You are on page 1of 1

All the Productivity Rates are for working 8 hours/day

Description Qty Rate Resource


Earth Works
Excavation work in soft soil 120 m3/day Excavator (bucket type)
Excavation Work in Hard Soil 50 m3/day Rock breaker

In layer of 150 mm thickness 1 Skilled, 4 Unskilled,


Back Filling + Compaction 150 m2/day
with 95% MDD value 1 shovel,1 Roller compactor

Concrete Protection Works


Bitumen Priming Works Including surface preparation 200 m2/day 1 skilled + 1 unskilled
Bitustic works Horizontal/Vertical surface 150 m2/day 1 skilled + 1 unskilled
Protection works (torch applied) Horizontal/Vertical Surface 80 m2/day 1 skilled + 1 unskilled

Concrete Blinding Works 75/100 mm thick Blinding works 120 m2/day 1 Mason + 2 Helper

Screed Works 40/50 mm thick C/S Screed 200 m2/day 1 Mason + 2 Helper
75/100 mm thick screed with
120 m2/day
welded steel fabric 1 Mason + 2 Helper

Reinforcement Works
Isolated/ Strap Footing Up to 16 mm dia bars 200 kg 1 SF + 1 Helper
Above 16 mm dia bars 300 kg 1 SF + 1 Helper
Column/Corewall/Staircase 200 kg 1 SF + 1 Helper
Slab with beam/Raft Up to 12 mm 300 kg 1 SF + 1 Helper
16 mm and Above 400 kg 1 SF + 1 Helper

Shuttering
Footing With Ordinary(Ply wood) shutter 8 m2/day 1 Carpenter + 1 Helper
Column/Core Wall/Staircase " 6 m2/day 1 Carpenter + 1 Helper
Slab " 12 m2/day 1 Carpenter + 1 Helper

Concrete Pumping Works


Placing with concrete Pump 60 m3/hr
Boom Placer 40 m3/hr

Concrete Works
Footings Concrete Placing and Trowel Finishing 160 m3/day 1 Mason + 3 helper
Staircase " 60 m3/day 1 Mason + 2 helper
Slab " 150 m3/day 2 Mason + 3 Helper

Placing Precast/Hollow Core Slab Placing in line and level 400 m2/day 2 Rigger + 1 Mason + 2 Helper

Block works 10/15/20 cm thick Block works 10 m2/day 1 mason + 1 Helper

Plaster Works 15 mm thick Plaster Works with Acc. 12 m2/day 1 Plaster Mason + 1 Helper
20 mm thick Plaster Works with Acc. 10 m2/day 1 Plaster Mason + 1 Helper

Ordinary Painting
Priming Works Including Surface preparation works 150 m2/day 1 Painter + 1 Helper
Putty Works 75 m2/day 1 Painter + 1 Helper
Painting Works First Coat 250 m2/day 1 painter
Second Coat 350 m2/day 1 Painter

Epoxy Paint Surface Prep + Priming 50 m2/day 1 Painter + 1 Helper


Painting 100 m2/day 1 Painter + 1 Helper

Gypsum Partition Works Frame + Gypsum Partition Installation 120 m2/day 1 Mason + 1 Helper

False Ceiling Frame + False Ceiling Fixing 30 m2/day 1 Mason + 1 Helper

Tile Works On Floor 15 m2/day 1 Mason + 1 Helper


On Walls 12 m2/day 1 Mason + 1 Helper

Marble/Granite Works on Floor 20 m2/day 2 Mason + 1 Helper

You might also like