I PEKERJAAN PERSIAPAN
1 PEKERJAAN PERSIAPAN
- Pembersihan Lahan m2 277.20 10,000.00
Total
2 PEKERJAAN PASANGAN
- Pangan Dinding Bata Ringan m2 331.20 419,401.00
- Pasangan batu bata m2 140.40 354,714.00
Total
3 PEKERJAAN BETON
- Kolom (30x40)cm m' 136.00 130,124.00
- Kolom (15x15)cm m' 64.00 130,124.00
- Balok (30x40)cm m' 99.60 153,781.00
- Pengecoran tangga (anak tangga) M3 1.54 1,186,425.00
- Pembesian (anak tangga) Ø12mm kg 389.76 18,809.29
- Pembesian (anak tangga) Ø8mm kg 138.65 18,809.29
- Bekesting (anak tangga) m2 24.74 319,938.00
- Pengecoran tangga (bordes) M3 0.45 1,186,425.00
- Pembesian (anak tangga) Ø12mm kg 254.35 18,809.29
- Bekesting (anak tangga) m2 4.20 314,797.00
Total
4 PEKERJAAN PLESTERAN
- Pekerjaan plesteran mortar m2 662.40 58,439.00
- Pekerjaan acian mortar m2 662.40 30,753.00
- Pekerjaan benangan M' 82.80 10,000.00
- Pekerjaan waterproofing m2 331.20 65,700.00
Total
5 PEKERJAAN KUSEN, PINTU, JENDELA DAN PENGUNCI
- Pekerjaan Pintu (P1) m2 7.36 259,000.00
- Pekerjaan jendela (J1) m2 6.00 216,000.00
- Pekerjaan kaca m2 9.00 135,000.00
- Aksesoris Pintu ls 4.00 22,000.00
- Aksesoris jendela ls 10.00 25,000.00
Total
6 PEKERJAAN LANTAI
- Pekerjaan keramik 30x30cm m2 260.70 177,973.00
- Pekerjaan keramik 20x20cm m2 16.50 89,604.00
- Pekerjaan dinding keramik m2 43.88 89,604.00
- Pekerjaan keramik lantai tangga m2 10.26 177,973.00
Total
7 PEKERJAAN PLAFOND
- Pekerjaan plafond Gypsum 9mm m2 277.20 80,788.00
- Pekerjaan rangka plafon Hollow m2 277.20 53,803.00
Total
8 PEKERJAAN PENGECATAN
- Pengecatan dinding exterior m2 331.20 29,705.00
- Pengecatan dinding interior m2 331.20 29,705.00
- Pengcatan plafon m2 206.00 29,705.00
Total
9 PEKERJAAN ATAP
- Pekerjaan kuda-kuda Baja WF 200.100.5 kg 609.00 29,440.00
- Pekerjaan rangka baja ringan m2 364.00 27,192.00
- Pekerjaan genteng m2 364.00 87,975.00
- Pekerjaan lisplank M' 82.80 44,469.00
Total
10 PEKERJAAN LAIN-LAIN
- Pekerjaan railing balkon M' 96.00 285,991.00
- Pekerjaan railing tangga M' 70.20 285,991.00
Total
HARGA SATUAN
PEKERJAAN (Rp.)
