You are on page 1of 126

SCHEDULE PEMASUKAN LAPORAN INSPECTOR

Laporan Laporan
Bulan Minggu Sampai Dengan
Mingguan Bulanan

1 12-Mar 18-Mar Mingguan 7.00

2 19-Mar 25-Mar Mingguan 14.00


1
3 26-Mar 1-Apr Mingguan 21.00

4 2-Apr 8-Apr Mingguan Bulanan 28.00

5 9-Apr 15-Apr Mingguan 35.00

6 16-Apr 22-Apr Mingguan 42.00


2
7 23-Apr 29-Apr Mingguan 49.00

8 30-Apr 6-May Mingguan Bulanan 56.00

9 7-May 13-MayMingguan 63.00

10 14-May 20-May Mingguan 70.00


3
11 21-May 27-May Mingguan 77.00

12 28-May 3-Jun Mingguan Bulanan 84.00

13 4-Jun 10-Jun Mingguan 91.00

14 11-Jun 17-Jun Mingguan 98.00


4
15 18-Jun 24-Jun Mingguan 105.00

16 25-Jun 1-Jul Mingguan Bulanan 112.00

17 2-Jul 8-Jul Mingguan 119.00

18 9-Jul 15-Jul Mingguan 126.00


5
19 16-Jul 22-Jul Mingguan 133.00

20 23-Jul 29-Jul Mingguan Bulanan 140.00


21 30-Jul 5-Aug Mingguan 147.00

6 22 6-Aug 12-Aug Mingguan 154.00

23 13-Aug 19-Aug Mingguan 161.00

24 20-Aug 26-Aug Mingguan Bulanan 168.00

25 27-Aug 2-Sep Mingguan 175.00

7 26 3-Sep 9-Sep Mingguan 182.00

27 10-Sep 16-Sep Mingguan 189.00

28 17-Sep 23-Sep Mingguan Bulanan 196.00

29 24-Sep 30-Sep Mingguan 203.00

8 30 1-Oct 7-Oct Mingguan 210.00 selesai kontrak


175
selesai kontrak
PROGRES KEMAJUAN PEK

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN NUSA TENGGARA TIMUR
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE
TAHUN ANGGARAN : 2018

KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan Ls 1.00 12,815,000.00
Mobilisasi Dan Demobilisasi Ls 1.00 5,000,000.00
Jumlah Total I

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
Pekerjaan Galian Tanah
- Galian Tanah Biasa M3 1,152.11 48,335.00
- Galian Batu M3 768.07 98,795.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Timbunan Tanah Termasuk Pemadatan M3 576.06 43,758.00
Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')
- Pekerjaan Rabat Lantai dasar Saluran m³ 21.02 1,010,463.00
- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast) buah 473.00 1,990,119.00
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100) buah 378.00 1,081,619.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600 unit 94.00 867,943.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 17.03 71,105.00
- Pekerjaan Pasangan Batu m3 7.78 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 40.00 28,333.33

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran m³ 37.70 1,010,463.00
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast) buah 628.00 2,536,369.00
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100) buah 502.00 1,167,869.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800 unit 125.00 885,979.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 30.14 71,105.00
- Pekerjaan Pasangan Batu m3 21.00 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 50.00 28,333.33
Jumlah Total A
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

BANGUNAN PLAT DEUKER/BOX CULVERT


Pekerjaan Galian Tanah
- Galian Tanah Biasa m3 12.96 48,335.00
- Galian Batu m3 8.64 98,795.00
- Timbunan Tanah Termasuk Pemadatan m3 6.48 43,758.00
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran m³ 0.90 1,010,463.00
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200 buah 15.00 5,089,491.00
- Pekerjaan Pasangan Batu m³ 5.23 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 10.04 71,105.00
- Acian m2 10.04 31,951.00
Jumlah Total B

PEKERJAAN BANGUNAN PELENGKAP


Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12 M3 1,304.05 15,118.65
- Beton Mutu K-200 M3 44.00 1,618,377.00
Jumlah Total C
PEKERJAAN KOLAM OLAKAN
Pekerjaan Kolam Olakan
- Galian Tanah Biasa m3 15.00 48,355.00
- Galian Batu m3 7.00 98,795.00
- Pasangan Batu (Campuran 1 PC : 4 PP) m³ 2.45 785,590.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Plesteran (Campuran 1 PC : 3 PP) m2 5.76 71,105.00
- Acian m2 5.76 31,951.00
Jumlah Total D
Jumlah Total D * 5 UNIT

A. J U M L A H

B. PAJAK PERTAMBAHAN NILAI (PPN ) = 10% x A

C. JUMLAH TOTOL HARGA PENAWARAN = A + B

JUMLAH DIBULATKAN

Mengetahui / Menyetujui : Disetujui Oleh :


PPK Pengembangan Sistem PLP I Direksi Teknis
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT

Tinny Touselak, ST, MT Indri M. Susetyo, ST


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
MAJUAN PEKERJAAN MINGGUAN

SA TENGGARA TIMUR MINGGU KE : (I) SATU


TANGGAL : 12 Maret 2018 s/d 18 Maret 2018

REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini

JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

12,815,000.00 0.31 - - -
5,000,000.00 0.12 - - -
17,815,000.00 0.43 - - -

55,687,344.35 1.33 - - -
75,881,951.45 1.82 - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini

JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

25,207,063.35 0.60 - - -

21,235,890.41 0.51 - - -
941,326,287.00 22.52 - - -
408,851,982.00 9.78 - - -
81,586,642.00 1.95 - - -
1,210,775.94 0.03 - - -
6,108,747.84 0.15 - - -
568,840.00 0.01 - - -
255,608.00 0.01 - - -
1,133,333.20 0.03 - - -

38,094,455.10 0.91 - - -
1,592,839,732.00 38.10 - - -
586,270,238.00 14.02 - - -
110,747,375.00 2.65 - - -
2,143,389.12 0.05 - - -
16,497,390.00 0.39 - - -
568,840.00 0.01 - - -
255,608.00 0.01 - - -
1,416,666.50 0.03 - - -
3,967,888,159.25 94.92 - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini

JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

626,421.60 0.01 - - -
853,588.80 0.02 - - -
283,551.84 0.01 - - -

909,416.70 0.02 - - -
76,342,365.00 1.83 - - -
4,108,635.70 0.10 - - -
713,894.20 0.02 - - -
320,788.04 0.01 - - -
84,158,661.88 2.01 - - -

