3. What is SAES-H-001?
Coating Selection and Application Requirements for Industrial Plants and Equipment.
4. What is SAES-H-002?
Internal and External Coatings for Steel Pipelines and Piping.
5. What is SAES-H-100?
Coating Materials & Application Requirements for Industrial Facilities.
9. What do you call application of paint on weld lines, edges, bolts, nuts and rivets ?
Stripe coat
12. What is the method of measurement of Dry Paint Thickness with Magnetic
Gages?
SSPC-PA 2
13. From where we can get required coating thickness for any coating system?
From Approved Saudi Aramco Data Sheet or Paint Manufacture Data Sheet
14. What is the paint defects?
Non-Dry film
- Adding wrong cure
- Not adding correct amount of cure.
Blushing
- Cool ambient temp
- High humidity
Holiday
- Poor application
Chalking
- Exposure to UV light.
Pinhole
- Air or solvent.
Orang peel
- Hot air.
- Improper application.