5
2,772,000.00
2,772,000.00
138,905,611.20
49,801,845.60
188,707,456.80
17,696,864.00
8,327,936.00
15,316,587.60
1,825,908.08
7,331,106.92
2,607,907.37
7,914,626.24
533,891.25
4,784,141.64
1,322,147.40
61,554,827.46
38,709,993.60
20,370,787.20
828,000.00
21,759,840.00
81,668,620.80
1,905,981.00
1,296,000.00
1,215,000.00
88,000.00
250,000.00
4,754,981.00
46,397,561.10
1,478,466.00
3,931,375.50
1,826,002.98
53,633,405.58
22,394,433.60
14,914,191.60
37,308,625.20
9,838,296.00
9,838,296.00
6,119,230.00
25,795,822.00
17,928,960.00
9,897,888.00
32,022,900.00
3,682,033.20
63,531,781.20
27,455,136.00
20,076,568.20
47,531,704.20
PERHITUNGAN BACK UP VOLUME
I PEKERJAAN LANTAI 2
1 PEKERJAAN PERSIAPAN
- Pembersihan Lahan 33 8.4
2 PEKERJAAN PASANGAN
- Pangan Dinding Bata Ringan 33 8.4 4
- Pasangan batu bata 3 1.35 4
3 1.425 4
3 PEKERJAAN BETON
- Kolom (30x40)cm 4
- Kolom (15x15)cm 4
- Balok (30x40)cm 33
8.4
- Pengecoran tangga (anak tangga) 1 0.27 0.15
- Pembesian (anak tangga) Ø12mm
- Pembesian (anak tangga) Ø8mm
- Bekesting (anak tangga) 1 0.27 0.15
- Pengecoran tangga (bordes) 3 1 0.15
- Pembesian (anak tangga) Ø12mm
- Bekesting (anak tangga) 3 1 0.15
4 PEKERJAAN PLESTERAN
- Pekerjaan plesteran mortar 33 8.4 4
- Pekerjaan acian mortar 33 8.4 4
- Pekerjaan benangan 33 8.4
- Pekerjaan waterproofing 33 8.4 4
PEKERJAAN KUSEN, PINTU, JENDELA DAN
5
PENGUNCI
- Pekerjaan Pintu (P1) 1.65 2.23
- Pekerjaan jendela (J1) 1.5 2
- Pekerjaan kaca 1.8 1
- Aksesoris Pintu
- Aksesoris jendela
6 PEKERJAAN LANTAI
- Pekerjaan keramik 30x30cm 33 8.4
- Pekerjaan keramik 20x20cm 5.5 3
- Pekerjaan dinding keramik 3 1.35 1.25
3 1.425 1.25
- Pekerjaan keramik lantai tangga 1 0.27
7 PEKERJAAN PLAFOND
- Pekerjaan plafond Gypsum 9mm 33 8.4
- Pekerjaan rangka plafon Hollow 33 8.4
8 PEKERJAAN PENGECATAN
- Pengecatan dinding exterior 33 8.4 4
- Pengecatan dinding interior 33 8.4 4
- Pengcatan plafon 33 8.4
9 PEKERJAAN ATAP
- Pekerjaan kuda-kuda Baja WF 200.100.5.5 8.4
- Pekerjaan rangka baja ringan 35 10.4
- Pekerjaan genteng 35 10.4
- Pekerjaan lisplank 33 8.4
10 PEKERJAAN LAIN-LAIN
- Pekerjaan railing balkon 30 1.2
- Pekerjaan railing tangga 4 1.2
OLUME
277.20 277.20 m2
331.2 331.20 m2
2 69.6 140.40 m2
2 70.8
2 662.4 662.40 m2
2 662.4 662.40 m2
82.8 82.80 M'
331.2 331.20 m2
2 7.359 7.36 m2
5 6 6.00 m2
5 9 9.00 m2
4 4.00 ls
10 10.00 ls
277.2 260.70 m2
16.5 16.50 m2
2 21.75 43.88 m2
2 22.125
38 10.26 10.26 m2
277.2 277.20 m2
277.2 277.20 m2
331.2 331.20 m2
331.2 331.20 m2
277.2 206.00 m2
5 609 609.00 kg
364 364.00 m2
364 364.00 m2
82.8 82.80 M'
55 96 96.00 M'
36 70.2 70.20 M'
1 2 3 4 5
II BAHAN / MATERIAL
A Bahan Material Non Sanitasi
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 1.6500 59,500.00
Tukang Batu L.02 OH 0.2750 80,000.00
Kepala Tukang L.03 OH 0.0280 100,000.00
Mandor L.04 OH 0.0830 100,000.00
2 BAHAN
Semen Portlan M.15 Kg 326.0000 1,489.75
Pasir Beton M.14.A Kg 760.0000 195.39
Krikil M.12 Kg 1029.0000 176.67
Air M.02 L 215.0000 16.00
3 PERALATAN
Molen E.28.b Jam 1.7500 34,250.00
Vibrator Jam 0.7000 25,270.00
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 1.6500 59,500.00
Tukang Batu L.02 OH 0.2750 80,000.00
Kepala Tukang L.03 OH 0.0280 100,000.00
Mandor L.04 OH 0.0830 100,000.00
-
2 BAHAN -
Semen Portlan M.15 Kg 371.0000 1,489.75
Pasir Beton M.14.A Kg 698.0000 195.39
Krikil M.12 Kg 1047.0000 176.67
Air M.02 L 215.0000 16.00
3 PERALATAN
Molen E.28.b Jam 1.7500 34,250.00
Vibrator Jam 0.7000 25,270.00