19,715,475.53 0.47 - - -
71,208,588.00 1.70 - - -
90,924,063.53 2.17 - - -

725,325.00 0.02 - - -
691,565.00 0.02 - - -
1,923,124.32 0.05 - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini

JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

409,564.80 0.01 - - -
184,037.76 0.00 - - -
3,933,616.88 0.09 - - -
19,668,084.40 0.47 - - -

4,180,453,969.06 100.00 - - -

418,045,396.91

4,598,499,365.97

4,598,490,000.00

Ende, 18 Maret 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
A PSPLP-NTT PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


201001 2 056 PELAKSANA Site Engineering
PRESENTASI
PEKERJAAN (%)

-
-

-
-
PRESENTASI
PEKERJAAN (%)

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
PRESENTASI
PEKERJAAN (%)

-
-
-

-
-
-
-
-

-
-

-
-
-
PRESENTASI
PEKERJAAN (%)

-
-
REKAPITULASI KEMAJUAN PEKERJAAN MINGGUAN
Mengetahui/Menyetujui :
Konsultan Pengawas
CV. NUSA PRATAMA KONSULT
JO
SATUAN KERJA : PENGEMBANGAN SISTEM
PT. ARGA PASCALINGKUNGAN
PENYEHATAN RENCANA PERMUKIMAN NUSA TENGGARA TIMUR
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE MINGGU KE : (I) SATU
TAHUN ANGGARAN : 2018 TANGGAL : 12 Maret 2018
DANIEL FREDRIK MARO, SP
Direktur

B
NO JENIS PEKERJAAN JUMLAH HARGA
BOBOT
(%)

I PEKERJAAN PERSIPAN Rp 17,815,000.00 0.43

II KONSTRUKSI PEKERJAAN SALURAN DAN

BANGUNAN PELENGKAP

- PEKERJAAN SALURAN DRAINASE Rp 3,967,888,159.25 94.92

- BANGUNAN PLAT DEUKER/BOX CULVERT Rp 84,158,661.88 2.01


- PEKERJAAN BANGUNAN PELENGKAP Rp 90,924,063.53 2.17

- PEKERJAAN KOLAM OLAKAN Rp 19,668,084.40 0.47

JUMLAH Rp 4,180,453,969.06 100.00


PPN 10 % Rp 418,045,396.91
TOTAL NILAI Rp 4,598,499,365.97
PEMBULATAN Rp 4,598,490,000.00
Minggu ini
Sampai dengan Ming
Sampai dengan Ming
Rencana sampai den
Deviasi

Mengetahui / Menyetujui : Disetujui Oleh : Diketahu


PPK Pengembangan Sistem PLP I Direksi Teknis Kontraktor P
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT PT. BAHANA KRID

Tinny Touselak, ST, MT Indri M. Susetyo, ST Septian Mau


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
AJUAN PEKERJAAN MINGGUAN

(I) SATU
12 Maret 2018 s/d 18 Maret 2018

BOBOT PRESTASI YANG DICAPAI (%)


S/D KET
MINGGU JUMLAH S/D
MINGGU
INI MINGGU INI
LALU

- 0.00 0.00

- 0.00 0.00

- 0.00 0.00
- 0.00 0.00

- 0.00 0.00

0.00 0.00 0.00 %


0.00 %
Sampai dengan Minggu Lalu 0.00 %
Sampai dengan Minggu ini 0.00 %
Rencana sampai dengan minggu ini 0.12 %
-0.12 %

Ende, 18 Maret 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


Pelaksana Site Engineering
PROGRES KEMAJUAN PEK

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN NUSA TENGGARA TIMU
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE
TAHUN ANGGARAN : 2018

KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan Ls 1.00 12,815,000.00
Mobilisasi Dan Demobilisasi Ls 1.00 5,000,000.00
Jumlah Total I

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
Pekerjaan Galian Tanah
- Galian Tanah Biasa M3 1,152.11 48,335.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Galian Batu M3 768.07 98,795.00
- Timbunan Tanah Termasuk Pemadatan M3 576.06 43,758.00
Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')
- Pekerjaan Rabat Lantai dasar Saluran m³ 21.02 1,010,463.00
- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast) buah 473.00 1,990,119.00
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100) buah 378.00 1,081,619.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600 unit 94.00 867,943.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 17.03 71,105.00
- Pekerjaan Pasangan Batu m3 7.78 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 40.00 28,333.33

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran m³ 37.70 1,010,463.00
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast) buah 628.00 2,536,369.00
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100) buah 502.00 1,167,869.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800 unit 125.00 885,979.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 30.14 71,105.00
- Pekerjaan Pasangan Batu m3 21.00 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 50.00 28,333.33
Jumlah Total A
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

BANGUNAN PLAT DEUKER/BOX CULVERT


Pekerjaan Galian Tanah
- Galian Tanah Biasa m3 12.96 48,335.00
- Galian Batu m3 8.64 98,795.00
- Timbunan Tanah Termasuk Pemadatan m3 6.48 43,758.00
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran m³ 0.90 1,010,463.00
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200 buah 15.00 5,089,491.00
- Pekerjaan Pasangan Batu m³ 5.23 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 10.04 71,105.00
- Acian m2 10.04 31,951.00
Jumlah Total B

PEKERJAAN BANGUNAN PELENGKAP


Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12 M3 1,304.05 15,118.65
- Beton Mutu K-200 M3 44.00 1,618,377.00
Jumlah Total C
PEKERJAAN KOLAM OLAKAN
Pekerjaan Kolam Olakan
- Galian Tanah Biasa m3 15.00 48,355.00
- Galian Batu m3 7.00 98,795.00
- Pasangan Batu (Campuran 1 PC : 4 PP) m³ 2.45 785,590.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Plesteran (Campuran 1 PC : 3 PP) m2 5.76 71,105.00
- Acian m2 5.76 31,951.00
Jumlah Total D
Jumlah Total D * 5 UNIT

A. J U M L A H

B. PAJAK PERTAMBAHAN NILAI (PPN ) = 10% x A

C. JUMLAH TOTOL HARGA PENAWARAN = A + B

JUMLAH DIBULATKAN

Mengetahui / Menyetujui : Disetujui Oleh :


PPK Pengembangan Sistem PLP I Direksi Teknis
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT

