You are on page 1of 8

AS4324.

1-1995 Standard for Design of Bulk Materials Handling


Machines
Richard Morgan
ASPEC Engineering

Abstract
The increasing level of mineral exports from Australia has resulted in the need for expansions to
existing facilities and new export facilities. Rail-mounted materials handling machines such as
shiploaders, stackers and reclaimers are significant investment items for the ports and mines
involved in the supply chain for export of these commodities. Australia is one of the few countries
to have its own standard for such equipment: AS4324.1.

INTRODUCTION important in determining the load imposed on a


machine. This is an area which requires close attention
AS4324.1 Mobile equipment for continuous handling of
both in the design phase and on site to ensure that the
bulk materials Part 1- General requirements for the
installed devices perform the correct function.
design of steel structures was introduced in 1995. The
AS4324.1 adopts a philosophy of not overly relying on
Standard had a long gestation period [5], with work
electrical protection devices for structural integrity.
commencing in 1978. Its release in 1995 was timely in
response to a number of failures of bulk materials
APPLICATION OF AS4324.1 TO TYPES OF
handling machines in Australia in the early 1990s. This
Standard applies to mobile equipment for continuous MACHINES
handling of bulk materials, e.g. excavators, stackers, AS4324.1 is intended to apply to both rail-mounted yard
reclaimers, shiploaders, and ship unloaders. It was machines and continuous mining machines which are
intended that AS4324: Part 1, which deals with steel usually mounted on crawlers. Appendix E in the
structures, would be followed by other parts addressing Standard gives illustrations of the types of machines for
mechanical, electrical and other aspects. However this which the Standard is intended to apply. A description
has not occurred. of some of the more common types of rail-mounted
machines follows below.
The International Organization for Standardization (ISO)
has published a design standard for bulk materials Stacker Reclaimers
handling machines, ISO5049.1 [3] which has been
widely used internationally and was used in Australia Figure 1 shows the components on an older style of
prior to 1995. There are significant differences between stacker reclaimer. The machine has a long travel
AS4324.1 and ISO5049.1; generally speaking, motion along tracks propelled by driven wheels on the
machines designed according to AS4324.1 are heavier bogie system. In the stacking mode, bulk material is fed
than similar machines designed to ISO5409.1. German onto the machine from the yard belt via a tripper which
Standard DIN 2226 [2] has been written specifically for discharges onto the elevator. Material travels on a
machines working in large brown coal open cut mines, conveyor up the elevator and discharges through a
including bucket wheel excavators. AS4324.1 has chute onto the boom conveyor. The bulk material
adopted material from DIN 22261 and its predecessors discharges onto the stockpile from the end of the boom.
in addition to material from ISO5049.1.

Protective or load limiting devices in the electrical,


control, mechanical and hydraulic systems are very

PEC Technical Article,July 2012 1


Figure 1 - Stacker Reclaimer

In reclaiming mode the boom conveyor reverses to extend the elevator away from the machine with the
direction. Bulk material is reclaimed from the stockpile tow bridge.
by the bucket wheel which rotates via a driven shaft.
The buckets dig material from the stockpile and Stackers
discharge them onto the boom conveyor. The boom
Stackers predominately long travel with limited slewing
conveyor discharges material through a central chute
motions in order to lay the stockpiles for subsequent
onto the yard conveyor.
reclaiming by a slewing or bridge type reclaimers. On
modern designs luffing is carried out by means of
The boom can pivot in a vertical plane about a central
hydraulic cylinders. Stackers with longer spans are
bearing to follow the stockpile terrain. This motion is
often articulated to provide less variation in load during
driven by hydraulic cylinders and is termed “luffing”.
the luffing motion.
The boom can also rotate in the horizontal plane about
a circular bearing. This motion is driven by a gear
Reclaimers
system and is termed “slewing”.
Bucket wheel boom type reclaimers are similar to a
Machines of this type are sensitive to changes in bucket wheel stacker reclaimer (see Figure 1) but
balance about the luffing pivot. Changes in weight and without the stacking function, so they do not include a
weight distribution need to be carefully monitored and tripper and elevator. Bridge reclaimers of the bucket
controlled. The repetitive loading due to the bucket wheel type are often used for reclaiming on the face of
wheel motion requires consideration for metal fatigue of a blended stockpile. Such machines have “rakes”
the structure and slew bearing. Other machine which are used to loosen material on the active face.
configurations are used, e.g. a “C” frame configuration
can slew to both sides of the rail tracks without the need