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 1.6500 59,500.00
Tukang Batu L.02 OH 0.2750 80,000.00
Kepala Tukang L.03 OH 0.0280 100,000.00
Mandor L.04 OH 0.0830 100,000.00
2 BAHAN
Semen Portlan M.15 Kg 384.0000 1,489.75
Pasir Beton M.14.A Kg 692.0000 195.39
Krikil M.12 Kg 1039.0000 176.67
Air M.02 L 215.0000 16.00
3 PERALATAN
Molen E.28.b Jam 1.7500 34,250.00
Vibrator Jam 0.7000 25,270.00
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.0700 59,500.00
Tukang Besi L.02 OH 0.0700 80,000.00
Kepala Tukang L.03 OH 0.0070 100,000.00
Mandor L.04 OH 0.0040 100,000.00
2 BAHAN
Besi Beton (Polos/Ulir) M.55.d KG 10.5000 14,328.00
Kawar Ikat M.60 KG 0.1500 15,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.6600 59,500.00
Tukang Batu L.02 OH 0.3300 80,000.00
Kepala Tukang L.03 OH 0.0330 100,000.00
Mandor L.04 OH 0.0330 100,000.00
2 BAHAN
Kayu Kelas III M.58 M3 0.0400 2,525,000.00
Paku 5 cm dan 10 cm M.83 KG 0.4000 15,000.00
Minyak Bekesting M.75 LITER 0.2000 25,000.00
Balok Kayu Kelas II M.53 M3 0.0150 1,490,000.00
Plywood Tebal 9 mm M.78 LEMBAR 0.3500 135,000.00
Kayu Dolken Ukuran 8/10 p. 4m M.56 BATANG 2.0000 9,933.33
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.6600 59,500.00
Tukang Batu L.02 OH 0.3300 80,000.00
Kepala Tukang L.03 OH 0.0330 100,000.00
Mandor L.04 OH 0.0330 100,000.00
2 BAHAN
Kayu Kelas III M.58 M3 0.0400 2,525,000.00
Paku 5 cm dan 10 cm M.83 KG 0.4000 15,000.00
Minyak Bekesting M.75 LITER 0.2000 25,000.00
Balok Kayu Kelas II M.53 M3 0.0180 1,490,000.00
Plywood Tebal 9 mm M.78 LEMBAR 0.3500 135,000.00
Kayu Dolken Ukuran 8/10 p. 4m M.56 BATANG 2.0000 9,933.33
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.1800 59,500.00
Tukang batu L.02 OH 0.0200 80,000.00
Tukang kayu L.02 OH 0.0200 80,000.00
Tukang besi L.02 OH 0.0200 80,000.00
Kepala tukang L.03 OH 0.0060 100,000.00
Mandor L.04 OH 0.0090 100,000.00
2 BAHAN
Kayu kelas III M3 0.0020 2,525,000.00
Paku Biasa KG 0.0100 15,000.00
Minyak bekisting Liter 1.2000 25,000.00
Besi beton (polos/ulir) KG 3.0000 14,328.00
Kawat beton KG 0.4500 15,000.00
Semen portland KG 4.5000 1,489.75
Pasir Beton M3 0.0060 273,550.00
Kerikil M3 0.0090 318,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.2970 59,500.00
Tukang batu L.02 OH 0.0330 80,000.00
Tukang kayu L.02 OH 0.0330 80,000.00
Tukang besi L.02 OH 0.0330 80,000.00
Kepala tukang L.03 OH 0.0100 100,000.00
Mandor L.04 OH 0.0150 100,000.00
2 BAHAN
Kayu kelas III M3 0.0030 2,525,000.00
Paku Biasa KG 0.0200 15,000.00
Minyak bekisting Liter 1.2000 25,000.00
Besi beton (polos/ulir) KG 3.6000 14,328.00
Kawat beton KG 0.0500 15,000.00
Semen portland KG 5.5000 1,489.75
Pasir Beton M3 0.0090 273,550.00
Kerikil M3 0.0150 318,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.0600 59,500.00
Tukang Batu L.02 OH 0.0600 80,000.00
Kepala Tukang L.03 OH 0.0060 100,000.00
Mandor L.04 OH 0.0030 100,000.00
2 BAHAN
BESI BAJA IWF KG 1.1500 14,200.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.0600 59,500.00
Tukang Batu L.02 OH 0.0600 80,000.00
Kepala Tukang L.03 OH 0.0060 100,000.00
Mandor L.04 OH 0.0030 100,000.00
2 BAHAN
BESI PROFIL KG 1.1500 12,500.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.1000 59,500.00
Tukang Batu L.02 OH 0.1000 80,000.00
Kepala Tukang L.03 OH 0.0010 100,000.00
Mandor L.04 OH 0.0050 100,000.00
2 BAHAN
Solar Liter 1.0000 6,600.00
Minyak Pelumas Liter 0.1000 20,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
HARGA SATUAN
No. URAIAN Kode SATUAN KOEFISIEN
(Rp.)
