You are on page 1of 97

CONTOH PERHITUNGAN BERAT BESI BETON DALAM 1 M3

BESI BETON POLOS BESI BETON SPIRAL

Diameter Berat besi Diameter Berat besi Kg / Diameter Berat besi


No. No. No.
mm Kg / m' mm m' mm Kg / m'

1 4.0 0.10 11 12.0 0.89 1 10.0 0.62


2 5.0 0.15 12 13.0 1.04 2 13.0 1.04
3 5.5 0.19 13 14.0 1.21 3 16.0 1.58
4 5.7 0.20 14 16.0 1.58 4 19.0 2.23
5 6.0 0.22 15 19.0 2.23 5 22.0 2.98
6 6.5 0.26 16 22.0 2.98 6 25.0 3.85
7 8.0 0.39 17 23.0 3.26 7 29.0 5.18
8 9.0 0.50 18 25.0 3.85 8 32.0 6.31
9 10.0 0.62 19 28.0 4.83 9 36.0 7.99
10 11.0 0.75 20 31.0 5.92
21 32.0 6.31
PERHITUNGAN VOLUME PEKERJAAN
JARINGAN AIR MINUM GATAK
KABUPATEN SUKOHARJO

A PEKERJAAN PIPA
I PEKERJAAN GALIAN PIPA
1 Galian Tanah biasa Jalur A Pipa Transmisi Ø 300 mm =
Jalur B Pipa Distribusi Ø 150 mm =
Pipa Distribusi Ø 100 mm =
Jalur C Pipa Distribusi Ø 150 mm =
Jalur D Pipa Distribusi Ø 100 mm =
Jalur E Pipa Distribusi Ø 75 mm =
Jalur F Pipa Distribusi Ø 75 mm =
Jalur G Pipa Distribusi Ø 100 mm =
Jalur H Pipa Distribusi Ø 75 mm =
Jalur I Pipa Distribusi Ø 100 mm =
Jalur J Pipa Distribusi Ø 75 mm =
Jalur k Pipa Distribusi Ø 75 mm =
Jalur L Pipa Distribusi Ø 75 mm =
Jalur M Pipa Distribusi Ø 75 mm =

0.11 2 Urugan Tanah Kembali Jalur A Pipa Transmisi Ø 300 mm =


Jalur B Pipa Distribusi Ø 150 mm =
Pipa Distribusi Ø 100 mm =
Jalur C Pipa Distribusi Ø 150 mm =
Jalur D Pipa Distribusi Ø 100 mm =
Jalur E Pipa Distribusi Ø 75 mm =
Jalur F Pipa Distribusi Ø 75 mm =
Jalur G Pipa Distribusi Ø 100 mm =
Jalur H Pipa Distribusi Ø 75 mm =
Jalur I Pipa Distribusi Ø 100 mm =
Jalur J Pipa Distribusi Ø 75 mm =
Jalur k Pipa Distribusi Ø 75 mm =
Jalur L Pipa Distribusi Ø 75 mm =
Jalur M Pipa Distribusi Ø 75 mm =

Urugan Tanah Kembali

III PEKERJAAN CROSSING JALAN ASPAL


1 jalur =
bongkaran aspal
2 Pengembalian bongkaran dengan jalan beton
Lapis pondasi agregat kelas B =
lantai kerja beton K-175 =
Perkerasan Beton K-350 =

IV PEKERJAAN PENGADAAN PIPA DAN ASSESORIS)


1 Pengadaan dan Pemasangan
Jalur A Pipa Transmisi Ø 300 mm =
Jalur B Pipa Distribusi Ø 150 mm =
Pipa Distribusi Ø 100 mm =
Jalur C Pipa Distribusi Ø 150 mm =
Jalur D Pipa Distribusi Ø 100 mm =
Jalur E Pipa Distribusi Ø 75 mm =
Jalur F Pipa Distribusi Ø 75 mm =
Jalur G Pipa Distribusi Ø 100 mm =
Jalur H Pipa Distribusi Ø 75 mm =
Jalur I Pipa Distribusi Ø 100 mm =
Jalur J Pipa Distribusi Ø 75 mm =
Jalur k Pipa Distribusi Ø 75 mm =
Jalur L Pipa Distribusi Ø 75 mm =
Jalur M Pipa Distribusi Ø 75 mm =
Rekap pipa