Tinny Touselak, ST, MT Indri M. Susetyo, ST


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
UAN PEKERJAAN MINGGUAN

GGARA TIMUR MINGGU KE : (II) DUA


TANGGAL : 19 Maret 2018 s/d 25 Maret 2018

REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

12,815,000.00 0.31 - - - - - -
5,000,000.00 0.12 - - 0.20 0.02 0.20 0.02 20.00
17,815,000.00 0.43 - 0.02 0.02

55,687,344.35 1.33 - - - - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

75,881,951.45 1.82 - - - - - -
25,207,063.35 0.60 - - - - - -

21,235,890.41 0.51 - - - - - -
941,326,287.00 22.52 - - - - - -
408,851,982.00 9.78 - - - - - -
81,586,642.00 1.95 - - - - - -
1,210,775.94 0.03 - - - - - -
6,108,747.84 0.15 - - - - - -
568,840.00 0.01 - - - - - -
255,608.00 0.01 - - - - - -
1,133,333.20 0.03 - - - - - -

38,094,455.10 0.91 - - - - - -
1,592,839,732.00 38.10 - - - - - -
586,270,238.00 14.02 - - - - - -
110,747,375.00 2.65 - - - - - -
2,143,389.12 0.05 - - - - - -
16,497,390.00 0.39 - - - - - -
568,840.00 0.01 - - - - - -
255,608.00 0.01 - - - - - -
1,416,666.50 0.03 - - - - - -
3,967,888,159.25 94.92 - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

626,421.60 0.01 - - - - - -
853,588.80 0.02 - - - - - -
283,551.84 0.01 - - - - - -

909,416.70 0.02 - - - - - -
76,342,365.00 1.83 - - - - - -
4,108,635.70 0.10 - - - - - -
713,894.20 0.02 - - - - - -
320,788.04 0.01 - - - - - -
84,158,661.88 2.01 - - -

19,715,475.53 0.47 - - - - - -
71,208,588.00 1.70 - - - - - -
90,924,063.53 2.17 - - -

725,325.00 0.02 - - - - - -
691,565.00 0.02 - - - - - -
1,923,124.32 0.05 - - - - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

409,564.80 0.01 - - - - - -
184,037.76 0.00 - - - - - -
3,933,616.88 0.09 - - -
19,668,084.40 0.47 - - -

4,180,453,969.06 100.00 - 0.02 0.02

418,045,396.91

4,598,499,365.97

4,598,490,000.00

Ende, 24 Maret 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
P-NTT PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


2 056 PELAKSANA Site Engineering
REKAPITULASI KEMAJUAN PEKERJAAN MINGGUAN
Mengetahui/Menyetujui :
Konsultan Pengawas
CV. NUSA PRATAMA KONSULT
JO
SATUAN KERJA : PENGEMBANGAN SISTEM
PT. ARGA PASCALINGKUNGAN
PENYEHATAN RENCANA PERMUKIMAN NUSA TENGGARA TIMUR
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE MINGGU KE : (II) DUA
TAHUN ANGGARAN : 2018 TANGGAL : 19 Maret 2018
DANIEL FREDRIK MARO, SP
Direktur

B
NO JENIS PEKERJAAN JUMLAH HARGA
BOBOT
(%)

I PEKERJAAN PERSIPAN Rp 17,815,000.00 0.43

II KONSTRUKSI PEKERJAAN SALURAN DAN

BANGUNAN PELENGKAP

- PEKERJAAN SALURAN DRAINASE Rp 3,967,888,159.25 94.92

- BANGUNAN PLAT DEUKER/BOX CULVERT Rp 84,158,661.88 2.01


- PEKERJAAN BANGUNAN PELENGKAP Rp 90,924,063.53 2.17

- PEKERJAAN KOLAM OLAKAN Rp 19,668,084.40 0.47

JUMLAH Rp 4,180,453,969.06 100.00


PPN 10 % Rp 418,045,396.91
TOTAL NILAI Rp 4,598,499,365.97
PEMBULATAN Rp 4,598,490,000.00
Minggu ini
Sampai dengan Minggu
Sampai dengan Minggu
Rencana sampai denga
Deviasi

Mengetahui / Menyetujui : Disetujui Oleh : Diketah


PPK Pengembangan Sistem PLP I Direksi Teknis Kontrakto
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT PT. BAHANA K

Tinny Touselak, ST, MT Indri M. Susetyo, ST Septian M


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
JUAN PEKERJAAN MINGGUAN

s/d 25 Maret 2018

BOBOT PRESTASI YANG DICAPAI (%)


S/D KET
MINGGU JUMLAH S/D
MINGGU
INI MINGGU INI
LALU

- 0.02 0.02

- 0.00 0.00

- 0.00 0.00
- 0.00 0.00

- 0.00 0.00

0.00 0.02 0.02 %


0.02 %
Sampai dengan Minggu Lalu 0.00 %
Sampai dengan Minggu ini 0.02 %
Rencana sampai dengan minggu ini 0.27 %
-0.25 %

Ende, 24 Maret 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


Pelaksana Site Engineering
PROGRES KEMAJUAN PEK

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN NUSA TENGGARA TIMU
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE
TAHUN ANGGARAN : 2018

KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan Ls 1.00 12,815,000.00
Mobilisasi Dan Demobilisasi Ls 1.00 5,000,000.00
Jumlah Total I

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
Pekerjaan Galian Tanah
- Galian Tanah Biasa M3 1,152.11 48,335.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Galian Batu M3 768.07 98,795.00
- Timbunan Tanah Termasuk Pemadatan M3 576.06 43,758.00
Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')
- Pekerjaan Rabat Lantai dasar Saluran m³ 21.02 1,010,463.00
- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast) buah 473.00 1,990,119.00
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100) buah 378.00 1,081,619.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600 unit 94.00 867,943.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 17.03 71,105.00
- Pekerjaan Pasangan Batu m3 7.78 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 40.00 28,333.33

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran m³ 37.70 1,010,463.00
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast) buah 628.00 2,536,369.00
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100) buah 502.00 1,167,869.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800 unit 125.00 885,979.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 30.14 71,105.00
- Pekerjaan Pasangan Batu m3 21.00 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 50.00 28,333.33
Jumlah Total A
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