1 UPAH
Tukang Batu L.02 OH 0.0500 80,000.00
Mandor L.04 OH 0.0030 100,000.00
2 BAHAN
Mur dan Baut Buah 1.1500 1,500.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
JUMLAH
(Rp.)
98,175.00
14,175.00
2,800.00
8,300.00
485,658.50
148,498.57
181,790.00
3,440.00
59,937.50
17,689.00
1,020,463.57
102,046.36
1,122,510.00 948584
JUMLAH
(Rp.)
98,175.00
14,175.00
2,800.00
8,300.00
552,697.25
136,384.21
184,970.00
3,440.00
59,937.50
17,689.00
1,078,567.96
107,856.80
1,186,425.00
JUMLAH
(Rp.)
98,175.00
14,175.00
2,800.00
8,300.00
572,064.00
135,211.86
183,556.67
3,440.00
59,937.50
17,689.00
1,095,349.02
109,534.90
1,204,884.00
JUMLAH
(Rp.)
4,165.00
5,600.00
700.00
400.00
150,444.00
2,250.00
163,559.00
24,533.85
188,092.85
JUMLAH
(Rp.)
39,270.00
26,400.00
3,300.00
3,300.00
101,000.00
6,000.00
5,000.00
22,350.00 4
47,250.00 0.05
19,866.67
0.07
0.014
71.428571
273,736.67
41,060.50
314,797.00
0.06
0.12
6
0.0432
23.148148
JUMLAH
(Rp.)
39,270.00
26,400.00
3,300.00
3,300.00
101,000.00
6,000.00
5,000.00
26,820.00 4
47,250.00 0.05
19,866.67
-
-
278,206.67
41,731.00
319,938.00
JUMLAH
(Rp.)
10,710.00
1,600.00
1,600.00
1,600.00
600.00
900.00
5,050.00
150.00
30,000.00
42,984.00
6,750.00
6,703.88
1,641.30
2,862.00
70
9,108,680.00
113,151.18
16,972.68
130,124.00 5,204,960.00
10 X 15 CM
JUMLAH
(Rp.)
17,671.50
2,640.00
2,640.00
2,640.00
1,000.00
1,500.00
7,575.00
300.00
30,000.00
51,580.80
750.00
8,193.63
2,461.95
4,770.00
70
10,764,670.00
133,722.88
20,058.43
153,781.00 6,151,240.00
JUMLAH
(Rp.)
3,570.00
4,800.00
600.00
300.00
16,330.00
25,600.00
3,840.00
29,440.00
JUMLAH
(Rp.)
3,570.00
4,800.00
600.00
300.00
14,375.00
23,645.00
3,546.75
27,192.00
JUMLAH
(Rp.)
5,950.00
8,000.00
100.00
500.00
6,600.00
2,000.00
23,150.00
3,472.50
26,623.00
JUMLAH
(Rp.)