Pipa Distribusi Ø 300 mm =


Pipa Distribusi Ø 150 mm =
Pipa Distribusi Ø 100 mm =
Pipa Distribusi Ø 75 mm =

2 Pengadaan dan Pemasangan Assesoris " =


Jalur A
Bend all socket. PVC RRJ 90° SNI DN 300 mm =
Bend all socket. PVC RRJ 45 SNI DN 300 mm =
Bend all socket PVC RRJ 11,25° SNI DN 300 mm (Shipon) =
Jalur B
Bend all socket. PVC RRJ 90° SNI DN 150 mm =
Bend all socket. PVC RRJ 45° SNI DN 150 mm =
Bend all socket. PVC RRJ 90° SNI DN 100 mm =
Reducer PVC DN 150 x 100 mm =
Bend all socket PVC RRJ 11,25° SNI DN 150 mm (Shipon) =
Tee all socket. PVC RRJ SNI DN 150 x 150 mm =
Tee all socket. PVC RRJ SNI DN 100 x 75 mm =
Jalur C
Bend all socket. PVC RRJ 90° SNI DN 150 mm =
Tee all socket. PVC RRJ SNI DN 150 x 100 mm =
Jalur D
Bend all socket. PVC RRJ 90° SNI DN 100 mm =
Bend all socket PVC RRJ 11,25° SNI DN 100 mm (Shipon) =
Jalur E
Bend all socket. PVC RRJ 90° SNI DN 75 mm =
Jalur F
Bend all socket PVC RRJ 11,25° SNI DN 75 mm (Shipon) =
Jalur G
Bend all socket. PVC RRJ 90° SNI DN 100 mm =
Tee all socket. PVC RRJ SNI DN 200 x 100 mm =
Tee all socket. PVC RRJ SNI DN 100 x 75 mm =
Tee all socket. PVC RRJ SNI DN 100 x 100 mm =
Jalur H =
Jalur I
Tee all socket. PVC RRJ SNI DN 100 x 75 mm =
Bend all socket. PVC RRJ 90° SNI DN 100 mm =
Bend all socket PVC RRJ 11,25° SNI DN 100 mm (Shipon) =
Jalur J =
Jalur K
Bend all socket. PVC RRJ 90° SNI DN 75 mm =
Jalur L =
Jalur M
Bend all socket. PVC RRJ 90° SNI DN 75 mm =

Rekap ACC
Bend all socket. PVC RRJ 90° SNI DN 300 mm =
Bend all socket. PVC RRJ 45 SNI DN 300 mm =
Bend all socket. PVC RRJ 90° SNI DN 150 mm =
Bend all socket. PVC RRJ 45° SNI DN 150 mm =
Bend all socket. PVC RRJ 90° SNI DN 100 mm =
Bend all socket. PVC RRJ 90° SNI DN 75 mm =
Tee all socket. PVC RRJ SNI DN 150 x 150 mm =
Tee all socket. PVC RRJ SNI DN 150 x 100 mm =
Tee all socket. PVC RRJ SNI DN 100 x 75 mm =
Tee all socket. PVC RRJ SNI DN 200 x 100 mm =
Tee all socket. PVC RRJ SNI DN 100 x 100 mm =
Bend all socket PVC RRJ 11,25° SNI DN 300 mm (Shipon) =
Bend all socket PVC RRJ 11,25° SNI DN 150 mm (Shipon) =
Bend all socket PVC RRJ 11,25° SNI DN 100 mm (Shipon) =
Bend all socket PVC RRJ 11,25° SNI DN 75 mm (Shipon) =
Reducer PVC DN 150 x 100 mm =

V PEKERJAAN JEMBATAN
1 Jembatan Panjang 6 m (1 unit)

1) Galian tanah abutmen =


Urugan Kembali

2) Urugan pasir =
Lantai kerja =

3 Abutment IWF 150 =


beton K-225 plat kaki =
badan =
badan atas =

pembesian plat kaki Ø12 - 150 rangkap =


=
badan Ø16 - 150 =
beugel =

begisting =

2) Trush block
Pasir Urug =
beton K-225 =
begisting =

3) Pekerjaan Konstruksi Jembatan


baja WF 2x150x75 =
plat landas 400 x 1000 x16 mm =
Angkur baut Ø 16 =
balok penyanga 8/16 =
klem plat pengikat 50 x 700 x 5 mm =
mur baut Ø 12 =
Besi Pengaman Bentuk Kipas DN. 16 mm =