PEC Technical Article,July 2012 2


Shiploaders Permanent Dynamics D
The treatment of permanent dynamics uses dynamic
Long travelling shiploaders with a wheelbase up to
effects factors which multiply the appropriate dead and
approximately 20 metres commonly have a portal
live loads. The factors used in AS4324.1 include
structure spanning the rails and a fixed boom gantry set
additional values to cover rail-mounted machines as
at 90 degrees to the rail track. The boom conveyor and
well as crawler mounted equipment.
shiploading chute shuttle in and out to load the hatches
and due to geometry, there are limitations on the length
Wind Loads Operating W and Wind While Idle
of in-board travel of the shuttle. The shuttle mechanism
may vary the length of the boom or the boom may be of WW
fixed length with the shuttle within the boom. Another Wind loads, either for operating conditions or for
configuration is the bridge type which has a large extreme winds with the machine out of operation, are
travelling bridge spanning from the seaward rail to a referred to the Australian Standard AS1170.2.
second rail or pivot point some distance behind the Additional requirements are included for gust effects on
berth. A shuttling trolley system, which supports the the superstructure and for wind at a 45 degree angle to
boom, tower, and luffing winch system, travels along the the main structure axes.
bridge.
Travel Skew Forces LS
The portal slewing type shiploader is suitable for ships
without masts and cargo gear. Trimming of hatches is For rail-mounted machines, AS4324.1 nominates a
accomplished by a combination of slewing and long calculation procedure for travel skew forces which is
travel motions. The portal slewing and shuttling type similar to that in the Crane Standard AS1418. This
shiploader allows for greater flexibility in loading includes consideration of asymmetrical traction forces
different ship types than the portal slewing type. on each rail, commonly encountered on bridge-type
shiploaders.
LOADS
Travel Device Obstructed LL
The following section describes some of the important
load conditions which have been expanded or covered In AS4324.1, the approach adopted is to assume that
in more detail in AS4324.1 than in the ISO or DIN these loads are generated where one side of a
Standards. travelling machine is suddenly obstructed and brought
to rest in 300 mm. Consideration of the dynamics of the
Digging Resistance U and Abnormal Digging event, including inertial effects, is required.
Resistance UU
Boom Collision Loads FS, FT
The calculation procedure for digging resistance
AS4324.1 considers the combined effect of both inertia
requires this load to be based on drive motor torque. In
and drive torques for a stopping distance of 300 mm.
the authors experience site measurements generally
AS4324.1 includes load cases to address such
show that machines are driven to the limits of the drive
accidents for both slewing and non-slewing machines.
system.
In the latter case, the limiting long travel drive force
rather than slew torque will determine impact loads.
Lateral Digging Resistance S and Abnormal
AS4324.1 includes a longitudinal boom impact case,
Lateral Digging Resistance SS
representing the situation for a slewable boom machine,
AS4324.1 requires lateral digging resistance to be where the impact might occur while the boom is facing
based on available slew or long travel drive capacity. forward at a shallow angle to the long travel direction.
Site measurements generally support this approach,
even for bucket wheel reclaimers or other yard
machines.

