JADWAL PELAKSANAAN PEKERJAAN

Jumlah Bobot MINGGU KE -


No. Uraian Pekerjaan
Harga (Rp) (%) 1 2 3 4 5 6 7 8 9 10 11 12
I PEKERJAAN PERSIAPAN 21,176,302 1.80101 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286 0.1286
II PEKERJAAN PEMBONGKARAN 6,863,336 0.58372 0.5837
III PEKERJAAN PONDASI 3,252,850 0.27665 0.2766
IV PEKERJAAN STRUKTUR 165,234,284 14.0529 4.6843 4.6843 4.6843
V PEKERJAAN EXTERIOR 168,517,905 14.3322 4.7774 4.7774 4.7774
VI PEKERJAAN LANTAI 283,228,796 24.0881 12.044 12.044
VII PEKERJAAN INTERIOR 16,025,772 1.36296 0.6815
VIII PEKERJAAN ATAP 95,344,522 8.10889 4.0544 4.0544
IX PEKERJAAN CAT 9,409,266 0.80024
X PEKERJAAN KUSEN/PINTU 334,200,000 28.4231 14.212 14.212
XI PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 72,549,317 6.1702
JUMLAH 1,175,802,348 100 0.1286 0.7124 0.4053 4.8129 4.8129 4.8129 4.906 16.95 16.95 4.1831 18.395 15.022
BOBOT KUMULATIF (%) 0.1286 0.841 1.2463 6.0592 10.872 15.685 20.591 37.541 54.491 58.674 77.069 92.091
13 14
0.1286 0.1286

0.6815

0.4001 0.4001

3.0851 3.0851
4.2953 3.6139
96.386 100