3) Pekerjaan Perpipaan dan Assesoris Jembatan pipa


- Pipa Galvanished DN. 300 mm =
- Pipa PVC (wash out) DN. 75 mm =
- All Flanged Bend Cl DN. 300 - 45° =
- All Flanged Tee Cl DN. 300 =
- Gate Valve DN. 300 mm =
- Gate Valve DN. 75 mm =
- Flanged Spigot DN. 75 mm =
- Flanged Spigot DN. 300 mm =
- Taping Sadle DN. 300 mm x 75 mm =
- Air Valve ( lengkap dengan box dan gembok ) DN 25 mm =
- Street Box DN. 300 mm =
- Street Box DN. 75 mm =
- Flanged Steel DN. 300 mm =
- Karet Packing tebal 5 mm DN. 300 mm =

3) Pekerjaan Konstruksi Jembatan bentang 14 m


baja 2 WFx350x175 =
plat landas 400 x 1000 x16 mm =
plat penyambung 300 x 350 x10 mm =
plat penyambung 175 x 350 x10 mm =
Angkur baut Ø 16 =
balok penyanga 8/16 =
klem plat pengikat 50 x 700 x 5 mm =
mur baut Ø 13 =
mur baut Ø 12 =
Besi Pengaman Bentuk Kipas DN. 16 mm =

3) Pekerjaan Perpipaan dan Assesoris Jembatan pipa


- Pipa Galvanished DN. 75 mm =
- Pipa PVC (wash out) DN. 75 mm =
- All Flanged Bend Cl DN. 75 - 45° =
- All Flanged Tee Cl DN. 75 =
- Gate Valve DN. 75 mm =
- Gate Valve DN. 75 mm =
- Flanged Spigot DN. 75 mm =
- Flanged Spigot DN. 75 mm =
- Taping Sadle DN. 75 mm x 75 mm =
- Air Valve ( lengkap dengan box dan gembok ) DN 25 mm =
- Street Box DN. 75 mm =
- Street Box DN. 75 mm =
- Flanged Steel DN. 75 mm =
- Karet Packing tebal 5 mm DN. 75 mm =

3) Pekerjaan Konstruksi Jembatan bentang 17 m


baja 2 WFx400x200 =
plat landas 400 x 1000 x16 mm =
plat penyambung 400 x 450 x10 mm =
plat penyambung 200 x 400 x10 mm =
Angkur baut Ø 16 =
balok penyanga 8/16 =
klem plat pengikat 50 x 700 x 5 mm =
mur baut Ø 13 =
mur baut Ø 12 =
Besi Pengaman Bentuk Kipas DN. 16 mm =

3) Pekerjaan Perpipaan dan Assesoris Jembatan pipa


- Pipa Galvanished DN. 75 mm =
- Pipa PVC (wash out) DN. 75 mm =
- All Flanged Bend Cl DN. 75 - 45° =
- All Flanged Tee Cl DN. 75 =
- Gate Valve DN. 75 mm =
- Gate Valve DN. 75 mm =
- Flanged Spigot DN. 75 mm =
- Flanged Spigot DN. 75 mm =
- Taping Sadle DN. 75 mm x 75 mm =
- Air Valve ( lengkap dengan box dan gembok ) DN 25 mm =
- Street Box DN. 75 mm =
- Street Box DN. 75 mm =
- Flanged Steel DN. 75 mm =
- Karet Packing tebal 5 mm DN. 75 mm =

2 Jembatan Pipa Panjang 2 m

1) Galian tanah abutmen =


Urugan Kembali

2) Urugan pasir =
Lantai kerja =

3 Abutment IWF 150 =


beton K-225 plat kaki =
badan =
badan atas =

pembesian plat kaki Ø12 - 150 rangkap =


=
badan Ø16 - 150 =
beugel =

begisting =

2) Trush block
Pasir Urug =
beton K-225 =
begisting =
3) Pekerjaan Perpipaan dan Assesoris
- Pipa Galvanished DN. 100 mm =
- All Flanged Bend Cl DN. 100 - 45° =
- Flanged Steel DN. 100 mm =
- Karet Packing tebal 5 mm DN. 100 mm =
Pengaman jbt =

2 Jembatan Pipa Panjang 3 m


3) Pekerjaan Perpipaan dan Assesoris
- Pipa Galvanished DN. 100 mm =
- All Flanged Bend Cl DN. 100 - 45° =
- Flanged Steel DN. 100 mm =
- Karet Packing tebal 5 mm DN. 100 mm =
Pengaman jbt =