4,000.00
300.00
1,725.00
6,025.00
903.75
6,929.00
ANALI SA HAR GA SAT UAN
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : PEMASANGAN 1 M2 RANGKA PLAFOND
HARGA SATUAN : Rp. 53,803.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.2000 59,500.00
Tukang Kayu L.02 OH 0.3000 80,000.00
Kepala Tukang L.03 OH 0.0300 100,000.00
Mandor L.04 OH 0.0100 100,000.00
2 BAHAN
Kayu 5/7 cm Kelas III M3 0.0163 200,000.00
Paku 3-5 cm KG 0.2500 14,500.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : PEMASANGAN 1 M2 PLAFOND GYPSUM
HARGA SATUAN : Rp. 80,788.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.2000 59,500.00
Tukang Kayu L.02 OH 0.3000 80,000.00
Kepala Tukang L.03 OH 0.0300 100,000.00
Mandor L.04 OH 0.0100 100,000.00
2 BAHAN
Gypsum Board (120 x 240 x 9) cm M2 0.3800 70,000.00
Paku 3-5 cm KG 0.2500 15,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : KERAMIK 1 M2 LANTAI KERAMIK UKURAN 30 x 30 CM
HARGA SATUAN : Rp. 177,973.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.7000 59,500.00
Tukang Batu L.02 OH 0.3500 80,000.00
Kepala Tukang L.03 OH 0.0350 100,000.00
Mandor L.04 OH 0.0350 100,000.00
2 BAHAN
Lantai Keramik 30 X 30 cm BUAH 11.8700 4,100.00
Semen Porland KG 10.0000 1,489.75
Pasir Pasang M3 0.0450 273,550.00
Semen Warna KG 1.5000 1,489.75
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : KERAMIK 1 M2 LANTAI KERAMIK UKURAN 20 x 20 CM
HARGA SATUAN : Rp. 89,604.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.7000 59,500.00
Tukang Batu L.02 OH 0.3500 80,000.00
Kepala Tukang L.03 OH 0.0350 100,000.00
Mandor L.04 OH 0.0350 100,000.00
2 BAHAN
Lantai Keramik Ukuran 20 x 20 BUAH 26.5000 1,800.00
Semen Porland KG 10.4000 1,489.75
Pasir Pasang M3 0.0450 273,550.00
Semen Warna KG 1.6200 1,489.75
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : 1 M2 PLESTERAN TEBAL 1,5 CM, DENGAN CAMPURAN 1 PC : 3 P)
HARGA SATUAN : Rp. 58,439.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.3000 59,500.00
Tukang Batu L.02 OH 0.1500 80,000.00
Kepala Tukang L.03 OH 0.0150 100,000.00
Mandor L.04 OH 0.0150 100,000.00
2 BAHAN
Pasir Pasang M3 0.0230 273,550.00
Semen Portlan KG 7.7760 1,489.75
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : 1 M2 ACIAN
HARGA SATUAN : Rp. 30,753.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.2000 59,500.00
Tukang L.02 OH 0.1000 80,000.00
Kepala Tukang L.03 OH 0.0100 100,000.00
Mandor L.04 OH 0.0100 100,000.00
2 BAHAN
Semen Portlan kg 3.2500 1,489.75
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
: 1 M2 PENGECATAN TEMBOK BARU (1 x PLAMIR, 1 x CAT DASAR, 2 x CAT
ITEM PEKERJAAN
PENUTUP)
HARGA SATUAN : Rp. 29,705.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.0200 59,500.00
Tukang L.02 OH 0.0630 80,000.00
Kepala Tukang L.03 OH 0.0060 100,000.00
Mandor L.04 OH 0.0030 100,000.00
2 BAHAN
Plamir KG 0.1000 40,000.00
Cat Dasar KG 0.1000 30,000.00
Cat Penutup 2x KG 0.2600 45,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : PEMASANGAN GENTENG
HARGA SATUAN : Rp. 87,975.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.2000 59,500.00
Tukang Kayu L.02 OH 0.1000 80,000.00
Kepala Tukang L.03 OH 0.0100 100,000.00
Mandor L.04 OH 0.0010 100,000.00
2 BAHAN
Genteng Bh 5.0000 2,000.00
Paku Biasa Kg 0.2000 227,500.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : 1 M LISPLANK UKURAN (3 x 30) CM, KAYU KELAS II
HARGA SATUAN : Rp. 44,469.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.1000 59,500.00
Tukang Kayu L.02 OH 0.2000 80,000.00
Kepala Tukang L.03 OH 0.0200 100,000.00
Mandor L.04 OH 0.0050 100,000.00
2 BAHAN
Papan Kayu M3 0.0110 258,480.00
Paku 5 dan 7 cm KG 0.0500 227,500.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : 1 M2 RANGKA ATAP BAJA RINGAN
HARGA SATUAN : Rp. 934,000.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.2000 59,500.00
Tukang Kayu L.02 OH 0.4500 80,000.00
Kepala Tukang L.03 OH 0.0100 100,000.00
Mandor L.04 OH 0.0500 100,000.00
2 BAHAN
Profil C-75 M 3.7200 50,765.00
Mur, Baut dan Sekrup BUAH 28.0000 9,919.00
Reng Canai Dingin M 5.4000 25,000.00
Dynabol dia 12 x 120 mm BUAH 2.0000 75,000.00
Talang / Jurai Canai Dingin M 0.1240 54,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : PASANGAN 1 M2 DINDING BATU BATA
HARGA SATUAN : Rp. 354,714.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.3500 59,500.00
Tukang Batu L.02 OH 0.1500 80,000.00
Kepala Tukang L.03 OH 0.0150 100,000.00
Mandor L.04 OH 0.0180 100,000.00
2 BAHAN
Batu bata m2 12.5000 2,000.00
Semen Portlan KG 24.2600 1,489.75
Pasir Pasang M3 0.7720 273,550.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : PASANGAN 1 M2 DINDING BATA RINGAN
HARGA SATUAN : Rp. 419,401.00 M2
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.3500 59,500.00
Tukang Batu L.02 OH 0.1500 80,000.00
Kepala Tukang L.03 OH 0.0150 100,000.00
Mandor L.04 OH 0.0180 100,000.00
2 BAHAN
Batu Ringan m2 12.5000 6,500.00
Semen Portlan KG 24.2600 1,489.75
Pasir Pasang M3 0.7720 273,550.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
PEKERJAAN :
LOKASI :
ITEM PEKERJAAN : PEMASANGAN PIPA 1 M PIPA GIP Ø 75 MM
HARGA SATUAN : Rp. 285,991.00 M
BASIS PRODUKSI : 1 Unit
HARGA SATUAN
No. URAIAN Kode SATUANKOEFISIEN
(Rp.)