BANGUNAN PLAT DEUKER/BOX CULVERT


Pekerjaan Galian Tanah
- Galian Tanah Biasa m3 12.96 48,335.00
- Galian Batu m3 8.64 98,795.00
- Timbunan Tanah Termasuk Pemadatan m3 6.48 43,758.00
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran m³ 0.90 1,010,463.00
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200 buah 15.00 5,089,491.00
- Pekerjaan Pasangan Batu m³ 5.23 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 10.04 71,105.00
- Acian m2 10.04 31,951.00
Jumlah Total B

PEKERJAAN BANGUNAN PELENGKAP


Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12 M3 1,304.05 15,118.65
- Beton Mutu K-200 M3 44.00 1,618,377.00
Jumlah Total C
PEKERJAAN KOLAM OLAKAN
Pekerjaan Kolam Olakan
- Galian Tanah Biasa m3 15.00 48,355.00
- Galian Batu m3 7.00 98,795.00
- Pasangan Batu (Campuran 1 PC : 4 PP) m³ 2.45 785,590.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Plesteran (Campuran 1 PC : 3 PP) m2 5.76 71,105.00
- Acian m2 5.76 31,951.00
Jumlah Total D
Jumlah Total D * 5 UNIT

A. J U M L A H

B. PAJAK PERTAMBAHAN NILAI (PPN ) = 10% x A

C. JUMLAH TOTOL HARGA PENAWARAN = A + B

JUMLAH DIBULATKAN

Mengetahui / Menyetujui : Disetujui Oleh :


PPK Pengembangan Sistem PLP I Direksi Teknis
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT

Tinny Touselak, ST, MT Indri M. Susetyo, ST


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
UAN PEKERJAAN MINGGUAN

GGARA TIMUR MINGGU KE : (III) TIGA


TANGGAL : 26 Maret 2018 s/d 01 April 2018

REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

12,815,000.00 0.31 - - 0.25 0.08 0.25 0.08 25.00


5,000,000.00 0.12 0.20 0.02 - 0.20 0.02 20.00
17,815,000.00 0.43 0.02 0.08 0.10

55,687,344.35 1.33 - - - - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

75,881,951.45 1.82 - - - - - -
25,207,063.35 0.60 - - - - - -

21,235,890.41 0.51 - - - - - -
941,326,287.00 22.52 - - - - - -
408,851,982.00 9.78 - - - - - -
81,586,642.00 1.95 - - - - - -
1,210,775.94 0.03 - - - - - -
6,108,747.84 0.15 - - - - - -
568,840.00 0.01 - - - - - -
255,608.00 0.01 - - - - - -
1,133,333.20 0.03 - - - - - -

38,094,455.10 0.91 - - - - - -
1,592,839,732.00 38.10 - - - - - -
586,270,238.00 14.02 - - - - - -
110,747,375.00 2.65 - - - - - -
2,143,389.12 0.05 - - - - - -
16,497,390.00 0.39 - - - - - -
568,840.00 0.01 - - - - - -
255,608.00 0.01 - - - - - -
1,416,666.50 0.03 - - - - - -
3,967,888,159.25 94.92 - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

626,421.60 0.01 - - - - - -
853,588.80 0.02 - - - - - -
283,551.84 0.01 - - - - - -

909,416.70 0.02 - - - - - -
76,342,365.00 1.83 - - - - - -
4,108,635.70 0.10 - - - - - -
713,894.20 0.02 - - - - - -
320,788.04 0.01 - - - - - -
84,158,661.88 2.01 - - -

19,715,475.53 0.47 - - - - - -
71,208,588.00 1.70 - - - - - -
90,924,063.53 2.17 - - -

725,325.00 0.02 - - - - - -
691,565.00 0.02 - - - - - -
1,923,124.32 0.05 - - - - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

409,564.80 0.01 - - - - - -
184,037.76 0.00 - - - - - -
3,933,616.88 0.09 - - -
19,668,084.40 0.47 - - -

4,180,453,969.06 100.00 0.02 0.08 0.10

418,045,396.91

4,598,499,365.97

4,598,490,000.00

Ende, 30 Maret 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
P-NTT PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


2 056 PELAKSANA Site Engineering
REKAPITULASI KEMAJUAN PEKERJAAN MINGGUAN
Mengetahui/Menyetujui :
Konsultan Pengawas
CV. NUSA PRATAMA KONSULT
JO
SATUAN KERJA : PENGEMBANGAN SISTEM
PT. ARGA PASCALINGKUNGAN
PENYEHATAN RENCANA PERMUKIMAN NUSA TENGGARA TIMUR
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE MINGGU KE : (III) TIGA
TAHUN ANGGARAN : 2018 TANGGAL : 26 Maret 2018
DANIEL FREDRIK MARO, SP
Direktur

B
NO JENIS PEKERJAAN JUMLAH HARGA
BOBOT
(%)

I PEKERJAAN PERSIPAN Rp 17,815,000.00 0.43

II KONSTRUKSI PEKERJAAN SALURAN DAN

BANGUNAN PELENGKAP

- PEKERJAAN SALURAN DRAINASE Rp 3,967,888,159.25 94.92

- BANGUNAN PLAT DEUKER/BOX CULVERT Rp 84,158,661.88 2.01


- PEKERJAAN BANGUNAN PELENGKAP Rp 90,924,063.53 2.17

- PEKERJAAN KOLAM OLAKAN Rp 19,668,084.40 0.47

JUMLAH Rp 4,180,453,969.06 100.00


PPN 10 % Rp 418,045,396.91
TOTAL NILAI Rp 4,598,499,365.97
PEMBULATAN Rp 4,598,490,000.00
Minggu ini
Sampai dengan Minggu
Sampai dengan Minggu
Rencana sampai denga
Deviasi

Mengetahui / Menyetujui : Disetujui Oleh : Diketah


PPK Pengembangan Sistem PLP I Direksi Teknis Kontrakto
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT PT. BAHANA K

Tinny Touselak, ST, MT Indri M. Susetyo, ST Septian M


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
JUAN PEKERJAAN MINGGUAN

s/d 01 April 2018

BOBOT PRESTASI YANG DICAPAI (%)


S/D KET
MINGGU JUMLAH S/D
MINGGU
INI MINGGU INI
LALU

0.02 0.08 0.10

- 0.00 0.00

- 0.00 0.00
- 0.00 0.00

- 0.00 0.00

0.02 0.08 0.10 %


0.08 %
Sampai dengan Minggu Lalu 0.02 %
Sampai dengan Minggu ini 0.10 %
Rencana sampai dengan minggu ini 0.59 %
-0.49 %