2 Jembatan Pipa Panjang 4 m


3) Pekerjaan Perpipaan dan Assesoris
- Pipa Galvanished DN. 150 mm =
- All Flanged Bend Cl DN. 150 - 45° =
- Flanged Steel DN. 150 mm =
- Karet Packing tebal 5 mm DN. 150 mm =
Pengaman jbt =

2 Jembatan Pipa Panjang 5 m


3) Pekerjaan Perpipaan dan Assesoris
- Pipa Galvanished DN. 300 mm =
- All Flanged Bend Cl DN. 300 - 45° =
- Flanged Steel DN. 300 mm =
- Karet Packing tebal 5 mm DN. 300 mm =
Pengaman jbt =
bb ba h luas panjang (m)

0.5 x 0.5 x 1.5 0.75 x 6,827 =


0.4 x 0.4 x 1 0.4 x 2,440 =
0.3 x 0.3 x 0.8 0.24 x 960 =
0.4 x 0.4 x 1 0.4 x 510 =
0.3 x 0.3 x 0.8 0.24 x 1,600 =
0.25 x 0.25 x 0.7 0.175 x 400 =
0.25 x 0.25 x 0.7 0.175 x 800 =
0.3 x 0.3 x 0.8 0.24 x 1,679 =
0.25 x 0.25 x 0.7 0.175 x 600 =
0.3 x 0.3 x 0.8 0.24 x 1,839 =
0.25 x 0.25 x 0.7 0.175 x 200 =
0.25 x 0.25 x 0.7 0.175 x 233 =
0.25 x 0.25 x 0.7 0.175 x 225 =
0.25 x 0.25 x 0.7 0.175 x 444 =

¶ r
0.15 3.14 x 0.15 0.071 x 6827.00 =
0.075 3.14 x 0.075 0.018 x 2440.00 =
0.05 3.14 x 0.05 0.008 x 960.00 =
0.075 3.14 x 0.075 0.018 x 510.00 =
0.05 3.14 x 0.05 0.008 x 1600.00 =
0.0375 3.14 x 0.0375 0.004 x 400.00 =
0.0375 3.14 x 0.0375 0.004 x 800.00 =
0.05 3.14 x 0.05 0.008 x 1679.00 =
0.0375 3.14 x 0.0375 0.004 x 600.00 =
0.05 3.14 x 0.05 0.008 x 1839.00 =
0.0375 3.14 x 0.0375 0.004 x 200.00 =
0.0375 3.14 x 0.0375 0.004 x 233.00 =
0.0375 3.14 x 0.0375 0.004 x 225.00 =
0.0375 3.14 x 0.0375 0.004 x 444.00 =

24 + 13 + 8 =
0.7 x 0.15 x 45.00 =
0.7 x 0.2 x 45.00 =
0.7 x 0.1 x 45.00 =
0.7 x 0.3 x 45.00 =

=
=
=
=
=
=
=
=
=
=
=
=
=
=

=
=
=
=

=
=
=

=
=
=
=
=
=
=

=
=

=
=

=
=
=
=
=

=
=
=
=

=
=

=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
bb ba h luas jml panjang (m)

1.6 x 1.6 x 1.5 x 2 2=


=

1.4 x 1.45 x 0.1 x 2 =


1.4 x 1.45 x 0.05 x 2 =

0.15 + 0.16 =
1.4 x 1.45 x 0.25 x 2 =
1 x 1.05 x 3 x 2 =
0.5 x 1.05 x 0.31 x 2 =

3.4 x 10.66667 x 0.888 kg/m 2 =


3.5 x 10.33333 x 0.888 kg/m 2 =
3.86 x 24 x 1.578 kg/m 2 =
5.7 x 25.73333 x 0.888 kg/m 2 =

1 x 1.05 x 3 x 2 =

0.8 x 0.6 x 0.1 x 2=


0.6 0.3 0.5 2=
0.6 x x 0.5 x 2 x 2=

6 m x x 14 kg/m 2 =
0.4 x 1x 0.016 7,850.00 kg/m3 x 2 =
4 x 2 2 =
0.08 x 0.16 x 1 7 =
0.05 x 0.7 x 0.005 7,850.00 kg/m3 x 7 =
4 x 7 =
=

pipa 300
6 + 6+ 6 =
=
=
=
=
=
=
=
=
=
=
=
=
=

pipa 75 mm
14 m x x 41.4 kg/m 2 =
0.4 x 1x 0.016 7,850.00 kg/m3 x 2 =
0.3 x 0.35 x 0.01 7,850.00 kg/m3 x 4 =
0.175 x 0.35 x 0.01 7,850.00 kg/m3 x 2 =
4 x 2 2 =
0.08 x 0.16 x 1 15 =
0.05 x 0.7 x 0.005 7,850.00 kg/m3 x 15 =
16 + 32 2 =
4 x 15 =
=