PEC Technical Article,July 2012 3


Buffer Loads OO loads and special loads. The frequency of occurrence
of these load groups are similar to those stated in the
The principle adopted is that rail-mounted machines
crane standard, AS1418.1 [8].
should be equipped with buffers, and that the machine
structure should be capable of surviving a buffer impact
STABILITY AGAINST OVERTURNING
situation where the machine is driven into the buffers at
full long travel speed. With this impact case as well, In order to check safety against overturning, AS43241.1
both inertia and drive forces are required to be requires the stability ratio, (Ms/Mo) to be calculated for
considered concurrently. the prescribed load case combinations. Ms is the
minimum stabilising moment due to the total permanent
Bucket Wheel Loss BL load referred to a possible axis of tipping and Mo is the
maximum overturning moment due to the prescribed
AS4324.1 also includes a requirement to design bucket
load case combination of vertical and horizontal non-
wheel machines for the situation following loss of the
permanent overturning forces referred to the same axis
bucket wheel, shaft and associated gearbox from the
of tipping.
boom, as a result of a bucket wheel shaft failure or
similar accident. Inclusion of this load case was a result The Standard nominates minimum stability ratios
of several failures of this type. against overturning to be applied to load case
combinations varying between 1.5 and 1.1, being higher
Non-Permanent Dynamic Effects DD (1.5) for more frequent operational loading conditions,
This applies to inertia forces due to dynamic load lower (1.33) for less frequent operational loading
effects, such as abnormal acceleration and braking of conditions, and lower again (1.2 or 1.1) for much less
moving parts occurring less than 20,000 times during frequent “abnormal” loading conditions.
the life of the machine (e.g. emergency braking).
Allowance needs to be made during the design phase FATIGUE
for these effects. During the commissioning phase, AS4324.1 refers to AS4100 [7] for fatigue design.
care needs to be taken in testing the emergency stops AS4100 reflects current practice for the design of
on the machine. When emergency stopping is via the welded steel structures subject to fatigue loads. There
braking system, rather than via controlled electrical are important differences between AS4324.1 and
stopping, severe forces can be imparted into the ISO5049.1. AS4324.1 is prescriptive and gives detailed
structure if the brakes or rail clamps are not adjusted guidance on how to calculate the load cases and which
correctly and are applied too quickly following power load combinations to consider. ISO5049.1 uses an
deactivation of the electrical system. outdated “mean stress” approach to fatigue design
which is not adapted to modern standards. It should
Burying (ZZ) also be noted that structures affected by fatigue must
This load case is for where collapse of a stockpile or be regularly inspected for fatigue damage for design
slippage of the bank could cause the reclaiming or code rules such as AS4100 to apply.
excavating component of an operating machine to
become partially or fully buried. The Standard allows For combining the effects of cyclical load components,
for the need for any such appropriate loading to be the AS4324.1 approach is to consider the fatigue
addressed in the procurement specification and gives damage resulting from the cyclical stresses produced
suggestions on how this may be covered. by each component of the loading spectrum and
carrying out a cumulative damage assessment by
LOAD COMBINATIONS Miner's rule summation. AS4100 requires a capacity
factor of 0.7 to be applied for non-redundant load paths
AS4324.1 shows how different load components should and inaccessible areas for inspection.
be considered in combination. These are summarised
in Table 3.7 of AS4324.1, together with safety factors
and stability margins. Loads are grouped according to
their frequency of occurrence, i.e. main loads, additional

PEC Technical Article,July 2012 4


STRENGTH ASSESSMENT by more than five percent, the stresses in the machine
should be re-checked.
AS4324.1 allows for the use of either the permissible
stress method (also termed “working stress”) to AS3990
EXPERIENCE WITH AS4324.1 AND
[9] or limit states method to AS4100 to be used for
SUGGESTED CHANGES
strength design.
The following section covers some of the areas where
BUCKLING ASSESSMENT the author’s organisation has found issues in the
application of AS4324.1 that required resolution. Areas
AS4324.1 permits buckling assessment, either to the
that may need to be addressed in revisions to AS4324.1
limit state procedures of AS4100 or to the permissible
are also identified.
stress procedures of AS3990. This is directly applicable
to design of beams and columns. Design of plate work
Fatigue – Non-Redundant Load Paths
structures for the base and other major components to
resist buckling and to accommodate shear lag effects is The requirement in AS4100 to allow for a capacity
not well covered in the steel design standards AS4100 factor of 0.7 for non-redundant load paths or for areas
or AS3990. AS4324.1 covers this to some extent in which cannot be readily inspected has caused
section 5.4 and Appendix J. difficulties and can be subject to quite different
interpretation by different parties. Procurement
MACHINE PROCUREMENT SPECIFICATION specifications should be specific in this respect to avoid
differing interpretations.
The standard method for procuring bulk materials
handling machines is a design and construct contract
Treatment of Burying Load Case
with the contractor having responsibility for design,
manufacture, supply and installation. The procurement The burying load case is applicable to reclaimers and
specification needs to be written to ensure that the particularly covers the situation where material from the
configuration and performance parameters upon which bank or stockpile slumps onto the end of the boom.
the requirements for the machine were determined can One way of handling this, as suggested in AS4324.1, is
be met realistically in practice. Appendix B in AS4324.1 to assume that the boom can support the full weight of
gives guidance on issues which should be covered this material. Another way this has been handled is to
specifically in the purchase specification. allow the luffing hydraulic system to relieve and the
boom to be partially supported by the stockpile.
DESIGN AUDIT Procurement specifications should be specific in this
respect.
Appendix K in AS4324.1 gives guidance for design
auditing and certification by an independent third party
Blocked Chute – Flooded Belt
engineering consultant. This may be by means of
independent calculations or by checking and reviewing The case of blocked chutes and conveyor-flooded belts
the original design calculations and by computer happening concurrently can be onerous and there is a
analysis. temptation by designers to try to relax requirements to
design for a flooded belt by measures such as installing
WEIGHING a profile plate in the feed chute. This approach should
be treated with caution as the machine can easily be
AS4324.1 requires that after a machine has been
modified in service to remove the profile plate without
constructed, the mass and centre of gravity of the
reference to the designer. Similarly, designers may
machine as built should be accurately determined. The
tend to rely on blocked chute cut-off switches to limit the
final weight of a machine is often greater than that
load from material overflowing from the top of a clogged
advised at the time of tender even when the supplier
chute. In practice, these cut-offs are not instantaneous
has carried out an upfront concept design phase.
or may malfunction, causing greater loadings than
AS4324.1 stipulates that if the construction mass
assumed.
exceeds the mass used in the calculation of static loads

