented in the figure,
However, we caution that predictions of network as well as the voltage levels at the busbars. This work
bandwidth requirements and total network capacity can focuses on line-to-ground faults, since most faults in
be deceptively reassuring. History has shown a tendency power system transmission lines are of this type.
for networked applications to use all bandwidth made The protection system associated with this configuration
available to them. was simulated for conventional non-pilot protection as
To evaluate the feasibility of employing agents and well as a portion of the agent based relaying approach
network communication in power-systems relay proposed. Digital distance relays with three zone
protection, we need to understand the reliability and quadrilateral characteristics located at terminals 1, 2 and
latency requirements of the relays. By doing so, we can 3 were simulated. DFT (Discrete Fourier Transform)
determine whether or not a proposed combination of routines were utilized in order to filter the faulted waves.
network hardware and communication protocols can Circuit breakers were associated with the relays in order
meet the protection system's needs. Relays play a critical to isolate the line in case of an internal fault.
role in power grid operations with low tolerance for
failures. One can identify that situations in AGENT RELAYS
communication between agents used for relay control
might need to take place in as little as 10 ms, a latency Fig.2 presents the agent mechanism for protection
realm leaving little time to recover from data purposes. It can be initially divided into an adaptive pre-
transmission failures. It is therefore critical to ask fault approach and a post-fault transfer trip action. The
whether available technology can meet those mechanism utilizes local agents at terminals 1, 2 and 3
requirements. communicating with each other.
In order to face some of the network limitations,
communication protocols like Cornell's Spinglass have Adaptive Pre-fault Approach
been developed by Birman et al (11). Spinglass allows
the user to achieve high levels of reliability using The main purpose of the proposed agent mechanism is
protocols that probabilistically mask latency fluctuations to carry out the adaptation of the settings of distance
and message loss. Spinglass could be optimized for use relays for multi-terminal lines in order to ensure correct
in power relaying and might form a powerful performance over a wide variety of operation
infrastructure for improved protection schemes. conditions.
Initially, local agents for terminals 1, 2 and 3 can be
defined as:
The three-ended system utilized
Operation Agent: This is a local agent, which monitors
In order to simulate the real system encountered in the operating condition at a terminal. The following
practice, this work makes use of a digital simulator of parameters related to the system condition must be
faulted transmission lines known as PSCAD/EMTDC obtained from on-line measurements and/or calculations:
(Electromagnetic Transients and Controls Simulation
Engine) (12). It should be mentioned that although • Pre-fault busbar voltages
the technique described is based on Computer Aided • Power transfer angles
Design (CAD), practical considerations such as the • Source impedances
Capacitor Voltage Transformer (CVT), Current
Transformer (CT) and anti-aliasing filters on system Breaker Status Agent: This local agent monitors changes
fault data were also included in the simulation. in the system topology based on circuit breaker status.
The two local agents, shown in Fig.2, must external to a protection zone. The relationship between
communicate with the Coordination Agent, as defined in voltage and current is used for this purpose. This
item 3. relationship is disturbed when there is infeed or outfeed.
As mentioned earlier, this can make the relay experience
Coordination Agent: The coordination agent collects severe underreach or overreach problems, especially
information, makes decision, and disseminates considering non-pilot protection schemes for three
information to the other two Coordination agents. The terminal lines. Another situation that has to be taken into
Coordination Agent at each terminal can then choose the account is when the tap is not working for some reason.
correct relay characteristic, based on the information The setting of distance relays must reflect all the
received. situations described earlier. Fig. 3(a) shows the typical
non-pilot distance protection with the first zone for a
We propose that a group of settings be calculated off- three terminal line at the condition represented in Fig. 1.
line, and that these parameters be renewed from time to As shown in the figure, only approximately 20 from 210
time as the system condition changes beyond a certain km obtained instantaneous trip from the three ends of
limit, based on the Coordination Agent information. the lines in the case of an internal fault. Fig. 3(b)
Then, when a fault occurs the relay will operate close to illustrates the improvement that can be found with the
its ideal characteristic. adaptive scheme utilizing Agents that is proposed in this
work. The instantaneous trip area increased to
First Zone Transfer Trip approximately 67 km (more than three times the non-
pilot condition) for the same situation. As mentioned
This action takes place after the fault occurrence. In before, the proposed adaptive scheme can alter settings
order to decrease the clearance time, when a fault is to ensure better performance over a wide variety of
detected in the first zone of any of the relays located at operation conditions.
the three terminals, a trip signal is sent through the
communication network to the other two ends. A First Clearance Time
Zone Local Agent coordinates the first zone transfer
trip. In order to highlight the efficiency of the proposed
scheme, this section presents a figure comparing the
clearance time for the conventional non-pilot protection
First as well as for the proposed scheme utilizing Agents.
Zone Fig. 4 presents the clearance time for the three-ended
Agent
line shown in Fig. 1. Line-to-ground faults are applied to
different locations on leg 1-T, considering different fault
inception angles and fault resistance of 10 ohms. The
COORDINATION
figure shows the average clearance time considering legs
AGENT 1, 2 and 3 for the non-pilot protection as well as the
proposed scheme considering three different traffic
conditions. A considerable decrease in clearance time
considering the proposed scheme can be observed.
It should be noted that an opening time of approximately
Breaker Operati- three cycles for the circuit breaker utilized was
Status on considered. It isolates the fault by interrupting the
Agent Agent
current at or near a current zero. A coordination delay
data request for zone two of the order of 0.3 s was also utilized.
-INTERFACE WITH THE POWER SYSTEM-
Connection to the other two terminals
CONCLUSION