Ende, 30 Maret 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


Pelaksana Site Engineering
PROGRES KEMAJUAN PEK

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN NUSA TENGGARA TIMU
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE
TAHUN ANGGARAN : 2018

KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan Ls 1.00 12,815,000.00
Mobilisasi Dan Demobilisasi Ls 1.00 5,000,000.00
Jumlah Total I

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
Pekerjaan Galian Tanah
- Galian Tanah Biasa M3 1,152.11 48,335.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Galian Batu M3 768.07 98,795.00
- Timbunan Tanah Termasuk Pemadatan M3 576.06 43,758.00
Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')
- Pekerjaan Rabat Lantai dasar Saluran m³ 21.02 1,010,463.00
- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast) buah 473.00 1,990,119.00
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100) buah 378.00 1,081,619.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600 unit 94.00 867,943.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 17.03 71,105.00
- Pekerjaan Pasangan Batu m3 7.78 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 40.00 28,333.33

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran m³ 37.70 1,010,463.00
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast) buah 628.00 2,536,369.00
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100) buah 502.00 1,167,869.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800 unit 125.00 885,979.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 30.14 71,105.00
- Pekerjaan Pasangan Batu m3 21.00 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 50.00 28,333.33
Jumlah Total A
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

BANGUNAN PLAT DEUKER/BOX CULVERT


Pekerjaan Galian Tanah
- Galian Tanah Biasa m3 12.96 48,335.00
- Galian Batu m3 8.64 98,795.00
- Timbunan Tanah Termasuk Pemadatan m3 6.48 43,758.00
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran m³ 0.90 1,010,463.00
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200 buah 15.00 5,089,491.00
- Pekerjaan Pasangan Batu m³ 5.23 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 10.04 71,105.00
- Acian m2 10.04 31,951.00
Jumlah Total B

PEKERJAAN BANGUNAN PELENGKAP


Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12 M3 1,304.05 15,118.65
- Beton Mutu K-200 M3 44.00 1,618,377.00
Jumlah Total C
PEKERJAAN KOLAM OLAKAN
Pekerjaan Kolam Olakan
- Galian Tanah Biasa m3 15.00 48,355.00
- Galian Batu m3 7.00 98,795.00
- Pasangan Batu (Campuran 1 PC : 4 PP) m³ 2.45 785,590.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Plesteran (Campuran 1 PC : 3 PP) m2 5.76 71,105.00
- Acian m2 5.76 31,951.00
Jumlah Total D
Jumlah Total D * 5 UNIT

A. J U M L A H

B. PAJAK PERTAMBAHAN NILAI (PPN ) = 10% x A

C. JUMLAH TOTOL HARGA PENAWARAN = A + B

JUMLAH DIBULATKAN

Mengetahui / Menyetujui : Disetujui Oleh :


PPK Pengembangan Sistem PLP I Direksi Teknis
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT

Tinny Touselak, ST, MT Indri M. Susetyo, ST


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
UAN PEKERJAAN MINGGUAN

GGARA TIMUR MINGGU KE : (IV) EMPAT


TANGGAL : 02 April 2018 s/d 08 April 2018

REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

12,815,000.00 0.31 0.25 0.08 0.20 0.06 0.45 0.14 45.00


5,000,000.00 0.12 0.20 0.02 - 0.20 0.02 20.00
17,815,000.00 0.43 0.10 0.06 0.16

55,687,344.35 1.33 - - - - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

75,881,951.45 1.82 - - - - - -
25,207,063.35 0.60 - - - - - -

21,235,890.41 0.51 - - - - - -
941,326,287.00 22.52 - - - - - -
408,851,982.00 9.78 - - - - - -
81,586,642.00 1.95 - - - - - -
1,210,775.94 0.03 - - - - - -
6,108,747.84 0.15 - - - - - -
568,840.00 0.01 - - - - - -
255,608.00 0.01 - - - - - -
1,133,333.20 0.03 - - - - - -

38,094,455.10 0.91 - - - - - -
1,592,839,732.00 38.10 - - - - - -
586,270,238.00 14.02 - - - - - -
110,747,375.00 2.65 - - - - - -
2,143,389.12 0.05 - - - - - -
16,497,390.00 0.39 - - - - - -
568,840.00 0.01 - - - - - -
255,608.00 0.01 - - - - - -
1,416,666.50 0.03 - - - - - -
3,967,888,159.25 94.92 - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

626,421.60 0.01 - - - - - -
853,588.80 0.02 - - - - - -
283,551.84 0.01 - - - - - -

909,416.70 0.02 - - - - - -
76,342,365.00 1.83 - - - - - -
4,108,635.70 0.10 - - - - - -
713,894.20 0.02 - - - - - -
320,788.04 0.01 - - - - - -
84,158,661.88 2.01 - - -

19,715,475.53 0.47 - - - - - -
71,208,588.00 1.70 - - - - - -
90,924,063.53 2.17 - - -

725,325.00 0.02 - - - - - -
691,565.00 0.02 - - - - - -
1,923,124.32 0.05 - - - - - -
REALISASI PEKERJAAN
KONTRAK
Minggu Lalu Minggu ini Sampai dengan minggu ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

409,564.80 0.01 - - - - - -
184,037.76 0.00 - - - - - -
3,933,616.88 0.09 - - -
19,668,084.40 0.47 - - -

4,180,453,969.06 100.00 0.10 0.06 0.16

418,045,396.91

4,598,499,365.97

4,598,490,000.00

Ende, 05 April 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
P-NTT PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


2 056 PELAKSANA Site Engineering
REKAPITULASI KEMAJUAN PEKERJAAN MINGGUAN
Mengetahui/Menyetujui :
Konsultan Pengawas
CV. NUSA PRATAMA KONSULT
JO
SATUAN KERJA : PENGEMBANGAN SISTEM
PT. ARGA PASCALINGKUNGAN
PENYEHATAN RENCANA PERMUKIMAN NUSA TENGGARA TIMUR
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE MINGGU KE : (IV) EMPAT
TAHUN ANGGARAN : 2018 TANGGAL : 02 April 2018
DANIEL FREDRIK MARO, SP
Direktur

B
NO JENIS PEKERJAAN JUMLAH HARGA
BOBOT
(%)