pipa 75
14 + 6+ 6 =
=
=
=
=
=
=
=
=
=
=
=
=
=

pipa 75 mm
17 m x x 56.6 kg/m 2 =
0.4 x 1x 0.016 7,850.00 kg/m3 x 2 =
0.4 x 0.45 x 0.01 7,850.00 kg/m3 x 4 =
0.2 x 0.4 x 0.01 7,850.00 kg/m3 x 2 =
4 x 2 2 =
0.08 x 0.16 x 1 18 =
0.05 x 0.7 x 0.005 7,850.00 kg/m3 x 18 =
16 + 32 2 =
4 x 18 =
=

pipa 75
17 + 6+ 6 =
=
=
=
=
=
=
=
=
=
=
=
=
=

1 bh pipa 100

1.6 x 1.6 x 1.5 x 2 2=


=

1.4 x 1.45 x 0.1 x 2 =


1.4 x 1.45 x 0.05 x 2 =

+ 0.16 =
1.4 x 1.45 x 0.25 x 2 =
1 x 1.05 x 2 x 2 =
0.5 x 1.05 x 0.16 x 2 =

3.4 x 10.66667 x 0.888 kg/m 2 =


3.5 x 10.33333 x 0.888 kg/m 2 =
2.86 x 24 x 1.578 kg/m 2 =
5.7 x 19.06667 x 0.888 kg/m 2 =

1 x 1.05 x 2 x 2 =

0.8 x 0.6 x 0.1 x 2=


0.6 0.3 0.5 2=
0.6 x x 0.5 x 2 x 2=

2 + 1.75 + 1.5 + 1.75 + 1.5 =


=
=
=
=

1 bh pipa 100

3 + 1.75 + 1.5 + 1.75 + 1.5 =


=
=
=
=

2 bh pipa 150

4 + 1.75 + 1.5 + 1.75 + 1.5 =


=
=
=
=

1 bh pipa 300

5 + 1.75 + 1.5 + 1.75 + 1.5 =


=
=
=
=
2977

VOLUME
- volume Volume

5,120.25 m3 45.00 5,075.250 m3


976.00 m3
230.40 m3
204.00 m3
384.00 m3
70.00 m3
140.00 m3
402.96 m3
105.00 m3
441.36 m3
35.00 m3
40.78 m3
39.38 m3
77.70 m3
8,266.82 m3

- m
482.33 m3 5,075.250 4,583.472 m3
43.10 m3
7.54 m3
9.01 m3
12.56 m3
1.77 m3
3.53 m3
13.18 m3
2.65 m3
14.44 m3
0.88 m3
1.03 m3
0.99 m3
1.96 m3
594.96 m3
7,671.86 m3

45.00 M
4.73 m3
6.30 m3
3.15 m3
9.45 m3

6,827.00 M
2,440.00 M
960.00 M
510.00 M
1,600.00 M
400.00 M
800.00 M
1,679.00 M
600.00 M
1,839.00 M
200.00
233.00
225.00
444.00 M
18,757.00 m

6,827.00 M
2,950.00 M
6,078.00 M
2,902.00 M
18,757.00 M

6.00 bh
3.00 bh
2.00 bh

4.00 bh
1.00 bh
2.00 bh
1.00 bh
2.00 bh
1.00 bh
2.00 bh

2.00 bh
1.00 bh

3.00 bh
1.00 bh

2.00 bh

1.00 bh

3.00 bh
1.00 bh
4.00 bh
1.00 bh

1.00 bh
9.00 bh
6.00 bh

3.00 bh

2.00 bh
64.00 BH

6.00 bh
3.00 bh
6.00 bh
1.00 bh
17.00 bh
7.00 bh
1.00 bh
1.00 bh
7.00 bh
1.00 bh
1.00 bh
2.00 bh
2.00 bh
7.00 bh
1.00 bh
1.00 bh
64.00
VOLUME

15.36 m3
5.12 m3

0.41 m3
0.20 m3

0.31 m
1.02 m3
6.30 m3
0.33 m3
7.64 m3
64.39 kg
64.21 kg
292.42 kg
260.43 kg
681.46 kg

