tiempo de procesamiento en horas

Puestos de trabajo A B C D E F
H-1 8 10 14 5 9 14
H-2 13 11 7 5 28 20

Machine 1 Machine 2 Order Done Machine 1 Done Machine 2


Job 1 8 13 second 13 26
Job 2 10 11 fourth 32 65
Job 3 14 7 seventh 79 106
Job 4 5 5 first 5 10
Job 5 9 28 third 22 54
Job 6 13 20 fifth 45 85
Job 7 20 14 sixth 65 99
Job 8 26 4 eighth 105 110
Total 105 102 Makespan 110

SECUENCIA: 4,1,5,2,6,7,3,8
A)METODO DE JOHNSON
B)4,1,5,2,6,7,3,8
G H
20 26
14 4

)METODO DE JOHNSON
)4,1,5,2,6,7,3,8