Q. 1

MY PROFILE In cements, generally the increase in strength after 28 days


is primarily due to
REPORTS Have any Doubt ?

BUY PACKAGE A
C3A
ASK AN EXPERT

B
OFFER
C2S
Your answer is Correct
EXCLUSIVE OFFER FOR OTS
STUDENTS ONLY ON BOOK
PACKAGES Solution :
(b)

C
C3S

D
C4AF

QUESTION ANALYTICS

Q. 2
https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 1/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Which of the following is INCORRECT?


Venkateswarlu Marri 
Have any Doubt ?
(Enroll User) Sign out

A
Pozzolana improves workability with lesser amount of wat

B
Pozzolana increases the resistance of concrete to attack b
Venkateswarlu Marri
Course: GATE C
Civil Engineering (CE)
Ultrasonic pulse velocity test is used to measure dynamic

HOME
D
Curing of concrete by steam under pressure decreases the
MY TEST Your answer is Correct

BOOKMARKS
Solution :
(d)
MY PROFILE

REPORTS QUESTION ANALYTICS

BUY PACKAGE

Q. 3
ASK AN EXPERT
Two coplanar couples having equal and opposite moments
OFFER FAQ Have any Doubt ?

EXCLUSIVE OFFER FOR OTS A


STUDENTS ONLY ON BOOK
can balance each other
PACKAGES
Correct Option

Solution :
(a)

B
produce a couple and an unbalanced force

C
produce a moment of couple
Your answer is Wrong

D
can not balance each other
https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 2/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
(Enroll User)
QUESTION ANALYTICS Sign out

Q. 4

The total project duration for the following A-O-N (activity


on node) network is

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST

BOOKMARKS FAQ Have any Doubt ?

MY PROFILE A
34 days
REPORTS

B
BUY PACKAGE
25 days

ASK AN EXPERT
C
OFFER 36 days
Your answer is Correct
EXCLUSIVE OFFER FOR OTS
STUDENTS ONLY ON BOOK
Solution :
PACKAGES
(c)

D
38 days

QUESTION ANALYTICS

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 3/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
Q. 5
(Enroll User) Sign out
During the CPM updating process
Have any Doubt ?

A
critical path will remain same but duration will change.

Venkateswarlu Marri B
Course: GATE
critical path may change along with duration
Civil Engineering (CE) Correct Option

HOME Solution :
(b)
MY TEST

C
BOOKMARKS
critical path will remain same along with same duration.
Your answer is Wrong
MY PROFILE

REPORTS D
None of the above
BUY PACKAGE

QUESTION ANALYTICS
ASK AN EXPERT

OFFER
Q. 6
EXCLUSIVE OFFER FOR OTS
STUDENTS ONLY ON BOOK A container is filled with a sample of sand. The sand height
PACKAGES is measured as 200 mm. The sand is then taken out of the
container and the container is filled with water. The sand is
then slowly dropped in the container. Now if the height of
sand is measured as 160 mm, then bulking of sand will be
________ %.
FAQ Have any Doubt ?

25
Correct Option

Solution :
25

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 4/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
(Enroll User) Sign out
Your Answer is 20

QUESTION ANALYTICS

Q. 7
Venkateswarlu Marri
Variance for a given project is unity. If under most ideal
Course: GATE
conditions, the project can be completed in 4 days, then
Civil Engineering (CE)
the maximum time required (pessimistic time) to complete
the project is ______ days.
HOME Have any Doubt ?

MY TEST
10
Your answer is Correct10
BOOKMARKS

MY PROFILE Solution :
10

REPORTS

BUY PACKAGE

ASK AN EXPERT

OFFER

EXCLUSIVE OFFER FOR OTS


STUDENTS ONLY ON BOOK
PACKAGES

QUESTION ANALYTICS

Q. 8

In an experiment with simple pendulum, it was found that it


took 53 sec to complete 24 oscillations when the effective
length was 120 cm. From this data, the acceleration due to
gravity (in m/s2) will be ________.
Have any Doubt ?

9.717 (9.6 - 9.8)


Correct Option

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 5/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Solution :
Venkateswarlu Marri 
9.717 (9.6 - 9.8)
(Enroll User) Sign out

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST Your Answer is 0.01686

BOOKMARKS
QUESTION ANALYTICS

MY PROFILE

REPORTS Q. 9

BUY PACKAGE A particle moves in a circle of radius 50 cm. Its linear


speed is given by V = 3t2  – 6t, where ‘t’ is in second and ‘V’
is in metre/second. At t = 4 sec, the radial acceleration (in
ASK AN EXPERT
m/s2) is _______.
Have any Doubt ?
OFFER

EXCLUSIVE OFFER FOR OTS


STUDENTS ONLY ON BOOK 1152 (1150 - 1154)
PACKAGES Your answer is Correct1152

Solution :
1152 (1150 - 1154)

QUESTION ANALYTICS

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 6/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
Q. 10 (Enroll User) Sign out

Match List-I (Disease of timber) with List-II (Effect of


disease) and select the correct answer using the codes
given below the lists:

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST

BOOKMARKS
FAQ Have any Doubt ?