24.60 m2

0.10 m3
0.45 m3
1.20 m2

1.00 unit 2 unit


168.00 kg 336.00 kg
100.48 kg 200.96 kg
16.00 bh 32.00 bh
0.09 m3 0.18 m3
9.62 kg 19.23 kg
28.00 bh 56.00 bh
2.00 unit 4.00 unit

18.00 M
6.00 M
4.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
14.00 Bh
14.00 bh

1.00 unit
1,159.20 kg
100.48 kg
32.97 kg
9.62 kg 42.59 kg
16.00 bh
0.19 m3
20.61 kg
96.00 bh
60.00 bh
2.00 unit

26.00 M
6.00 M
4.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
14.00 Bh
14.00 bh

1.00 unit
1,924.40 kg
100.48 kg
56.52 kg
12.56 kg 69.08 kg
16.00 bh
0.23 m3
24.73 kg
96.00 bh
72.00 bh
2.00 unit
29.00 M
6.00 M
4.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
1.00 Bh
16.00 Bh
16.00 bh

15.36 m3
5.12 m3

0.41 m3
0.20 m3

0.16 m
1.02 m3
4.20 m3
0.17 m3
5.38 m3
64.39 kg
64.21 kg
216.66 kg
192.96 kg
538.23 kg

16.40 m2

0.10 m3
0.45 m3
1.20 m2

8.50 M
4.00 Bh
8.00 Bh
8.00 bh
2.00 bh

9.50 M
4.00 Bh
8.00 Bh
8.00 bh
2.00 bh

10.50 M
4.00 Bh
8.00 Bh
8.00 bh
2.00 bh

11.50 M
4.00 Bh
8.00 Bh
8.00 bh
2.00 bh
RENCANA ANGGARAN BIAYA (RAB)
ENGINEER ESTIMATE (EE)

PEKERJAAN : DED PEMBANGUNAN SPAM IKK GATAK


LOKASI : KABUPATEN SUKOHARJO
TAHUN ANGGARAN : 2013

PEKERJAAN JEMBATAN

HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5
A JEMBATAN PIPA BENTANG 6 M
I Pekerjaan Trush block
1 Pasir Urug 0.10 m3 148,832.00 14,287.87
2 beton K-225 0.45 m3 908,071.21 408,632.05
3 begisting 1.20 m2 98,366.20 118,039.44
SUB TOTAL - I 540,959.36
II Pekerjaan Abutment
1 Galian tanah abutmen 15.36 m3 32,780.00 503,500.80
2 Urugan Kembali 5.12 m3 10,926.67 55,944.53
3 Urugan pasir 0.41 m3 148,832.00 60,425.79
4 Lantai kerja 0.20 m3 728,325.68 147,850.11
5 Abutment
- Beton K-225 7.64 m3 908,071.21 6,938,118.09
- Pembesian 681.46 kg 19,987.83 13,620,834.93
- Begisting 24.60 m2 98,366.20 2,419,808.52

SUB TOTAL - II 23,746,482.78


III Pekerjaan Konstruksi Penyangga Pipa
1 baja WF 2 x 150 x 75 168.00 kg 26,628.60 4,473,604.80
2 Perakitan (Erection) 168.00 kg 1,252.90 210,487.10
3 plat landas 400 x 1000 x16 mm 100.48 bh 27,488.60 2,762,054.53
4 Angkur baut Ø 16 16.00 bh 30,000.00 480,000.00
5 balok penyanga 8/16 kayu bengkire 0.09 m3 10,780,000.00 965,888.00
6 klem plat pengikat 50 x 700 x 5 mm 9.62 kg 27,488.60 264,337.25
7 mur baut Ø 12 28.00 bh 18,000.00 504,000.00
8 Besi Pengaman Bentuk Kipas DN. 16 mm 2.00 unit 750,000.00 1,500,000.00