Figure 2 Agent mechanism in one terminal for protection An application of agents acting within a
purpose communication structure to adaptive relay settings for
multi-terminal lines was presented in this paper. Results
RESULTS OBTAINED UTILIZING AGENT illustrating the performance of the new method proposed
TECHNOLOGY compared to conventional fixed settings were shown.
The new approach based on agents was divided in an
Adaptive Pre-fault Approach Results adaptive pre-fault approach and a post-fault transfer trip
action. In order to test the proposed scheme, a digital
Distance relaying techniques have attracted considerable simulation of a faulted transmission line was performed
attention for the protection of transmission lines. The utilizing the PSCAD/EMTDC software. The protection
principle of this technique measures the impedance at a system associated with this configuration was also
fundamental frequency between the relay location and simulated both for conventional non-pilot protection as
the fault point, thus determining if a fault is internal or well as for the Agent based relaying.
Terminal 2 very attractive alternative to improve the performance of
Terminal 1 T
protection systems.
~
ACKNOWLEDGMENTS

The authors acknowledge the research support by


20km subcontract No. 35352-6085 with Cornell University
under WO 8333-04 from the Electric Power Institute
and the U.S. Army Research Office. Our
Terminal 3 acknowledgments also extend to DARPA/RADC grant
F30602-99-1-6532 as well as FAPESP (Fundação de
~ Amparo à Pesquisa do Estado de São Paulo -Brazil).

REFERENCES
(a) Non-pilot protection
(1) Horowitz S H and Phadke AG, 1996 “Power System
Terminal 1 Terminal 2
T
Relaying”, John Wiley and Sons.
~ (2) IEEE Working Group, 1979, “Protection Aspects of
Multi-terminal Lines”, IEEE Special Publication, 79
TH0056-2-PWR.
(3) Rockefeller G D, Wagner C L, Linders J R, Hicks K
L and Rizy D T, 1988 “Adaptive Transmission Relaying
67 km Concepts for Improved Performance”, IEEE Trans. on
Power Delivery, 3 (4), 1446-58.
(4) Horowitz S H, Phadke A G and Thorp J S, 1988
Terminal 3 “Adaptive Transmission System Relaying”, IEEE Trans.
on Power Delivery, 3 (4), 1436-45.
~ (5) Xia Y Q , Li K K and David A K , 1994 “Adaptive
Relay Setting for Stand Alone Digital Distance
(b)Agent Technology proposed – Adaptive pre-fault scheme Protection”, IEEE Trans. on Power Delivery, 9(1), 480-
91.
Figure 3 Distance relaying of a three ended transmission line (6) Xia Y Q, David A K and Li K K, 1994 “High-
Resistance Faults on a Multi-Terminal Line: Analysis,
Simulated Studies and an Adaptive Distance Relaying
Scheme”, IEEE Trans. on Power Delivery, 9 (1), 492-
Average clearance time on the three legs 500.
(7) Stedall B, Moore P, Johns A, Goody J and Burt M,
0,4 nonpilot 1996 “An Investigation into the use of Adaptive Setting
0,3 traffic1 Techniques for Improved Distance Back-up Protection”,
(msec)

0,2 traffic2 IEEE Trans. on Power Delivery, 11 (2), 757- 62.


0,1 traffic3 (8) Tomita Y, Fukui C, Kudo H, Koda J, Yabe K, 1998
0
“A Cooperative Protection System with an Agent
1 2 3
Model”, IEEE Trans. on Power Delivery, 13 (4), 1060-
66.
TL leg
(9) Genesereth M and Ketchpel S, 1994 "Software
Agents", Communications of the ACM, 37(7), 48-52,
147.
Figure 4 Average clearance time for the three legs considering (10) Schneider F, 1997 "Towards Fault-tolerant and
non-pilot protection and the scheme proposed
Secure Agentry", 111th International Workshop on
Distributed Algorithms, 1320, September 1-14.
The results showed that the new approach would alter
(11) Birman K, Hayden M, Ozkasap O, Xiao Z, Budiu
adaptive settings to ensure correct performance over a
M and Minsky Y, 1999 "Bimodal Multicast", ACM
wide variety of operation conditions, which is an
Trans. on Computer Systems, 17(2).
improvement compared to fixed settings for the relays.
(12) PSCAD/EMTDC Manual, 1998 Getting Started,
Moreover, a considerable decrease in clearance time
Manitoba HVDC Center
compared to conventional non-pilot protection was
observed.
It should then be emphasized that the new approach is
not only a solution for a well-known problem, but also a

You might also like