I PEKERJAAN PERSIPAN Rp 17,815,000.00 0.43

II KONSTRUKSI PEKERJAAN SALURAN DAN

BANGUNAN PELENGKAP

- PEKERJAAN SALURAN DRAINASE Rp 3,967,888,159.25 94.92

- BANGUNAN PLAT DEUKER/BOX CULVERT Rp 84,158,661.88 2.01


- PEKERJAAN BANGUNAN PELENGKAP Rp 90,924,063.53 2.17

- PEKERJAAN KOLAM OLAKAN Rp 19,668,084.40 0.47

JUMLAH Rp 4,180,453,969.06 100.00


PPN 10 % Rp 418,045,396.91
TOTAL NILAI Rp 4,598,499,365.97
PEMBULATAN Rp 4,598,490,000.00
Minggu ini
Sampai dengan Minggu
Sampai dengan Minggu
Rencana sampai denga
Deviasi

Mengetahui / Menyetujui : Disetujui Oleh : Diketah


PPK Pengembangan Sistem PLP I Direksi Teknis Kontrakto
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT PT. BAHANA K

Tinny Touselak, ST, MT Indri M. Susetyo, ST Septian M


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
JUAN PEKERJAAN MINGGUAN

(IV) EMPAT
s/d 08 April 2018

BOBOT PRESTASI YANG DICAPAI (%)


S/D KET
MINGGU JUMLAH S/D
MINGGU
INI MINGGU INI
LALU

0.10 0.06 0.16

- 0.00 0.00

- 0.00 0.00
- 0.00 0.00

- 0.00 0.00

0.10 0.06 0.16 %


0.06 %
Sampai dengan Minggu Lalu 0.10 %
Sampai dengan Minggu ini 0.16 %
Rencana sampai dengan minggu ini 0.90 %
-0.74 %

Ende, 05 April 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Septian Maulana, ST Ferry F. Pandie, ST


Pelaksana Site Engineering
PROGRES KEMAJUAN PE

SATUAN KERJA : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN NUSA TENGGARA TIMU
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE
TAHUN ANGGARAN : 2018

KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan Ls 1.00 12,815,000.00
Mobilisasi Dan Demobilisasi Ls 1.00 5,000,000.00
Jumlah Total I

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
Pekerjaan Galian Tanah
- Galian Tanah Biasa M3 1,152.11 48,335.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Galian Batu M3 768.07 98,795.00
- Timbunan Tanah Termasuk Pemadatan M3 576.06 43,758.00
Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')
- Pekerjaan Rabat Lantai dasar Saluran m³ 21.02 1,010,463.00
- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast) buah 473.00 1,990,119.00
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100) buah 378.00 1,081,619.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600 unit 94.00 867,943.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 17.03 71,105.00
- Pekerjaan Pasangan Batu m3 7.78 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 40.00 28,333.33

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran m³ 37.70 1,010,463.00
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast) buah 628.00 2,536,369.00
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100) buah 502.00 1,167,869.00
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800 unit 125.00 885,979.00
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter m2 30.14 71,105.00
- Pekerjaan Pasangan Batu m3 21.00 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 8.00 71,105.00
- Acian m2 8.00 31,951.00
- Pekerjaan Pipa Drain m1 50.00 28,333.33
Jumlah Total A
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)

BANGUNAN PLAT DEUKER/BOX CULVERT


Pekerjaan Galian Tanah
- Galian Tanah Biasa m3 12.96 48,335.00
- Galian Batu m3 8.64 98,795.00
- Timbunan Tanah Termasuk Pemadatan m3 6.48 43,758.00
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran m³ 0.90 1,010,463.00
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200 buah 15.00 5,089,491.00
- Pekerjaan Pasangan Batu m³ 5.23 785,590.00
- Plesteran (Campuran 1 PC : 3 PP) m2 10.04 71,105.00
- Acian m2 10.04 31,951.00
Jumlah Total B

PEKERJAAN BANGUNAN PELENGKAP


Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12 M3 1,304.05 15,118.65
- Beton Mutu K-200 M3 44.00 1,618,377.00
Jumlah Total C
PEKERJAAN KOLAM OLAKAN
Pekerjaan Kolam Olakan
- Galian Tanah Biasa m3 15.00 48,355.00
- Galian Batu m3 7.00 98,795.00
- Pasangan Batu (Campuran 1 PC : 4 PP) m³ 2.45 785,590.00
KONTRAK
URAIAN PEKERJAAN SAT.
HARGA SATUAN
VOLUME
(Rp)
- Plesteran (Campuran 1 PC : 3 PP) m2 5.76 71,105.00
- Acian m2 5.76 31,951.00
Jumlah Total D
Jumlah Total D * 5 UNIT

A. J U M L A H

B. PAJAK PERTAMBAHAN NILAI (PPN ) = 10% x A

C. JUMLAH TOTOL HARGA PENAWARAN = A + B

JUMLAH DIBULATKAN

Mengetahui / Menyetujui : Disetujui Oleh :


PPK Pengembangan Sistem PLP I Direksi Teknis
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT

Tinny Touselak, ST, MT Indri M. Susetyo, ST


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
UAN PEKERJAAN BULANAN

GGARA TIMUR BULAN KE : (I) SATU


TANGGAL : 12 Maret 2018 s/d 08 April 2018

REALISASI PEKERJAAN
KONTRAK
Bulan Lalu Bulan Ini Sampai dengan bulan ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

12,815,000.00 0.31 0.45 0.14 0.45 0.14 45.00


5,000,000.00 0.12 0.20 0.02 0.20 0.02 20.00
17,815,000.00 0.43 - 0.16 0.16

55,687,344.35 1.33 - - - - -
REALISASI PEKERJAAN
KONTRAK
Bulan Lalu Bulan Ini Sampai dengan bulan ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

75,881,951.45 1.82 - - - - -
25,207,063.35 0.60 - - - - -

21,235,890.41 0.51 - - - - -
941,326,287.00 22.52 - - - - -
408,851,982.00 9.78 - - - - -
81,586,642.00 1.95 - - - - -
1,210,775.94 0.03 - - - - -
6,108,747.84 0.15 - - - - -
568,840.00 0.01 - - - - -
255,608.00 0.01 - - - - -
1,133,333.20 0.03 - - - - -