SUB TOTAL - III 11,160,371.68


IV Pekerjaan Perpipaan dan Assesoris
- Pipa Galvanished DN. 300 mm 18.00 m 1,301,438.92 23,425,900.50
- Pipa PVC (wash out) DN. 75 mm 6.00 m 61,893.25 371,359.50
- All Flanged Bend Cl DN. 300 - 45° 4.00 bh 4,458,160.20 17,832,640.80
- All Flanged Tee Cl DN. 300 1.00 bh 1,893,123.55 1,893,123.55
- Gate Valve DN. 300 mm 1.00 bh 7,667,464.53 7,667,464.53
- Gate Valve DN. 75 mm 1.00 bh 1,150,000.00 1,150,000.00
- Flanged Spigot DN. 75 mm 1.00 bh 235,500.00 235,500.00
- Flanged Spigot DN. 300 mm 1.00 bh 4,194,003.43 4,194,003.43
- Taping Sadle DN. 300 mm x 75 mm 1.00 bh 1,893,123.55 1,893,123.55
- Air Valve ( lengkap dengan box dan gembok ) DN 25 mm 1.00 bh 719,811.05 719,811.05
- Street Box DN. 300 mm 1.00 bh 929,500.00 929,500.00
- Street Box DN. 75 mm 1.00 bh 164,450.00 164,450.00
- Flanged Steel DN. 300 mm 14.00 bh 620,856.15 8,691,986.03
- Karet Packing tebal 5 mm DN. 300 mm 14.00 bh 20,000.00 280,000.00
SUB TOTAL - IV 69,448,862.94
V Pekerjaan Cat - Catan
1 Cat besi 1.00 ls 510,000.00 510,000.00
2 Pembersihan 1.00 ls 500,000.00 500,000.00
SUB TOTAL - V 1,010,000.00
JUMLAH 105,906,676.75
B JEMBATAN PIPA BENTANG 14 M

HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5
RENCANA ANGGARAN BIAYA
ENGINEER ESTIMATE (EE)
Pekerjaan : DED PEMBANGUNAN SPAM IKK GATAK
Lokasi : KABUPATEN SUKOHARJO
Tahun : 2013

No. Jenis Pekerjaan Volume Diameter

1 2 3 4

I PEKERJAAN PERSIAPAN
1 Mobilisasi 1.00 -
2 Steak out 1.00 -
3 Papan Nama Proyek 1.00 -
4 Administrasi dan dokumentasi 1.00 -
5 Pembuatan Gudang dan barak 15.00 -

Jumlah
II SISTEM TRANMISI DAN DISTRIBUSI
II.1 PEKERJAAN TANAH
a Galian Tanah Biasa 8,266.82 -
b Mengurug Kembali Tanah 7,671.86 -
c Memadatkan Tanah Tiap 20 cm 7,671.86

Jumlah
II.2 PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA + ASESORISNYA
II.2.1 Pek. Pengadaan dan Pemasangan Pipa
a Pipa PVC RRJ (S. 10 - 12,5 bar) 6,827.00 300
b Pipa PVC RRJ (S. 10 - 12,5 bar) 2,950.00 150
c Pipa PVC RRJ (S. 10 - 12,5 bar) 6,078.00 100
d Pipa PVC RRJ (S. 10 - 12,5 bar) 2,902.00 75

II.2.2 Pek. Pengadaan dan Pemasangan Assesoris


a Bend all socket. PVC RRJ 90° SNI DN 300 mm 6.00 300
b Bend all socket. PVC RRJ 45 SNI DN 300 mm 3.00 300
c Bend all socket. PVC RRJ 90° SNI DN 150 mm 6.00 150
d Bend all socket. PVC RRJ 45° SNI DN 150 mm 1.00 150
e Bend all socket. PVC RRJ 90° SNI DN 100 mm 17.00 100
f Bend all socket. PVC RRJ 90° SNI DN 75 mm 7.00 75
g Tee all socket. PVC RRJ SNI DN 150 x 150 mm 1.00 150x150
h Tee all socket. PVC RRJ SNI DN 150 x 100 mm 1.00 150x100
i Tee all socket. PVC RRJ SNI DN 100 x 75 mm 7.00 100x75
j Tee all socket. PVC RRJ SNI DN 200 x 100 mm 1.00 200x100
k Tee all socket. PVC RRJ SNI DN 100 x 100 mm 1.00 100x100
l Bend all socket PVC RRJ 11,25° SNI DN 300 mm (Shipon) 2.00 300
m Bend all socket PVC RRJ 11,25° SNI DN 150 mm (Shipon) 2.00 150
n Bend all socket PVC RRJ 11,25° SNI DN 100 mm (Shipon) 7.00 100
o Bend all socket PVC RRJ 11,25° SNI DN 75 mm (Shipon) 1.00 75
p Reducer PVC DN 150 x 100 mm 1.00 150X100