PEC Technical Article,July 2012 5


Design Audit Fluid couplings of any type on the bucket wheel drive
train are not generally suitable as a torque limiting
Qualifications of the design audit engineer and the need
device for normal digging or associated lateral digging
to audit mechanical and electrical items are not covered
and it is suggested that the Standard be revised so as
in AS4324.1. Where the audit engineer’s function is
not to refer to fluid couplings as a load limiting device.
provided as part of the contract for the machine, the
purchase specifications should be specific in this
Permanent Dynamics D
respect to avoid differing interpretations.
In general more guidance on the application of
Boom Collision on Non-Slewing Machines permanent dynamic effects would be a useful addition
to the standard.
On non-slewing machines such as shiploaders and
stackers where the boom is fixed at right angles to the For stability calculations, a uniform dynamic multiplier
long travel tracks, it is usually not practical to design for as adopted in AS4324.1 can produce non-conservative
the boom collision load case and it may be necessary to results. A triangular-distributed acceleration as shown
rely on anti-collision systems. It is suggested that in Figure 2 is more appropriate.
further guidance be given in revisions to AS4324.1.

Travel Device Obstructed On Bridge Machines


On long span bridge machines such as shiploaders and
reclaimers it is usually not practical to design for the
travel device-obstructed load case and it is necessary to
rely on anti-collision and skew control systems. It is
suggested that further guidance be given in revisions to
AS4324.1.