38,094,455.10 0.91 - - - - -
1,592,839,732.00 38.10 - - - - -
586,270,238.00 14.02 - - - - -
110,747,375.00 2.65 - - - - -
2,143,389.12 0.05 - - - - -
16,497,390.00 0.39 - - - - -
568,840.00 0.01 - - - - -
255,608.00 0.01 - - - - -
1,416,666.50 0.03 - - - - -
3,967,888,159.25 94.92 - - -
REALISASI PEKERJAAN
KONTRAK
Bulan Lalu Bulan Ini Sampai dengan bulan ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

626,421.60 0.01 - - - - -
853,588.80 0.02 - - - - -
283,551.84 0.01 - - - - -

909,416.70 0.02 - - - - -
76,342,365.00 1.83 - - - - -
4,108,635.70 0.10 - - - - -
713,894.20 0.02 - - - - -
320,788.04 0.01 - - - - -
84,158,661.88 2.01 - - -

19,715,475.53 0.47 - - - - -
71,208,588.00 1.70 - - - - -
90,924,063.53 2.17 - - -

725,325.00 0.02 - - - - -
691,565.00 0.02 - - - - -
1,923,124.32 0.05 - - - - -
REALISASI PEKERJAAN
KONTRAK
Bulan Lalu Bulan Ini Sampai dengan bulan ini PRESENTASI
PEKERJAAN (%)
JUMLAH HARGA (Rp) BOBOT % Volume Bobot (%) Volume Bobot (%) Volume Bobot (%)

409,564.80 0.01 - - - - -
184,037.76 0.00 - - - - -
3,933,616.88 0.09 - - -
19,668,084.40 0.47 - - -

4,180,453,969.06 100.00 - 0.16 0.16

418,045,396.91

4,598,499,365.97

4,598,490,000.00

Ende, 05 April 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
P-NTT PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Andry Y. Berry, ST Ferry F. Pandie, ST


2 056 Kepala Proyek Site Engineering
REKAPITULASI KEMAJUAN PEKERJAAN BULANAN
Mengetahui/Menyetujui :
Konsultan Pengawas
CV. NUSA PRATAMA KONSULT
JO
SATUAN KERJA : PENGEMBANGAN SISTEM
PT. ARGA PASCALINGKUNGAN
PENYEHATAN RENCANA PERMUKIMAN NUSA TENGGARA TIMUR
PEKERJAAN : PENGAWASAN PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
LOKASI : KOTA ENDE KABUPATEN ENDE BULAN KE : (I) SATU
TAHUN ANGGARAN : 2018 TANGGAL : 12 Maret 2018
DANIEL FREDRIK MARO, SP
Direktur

B
NO JENIS PEKERJAAN JUMLAH HARGA
BOBOT
(%)

I PEKERJAAN PERSIPAN Rp 17,815,000.00 0.43

II KONSTRUKSI PEKERJAAN SALURAN DAN

BANGUNAN PELENGKAP

- PEKERJAAN SALURAN DRAINASE Rp 3,967,888,159.25 94.92

- BANGUNAN PLAT DEUKER/BOX CULVERT Rp 84,158,661.88 2.01


- PEKERJAAN BANGUNAN PELENGKAP Rp 90,924,063.53 2.17

- PEKERJAAN KOLAM OLAKAN Rp 19,668,084.40 0.47

JUMLAH Rp 4,180,453,969.06 100.00


PPN 10 % Rp 418,045,396.91
TOTAL NILAI Rp 4,598,499,365.97
PEMBULATAN Rp 4,598,490,000.00
Bulan Ini
Sampai dengan BUlan Lal
Sampai dengan Bulan ini
Rencana sampai dengan
Deviasi

Mengetahui / Menyetujui : Disetujui Oleh : Diketah


PPK Pengembangan Sistem PLP I Direksi Teknis Kontrakto
SATUAN KERJA PSPLP-NTT SATUAN KERJA PSPLP-NTT PT. BAHANA K

Tinny Touselak, ST, MT Indri M. Susetyo, ST Andry Y


NIP. 19841023 200903 2 002 NIP :19850510 201001 2 056
JUAN PEKERJAAN BULANAN

s/d 08 April 2018

BOBOT PRESTASI YANG DICAPAI (%)

S/D BULAN JUMLAH S/D KET


BULAN INI
LALU BULAN INI

- 0.16 0.16

- 0.00 0.00

- 0.00 0.00
- 0.00 0.00

- 0.00 0.00

0.00 0.16 0.16 %


0.16 %
Sampai dengan BUlan Lalu 0.00 %
Sampai dengan Bulan ini 0.16 %
Rencana sampai dengan Bulan ini 0.90 %
-0.74 %

Ende, 05 April 2018


Diketahui Oleh : Dibuat Oleh :
Kontraktor Pelaksana Konsultan Pengawas
PT. BAHANA KRIDA NUSANTARA CV. SABA CONSULT

Andry Y. Berry, ST Ferry F. Pandie, ST


Pelaksana Site Engineering
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator - -
3. Buldozer 15 ton - -
4. Vibro Compactor - -
5. Wheel Loader - -
6. Dump Truck 2 2
7. Three Wheel Roller - -
8. Asphalt Sprayer - -
9. Water Tank Truck - -
10. Concrete Mixer - -
11. Concrete Vibrator - -
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane - -

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIA
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

BANGUNAN PLAT DEUKER/BOX CU


Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian

IV. Peralatan
Peralatan Jumlah Operasi Idle Keteranga
1. Excavator 1 1
2. Breaker Excavator
3. Buldozer 15 ton
4. Vibro Compactor
5. Wheel Loader
6. Dump Truck 2 2
7. Three Wheel Roller
8. Asphalt Sprayer
9. Water Tank Truck
10. Concrete Mixer
11. Concrete Vibrator
12. Peralatan Ukur : T0 /WP 3 3
13. Mobil Crane

VI. Cuaca

1. Cerah √ 3. Hujan Gerim


2. Mendung 4. Hujan Dera
VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Superv

HESRON I. MONE, ST
Nip. - Inspektor
ORAN HARIAN
Tanggal : 12-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 13-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 14-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 15-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 16-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 17-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 18-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
- 1. Kepala Proyek 1
- 2. Kepala Pelaksana -
- 3. Pembantu Pelaksana -
- 4. Logistik -
- 5. Mandor 1
- 6. Tukaang 4
- 7. Pekerja 13
- 8. Sopir 2
- 9. Pembantu Sopir -
- 10. Operator 1
- 11. Surveyor -
-
-
-