1 UPAH
Pekerja L.01 OH 0.3450 59,500.00
Tukang Pipa L.02 OH 0.1720 80,000.00
Mandor L.04 OH 0.0340 100,000.00
2 BAHAN
Pipa GIP Ø 75 mm 0 M 1.0000 211,000.00
3 PERALATAN
BIAYA LANGSUNG
BIAYA UMUM DAN KEUNTUNGAN (15 % DARI BIAYA LANGSUNG)
TOTAL
Referensi : Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No 28 - 2016
JUMLAH
(Rp.)
11,900.00
24,000.00
3,000.00
1,000.00
3,260.00
3,625.00
46,785.00
7,017.75
53,803.00
JUMLAH
(Rp.)
11,900.00
24,000.00
3,000.00
1,000.00
26,600.00
3,750.00
70,250.00
10,537.50
80,788.00
CM
JUMLAH
(Rp.)
41,650.00
28,000.00
3,500.00
3,500.00
48,667.00
14,897.50
12,309.75
2,234.63
154,758.88
23,213.83
177,973.00
CM
JUMLAH
(Rp.)
41,650.00
28,000.00
3,500.00
3,500.00
47,700.00
15,493.40
12,309.75
2,413.40
77,916.55
11,687.48
89,604.00
RAN 1 PC : 3 P)
JUMLAH
(Rp.)
17,850.00
14,400.00
1,500.00
1,500.00
6,291.65
11,584.30
53,125.95
5,312.59
58,439.00
JUMLAH
(Rp.)
11,900.00
8,000.00
1,000.00
1,000.00
4,841.69
26,741.69
4,011.25
30,753.00
JUMLAH
(Rp.)
1,190.00
5,040.00
600.00
300.00
4,000.00
3,000.00
11,700.00
25,830.00
3,874.50
29,705.00
JUMLAH
(Rp.)
11,900.00
8,000.00
1,000.00
100.00
10,000.00
45,500.00
76,500.00
11,475.00
87,975.00
JUMLAH
(Rp.)
5,950.00
16,000.00
2,000.00
500.00
2,843.28
11,375.00
38,668.28
5,800.24
44,469.00
JUMLAH
(Rp.)
11,900.00
36,000.00
1,000.00
5,000.00
188,845.80
277,732.00
135,000.00
150,000.00
6,696.00
812,173.80
121,826.07
934,000.00
JUMLAH
(Rp.)
20,825.00
12,000.00
1,500.00
1,800.00
25,000.00
36,141.34
211,180.60
308,446.94
46,267.04
354,714.00
JUMLAH
(Rp.)
20,825.00
12,000.00
1,500.00
1,800.00
81,250.00
36,141.34
211,180.60
364,696.94
54,704.54
419,401.00
JUMLAH
(Rp.)
20,527.50
13,760.00
3,400.00
211,000.00
248,687.50
37,303.13
285,991.00
REKAPITULASI
NO JENIS PEKERJAAN TOTAL HARGA
1 2 3
JUMLAH 567,259,224.24
PPN 10% 56,725,922.42
JUMLAH TOTAL 623,985,146.66
JUMLAH DIBULATKAN 623,900,000.00