Digging Cut-Off Settings and Protection


Systems
Typically, bucket wheel drives are sized to provide Figure 2. Triangular Distribution of Acceleration
sufficient power to dig and lift the stockpile material.
The drive is sized to operate at about 100% of motor- Redundancy of Stays, Ropes and Hydraulic
rated torque for the majority of its operating time. Cylinders
During operation the digging torque will vary based on a In cases where an operator's cab is located on a boom,
number of factors, such as the type of material being there a requirement for the boom support to be
reclaimed and stockpile slumps. The primary and redundant, with two totally independent support
secondary protection settings are provided so that the systems. The design of ropes or stays is required to
load on the machine is not excessive and the machine consider the dynamic loading which would occur
can continue to operate without too many overload following failure of one of the support systems. The
stoppages. The normal digging resistance (U) is magnitude of the dynamic load multiplier and the need
calculated based on 1.1 times the first protection setting to have this on top of the safety factors is an area which
but not less than 1.1 times the motor-rated torque. The can be subject to quite different interpretation by
abnormal digging resistance (UU) is calculated based different parties. It is suggested that further guidance be
on 1.1 times the greatest protection setting but not less given in revisions to AS4324.1.
than 1.5 times the motor-rate torque. Diversity for
protection systems is particularly beneficial. For Loss of Bucket Wheel
example, a protection system implemented using one
mechanical protective device and one electrical This load case was introduced primarily for situations
protective device has a high diversity component. where the bucket wheel is on a cantilevered section of
shaft. Where the bucket wheel is not cantilevered but
held captive by the boom support structure and the
PEC Technical Article,July 2012 6
discharge/circular chute in case of shaft failure, this load CONCLUSIONS
event may not be applicable. It would be appropriate to
AS4324.1 has been in use for over 16 years and major
revise the Standard to reflect this.
machine suppliers and design audit engineers operating
in Australia are now familiar with the document. Since
Wind Loads
the introduction of AS4324.1, the majority of new
The Standard is written with reference to the 1989 machines in Australia have been subject to a third party
edition of AS1170.2 and uses wind forces for design audit. Its application in the procurement of bulk
permissible stress design, Vp rather than wind forces for handling equipment for Australian ports and mines has
ultimate design Vu. Subsequent editions of the wind generally resulted in robust and reliable machines which
load standard, AS1170.2 published in 2002 and 2011 are expected to offer long-term benefits. Some areas in
only include Vu and do not include Vp. specifically. This the Standard have caused issues and pending revisions
is an area where revision would be appropriate. It may to the Standard, this has generally been covered in
be necessary to define an intermediate wind speed for purchase specifications. Now that most industry
relocation to the storm park position and for parking with participants are familiar with the Standard, revisions
rail clamps. Care needs to be taken in cyclonic areas would be appropriate as part of continuous
where wind is a controlling load case, as use of improvement in the industry.
permissible stress design wind speed may be non-
conservative. REFERENCES
1. British Standards Institute (1982). BS5400:
Plate Buckling
Steel, Concrete and Composite Bridges.
The AS4324.1 assessment method for plate bucking
can be difficult to apply. In practice, plate bucking is 2. German Institute for Standardization (2006),
generally handled by finite element analysis and DIN 22261-2 Excavators, Stackers and
alternative design standards such as BS5400 [1] or the Ancillary Equipment in Brown Coal Open Cut
Merrison Committee recommendations [4] are used. It Mines Part 2 Calculation Principals
is suggested that revisions to AS4324.1 should address
this. 3. International Organization for Standardization
(1994). ISO5049.1: Mobile Equipment for the
Limit States Code Calibration Continuous Handling of Bulk Materials Part 1
Rules for the Design of Steel Structures.
Table 3.7 of AS4324.1 gives load multiplying factors to
be used with the limit states method to AS4100. 4. Merrison, A. W., Flint, A. R., Harper, W. J.,
Normally, the limit states design method uses partial Horne, M. R. and Scruby, G. F. B. (1973).
load factors νP, which differ for each type of load and HMSO Merrison Committee Report on the
range generally between 1.2 and 1.5 depending on the Design and Erection of Steel Box Girder
statistical variability of the load type. However, for Bridges, Part 1 to Part 4.
AS4324.1 this factor is taken as the same for all load
components. In AS1418.1 for cranes, the standard 5. Morgan, R. C. (2011) Design of Materials
notes that where the limit states design method is used, Handling Machines to AS4324.1-1995,
care needs to be taken so that the design gives a Australasian Structural Engineering
degree of safety not less than that for the permissible Conference, Perth, 12 July 2012
stress design method to AS3990. Such a cautionary
note could be included in a revision to AS4324.1 in the 6. Morrison, W. R. B. et al. (1996). A New
short term. Ultimately a full code calibration of the load Australian Standard for Continuous Bulk
multipliers should be carried out in a similar manner to Materials Handling Machines, National
that carried out by Warren et al [11] for crane girders. Conference on Bulk Materials Handling 30
September - 2 October 1996, Melbourne.

PEC Technical Article,July 2012 7


7. Standards Australia (2008). AS4100: Steel
Structures.

8. Standards Australia (2002). AS1418.1: Cranes,


hoists and winches - General requirements.

9. Standards Australia (1993). AS3990:


Mechanical Equipment – Steelwork.

10. Standards Australia (1995). AS4324.1: Mobile


equipment for continuous handling of bulk
materials Part 1 - General requirements for the
design of steel structures.

11. Warren, J. S. et al. (2005). Reliability models of


overhead traveling crane loading for code
calibration, ICOSSAR, Millpress, Rotterdam.

Every effort has been made to ensure that the


information contained in this article is correct. However,
Aspec Engineering Pty Ltd or its employees take no
responsibility for any errors, omissions or inaccuracies.

PEC Technical Article,July 2012 8

You might also like