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal : 18-Maret-2018
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan

L
I
B
U
R

V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
1. Kepala Proyek 1
2. Kepala Pelaksana
3. Pembantu Pelaksana
4. Logistik
5. Mandor 1
6. Tukaang 4
7. Pekerja 13
8. Sopir 2
9. Pembantu Sopir
10. Operator 1
11. Surveyor -

3. Hujan Gerimis Jam07.00s/d17.00


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
LAPORAN HARIAN
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak
No. Addendum - I
Kontraktor
Konsultan Pengawas
II. Kegiatan
No. Uraian kegiatan Volume Sat.
PEKERJAAN PERSIPAN
Mobilisasi, Demobilisasi
Pengukuran Ulang Uitzet, Papan Nama, Dokumentasi dan Pelaporan
Mobilisasi Dan Demobilisasi

KONSTRUKSI PEKERJAAN SALURAN DAN


BANGUNAN PELENGKAP
PEKERJAAN SALURAN DRAINASE
PEKERJAAN SALURAN DRAINASE
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan

Pekerjaan Drainase Mengunakan U-Gutter (P . 567,60 M')


- Pasang U - Gutter 600x600x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 60.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 600
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain

Pekerjaan Drainase Mengunakan U-Gutter (P . 753,60 M')


- Pekerjaan Rabat Lantai dasar Saluran
- Pasang U - Gutter 800x800x1200x10 cm (Saluran Pre-Cast)
- Pasang Cover Cu 80.10.120(Cover Uk. 800x1200 x100)
- Pas.Gril Besi penutup Saluran (Siku 70.70.7 dan Besi D Ø 13 mm) uk 800
- Pekerjaan Spesi/Plesteran Sambungan Antar U-Gutter
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
- Pekerjaan Pipa Drain
BANGUNAN PLAT DEUKER/BOX CU
Pekerjaan Galian Tanah
- Galian Tanah Biasa
- Galian Batu
- Timbunan Tanah Termasuk Pemadatan
Pekerjaan Pasangan Box Culvert
- Pekerjaan Rabat Lantai dasar Saluran
- Pasang Box Culvert Monolith Heavy Duty 1000x1000x1200
- Pekerjaan Pasangan Batu
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
PEKERJAAN BANGUNAN PELENGKAP
Pekerjaan Perlintasan Ke Rumah Warga
- Pembesian Besi ᴓ 12
- Beton Mutu K-200

PEKERJAAN KOLAM OLAKAN


Pekerjaan Kolam Olakan
- Galian Tanah Biasa
- Galian Batu
- Pasangan Batu (Campuran 1 PC : 4 PP)
- Plesteran (Campuran 1 PC : 3 PP)
- Acian
IV. Peralatan
Peralatan Jumlah Operasi Idle Keterangan
1. Excavator
2. Breaker Excavator
3. Buldozer 15 ton
4. Vibro Compactor
5. Wheel Loader
6. Dump Truck
7. Three Wheel Roller
8. Asphalt Sprayer
9. Water Tank Truck
10. Concrete Mixer
11. Concrete Vibrator
12. Peralatan Ukur : T0 /WP
13. Mobil Crane

VI. Cuaca
1. Cerah 3. Hujan Gerimis
2. Mendung 4. Hujan Deras

VII. Informasi lain / Instruksi


Disetujui Oleh : Diperiksa Oleh
DIreksi Lapangan Konsultan / Supervisi

HESRON I. MONE, ST
Nip. - Inspektor
LOGO PERUSAHAAN

LAPORAN HARIAN
I. Data Pekerjaan
Satuan kerja PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN PERMUKIMAN PROV. NTT
Pekerjaan PEMBANGUNAN DRAINASE KAWASAN PERMUKIMAN KOTA ENDE
No. Kontrak 0
No. Addendum - I
No. Addendum - II
Kontraktor 12/30/1899
Konsultan Pengawas 0
II. Kegiatan
No. Uraian kegiatan Volume Sat.

IV. Peralatan
Peralatan Jumlah Operasi Idle Keterangan
1. Excavator
2. Breaker Excavator
3. Buldozer 15 ton
4. Vibro Compactor
5. Wheel Loader
6. Dump Truck
7. Three Wheel Roller
8. Asphalt Sprayer
9. Water Tank Truck
10. Concrete Mixer
11. Concrete Vibrator
12. Peralatan Ukur : T0 /WP
13. Mobil Crane

VI. Cuaca

1. Cerah 3. Hujan Gerimis


2. Mendung 4. Hujan Deras

VII. Informasi lain / Instruksi

Disetujui Oleh : Diperiksa Oleh


DIreksi Lapangan Konsultan / Supervisi

HESRON I. MONE, ST
Nip. Site Enginner
ORAN HARIAN
Tanggal :
Lokasi Pekerjaan : ONEKORE
Kabupaten : ENDE

Jangka Waktu Pelaksanaan 210 Hk


No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan
V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
1. Kepala Proyek
2. Kepala Pelaksana
3. Pembantu Pelaksana
4. Logistik
5. Mandor
6. Tukaang
7. Pekerja
8. Sopir
9. Pembantu Sopir
10. Operator
11. Surveyor

3. Hujan Gerimis Jam …………….s/d ……………


4. Hujan Deras Jam …………….s/d ……………
Diperiksa Oleh Dibuat Oleh
Konsultan / Supervisi Kontraktor Pelaksana

Inspektor Pelaksana
ORAN HARIAN
Tanggal :
Lokasi Pekerjaan : KOTA LEWOLEBA
Kabupaten : LEMBATA

Jangka Waktu Pelaksanaan 210 Hk

No.

III. Bahan Yang Digunakan


Keterangan No. Jenis Bahan Volume Sat. Keterangan

V. Tenaga Kerja
Keterangan Uraian Jumlah Keterangan
1. Kepala Proyek
2. Kepala Pelaksana
3. Pembantu Pelaksana
4. Logistik
5. Mandor
6. Tukaang
7. Pekerja
8. Sopir
9. Pembantu Sopir
10. Operator
11. Surveyor

3. Hujan Gerimis Jam …………….s/d ……………


4. Hujan Deras Jam …………….s/d ……………

Diperiksa Oleh Dibuat Oleh


Konsultan / Supervisi Kontraktor Pelaksana

Site Enginner Kepala Proyek