Power Supply :

1. Air Compressor (for Pneumatic Actuator)


2. Hydraulic Power Unit (for Hydraulic Actuator)
Control Valve :

1. Pneumatic Actuator
List of testing :
 Modulating Valve :
o Hand wheel test
o Calibration (Linearity six step gradation)
o Continuity and Megger test (Power Cable, Instrument & Control Cable)
o Tubing test (leakage) and its connection
o Loop test (Instrument & Control Cable)
o Function test (including to ensure that the indication in the DCS and local is correct)
 On/Off Valve :
o Hand wheel test
o Calibration (Linearity full open / full close)
o Continuity and Megger test (Power Cable, Instrument & Control Cable)
o Tubing test (leakage) and its connection
o Loop test (Instrument & Control Cable)
o Function test (including to ensure that the indication in the DCS and local is correct)
2. Hydraulic Actuator
List of testing :
 Modulating Valve :
o Hand Pump test
o Calibration (Linearity six step gradation)
o Continuity and Megger test (Power Cable, Instrument & Control Cable)
o Tubing test (leakage) and its connection
o Loop test (Instrument & Control Cable)
o Function test (including to ensure that the indication in the DCS and local is correct)
 On/Off Valve :
o Hand Pump test
o Calibration (Linearity full open / full close)
o Continuity and Megger test (Power Cable, Instrument & Control Cable)
o Tubing test (leakage) and its connection
o Loop test (Instrument & Control Cable)
o Function test (including to ensure that the indication in the DCS and local is correct)
3. Electric Actuator
List of testing :
 Modulating Valve :
o Hand Wheel test
o Calibration (Linearity six step gradation)
o Continuity and Megger test (Power Cable, Instrument & Control Cable)
o Loop test (Instrument & Control Cable)
o Function test (including to ensure that the indication in the DCS and local is correct)
 On/Off Valve :
o Hand Wheel test
o Calibration (Linearity full open / full close)
o Continuity and Megger test (Power Cable, Instrument & Control Cable)
o Loop test (Instrument & Control Cable)
o Function test (including to ensure that the indication in the DCS and local is correct)