MY PROFILE
A
a
REPORTS

BUY PACKAGE B
b
ASK AN EXPERT

C
OFFER
c
EXCLUSIVE OFFER FOR OTS
STUDENTS ONLY ON BOOK
PACKAGES D
d
Correct Option

Solution :
(d)

QUESTION ANALYTICS

Q. 11

Network is drawn using the following data : A and B are


starting activities, and takes 8 and 4 days respectively for
completion. Activity C follows B; D follows A and C; D is the
finishing activity. Activity C and D takes 10 and 6 days
https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 7/14
2/11/2019 MADE EASY ONLINE TEST SERIES

respectively for completion. The time required for


completion of project is
Venkateswarlu Marri 
(Enroll User) Have any Doubt ?
Sign out

A
14 days

B
18 days
Venkateswarlu Marri
Course: GATE
Civil Engineering (CE) C
20 days
Your answer is Correct
HOME

Solution :
MY TEST
(c)

BOOKMARKS

MY PROFILE

REPORTS

BUY PACKAGE

ASK AN EXPERT

OFFER
D
EXCLUSIVE OFFER FOR OTS 22 days
STUDENTS ONLY ON BOOK
PACKAGES
QUESTION ANALYTICS

Q. 12

The resultant ‘R’ and angle of resultant ‘ ’ for the given


force system respectively are

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 8/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Have any Doubt ?


Venkateswarlu Marri 
(Enroll User) Sign out
A
190.58 kN, 43°39′
Correct Option

Solution :
(a)

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST

BOOKMARKS

MY PROFILE B
138.13 kN, 72°14′
REPORTS

BUY PACKAGE C
166.43 kN, 47°51′
ASK AN EXPERT
D
OFFER 190.58 kN, 72°14′
Your answer is Wrong
EXCLUSIVE OFFER FOR OTS
STUDENTS ONLY ON BOOK
PACKAGES QUESTION ANALYTICS

Q. 13

For a research project the duration of the project is


calculated as 130 weeks with the variance of 25 weeks.
The number of weeks required to complete the project with
95%, probability is ________ weeks. [Take probability factor
corresponding to 95% probability as 1.647]
Have any Doubt ?

138.235 (135 - 140)


Your answer is Correct138.235

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 9/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Solution :
138.235 (135 -Venkateswarlu
140) Marri 
(Enroll User) Sign out

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME
QUESTION ANALYTICS

MY TEST

BOOKMARKS Q. 14

Consider the following particulars in respect of a concrete


MY PROFILE mix design :

REPORTS

BUY PACKAGE

ASK AN EXPERT
The weight of the coarse aggregates shall be _______
OFFER kg/m3.
FAQ Have any Doubt ?
EXCLUSIVE OFFER FOR OTS
STUDENTS ONLY ON BOOK
PACKAGES
852.15 (850 - 855)
Your answer is Correct852.15

Solution :
852.15 (850 - 855)

QUESTION ANALYTICS

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 10/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
Q. 15
(Enroll User) Sign out
Consider the following data regarding an activity AB :
Earliest start time = 3 days
Earliest finish time = 8 days
Latest start time = 5 days
Latest finish time = 10 days
Then interferring float for this activity is ________ days.
Have any Doubt ?
Venkateswarlu Marri
Course: GATE
Civil Engineering (CE) 2
Your answer is Correct2
HOME
Solution :
2
MY TEST

BOOKMARKS

MY PROFILE

REPORTS

BUY PACKAGE

ASK AN EXPERT

OFFER

EXCLUSIVE OFFER FOR OTS


STUDENTS ONLY ON BOOK
PACKAGES
QUESTION ANALYTICS

Q. 16

A block of mass 5 kg placed on a horizontal surface is


being pushed by a force making an angle of 45° with the
vertical. If the friction coefficient is 0.25, the force (in
Newton) needed to get the block just started is ________.
Have any Doubt ?

23.126 (22.5 - 24)


Correct Option

Solution :
https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 11/14
2/11/2019 MADE EASY ONLINE TEST SERIES
Solution :
23.126 (22.5 - 24)
Venkateswarlu Marri 
(Enroll User) Sign out

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST

BOOKMARKS

MY PROFILE

REPORTS

BUY PACKAGE

ASK AN EXPERT Your Answer is 13.87

OFFER QUESTION ANALYTICS

EXCLUSIVE OFFER FOR OTS


STUDENTS ONLY ON BOOK
PACKAGES
Q. 17

For the given cross-section, the moment of inertia of the


section about vertical axis passing through the centroid of
the section is ___________ × 106 mm4.

FAQ Have any Doubt ?

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 12/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
20.89 (20.52 - 21.5)
(Enroll User) Sign out
Correct Option

Solution :
20.89 (20.52 - 21.5)

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST

BOOKMARKS

MY PROFILE

REPORTS

BUY PACKAGE

ASK AN EXPERT

OFFER

EXCLUSIVE OFFER FOR OTS


STUDENTS ONLY ON BOOK
PACKAGES

Your Answer is 17.3837

QUESTION ANALYTICS
https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 13/14
2/11/2019 MADE EASY ONLINE TEST SERIES

Venkateswarlu Marri 
(Enroll User) Sign out

Venkateswarlu Marri
Course: GATE
Civil Engineering (CE)

HOME

MY TEST

BOOKMARKS

MY PROFILE

REPORTS

BUY PACKAGE

ASK AN EXPERT

OFFER

EXCLUSIVE OFFER FOR OTS


STUDENTS ONLY ON BOOK
PACKAGES

https://onlinetestseriesmadeeasy.in/madeeasy/index.php?pageName=timeManagementReport&testid=993&t=a&testType=2 14/14

You might also like