Jumlah
III PEK. KONSTRUKSI JEMBATAN PIPA
a Jembatan Pipa bentang 6 m 1.00 300
b Jembatan Pipa bentang 14 m 1.00 75
c Jembatan Pipa bentang 17 m 1.00 75
d Jembatan Pipa bentang 2 m 1.00 100
e Jembatan Pipa bentang 3 m 1.00 100
f Jembatan Pipa bentang 4 m 2.00 150
f Jembatan Pipa bentang 5 m 1.00 300
d Crossing Jalan Aspal (panjang total 45 m) 1.00
Jumlah
IV PEKERJAAN LAIN-LAIN
1 Pembersihan lapangan setelah pekerjaan selesai 1.00 -
2 Perkiraan Utilitas 1.00 -

Jumlah
GGARAN BIAYA
ESTIMATE (EE)

Harga Satuan Jumlah Harga Total Harga


Sat.
(Rp.) (Rp.) (Rp.)
5 6 7 8

ls 5,500,000.00 5,500,000.00
ls 3,500,000.00 3,500,000.00
bh 400,000.00 400,000.00
ls 1,000,000.00 1,000,000.00
m2 500,000.00 7,500,000.00

17,900,000.00

m3 32,780.00 270,986,359.60
m3 10,926.67 83,827,874.76
m3 23,760.00 182,283,432.36

537,097,666.72

m' 1,049,819.40 7,167,117,043.80


m' 276,503.90 815,686,505.00
m' 139,136.40 845,671,039.20
m' 61,893.25 179,614,211.50 18,757.00

bh 3,201,514.00 19,209,084.00
bh 1,427,566.00 4,282,698.00
bh 873,245.65 5,239,473.90
bh 549,141.60 549,141.60
bh 326,644.60 5,552,958.20
bh 132,949.40 930,645.80
bh 843,019.55 843,019.55
bh 735,736.55 735,736.55
bh 515,780.55 3,610,463.85
bh 1,423,643.55 1,423,643.55
bh 468,887.55 468,887.55
bh 2,132,469.20 4,264,938.40
bh 498,529.20 997,058.40
bh 280,762.20 1,965,335.40
bh 124,859.20 124,859.20
bh 433,720.55 433,720.55

9,058,720,464.00

unit 105,906,676.75 105,906,676.75


unit 86,349,136.06 86,349,136.06
unit 110,850,109.80 110,850,109.80
unit 25,075,803.23 25,075,803.23
unit 25,517,476.50 25,517,476.50
unit 31,103,209.37 62,206,418.75
unit 58,769,143.49 58,769,143.49
unit 20,247,212.75 20,247,212.75
494,921,977.33

ls 18,757,000.00 18,757,000.00
ls 10,000,000.00 10,000,000.00

28,757,000.00
Jumlah Total 10,137,397,108.05
REKAPITULASI KUANTITAS DAN HARGA
ENGINEER ESTIMATE (EE)

PEKERJAAN : DED PEMBANGUNAN SPAM IKK GATAK


LOKASI : KABUPATEN SUKOHARJO
TAHUN ANGGARAN : 2013

NO URAIAN PEKERJAAN BIAYA JUMLAH BIAYA


(Rp) (Rp)

A PEKERJAAN PERSIAPAN 17,900,000.00

B SISTEM TRANMISI DAN DISTRIBUSI 9,595,818,130.72


I PEKERJAAN TANAH 537,097,666.72
II PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA + ASESORISNYA 9,058,720,464.00

C PEK. KONSTRUKSI JEMBATAN PIPA 494,921,977.33

E PEKERJAAN LAIN-LAIN 28,757,000.00

JUMLAH I 10,137,397,108.05
PPN 10% 1,013,739,710.80
JUMLAH II 11,151,136,818.85
DIBULATKAN 11,151,136,000.00

TERBILANG : SEBELAS MILYAR SERATUS LIMA PULUH SATU JUTA SERATUS TIGA PULUH ENAM RIBU RUPIAH

Sukoharjo, ....
MENGETAHUI/MENYETUJUI KONSULTAN PERENCANA
...................................... .....................................

.......................................... .....................................
....................................... Direktur
HARGA SATUAN ALAT

Harga Terendah
No Uraian Jenis Barang /Jasa/Kegiatan Satuan
(Rp)
R Alat Bantu
1 Mesin Molen Jam 23,625.00
2 Sabun Kg 20,790.00
3 Gunting Besi Jam 9,450.00
4 Mesin Las Jam 23,625.00
5 Asphalt Maxing Plant Jam 3,677,346.29
6 Asphalt Sprayer Jam 34,399.12
7 Batching Plant Jam 448,799.77
8 Concrette Mixer Truck Jam 370,287.32
9 Buldozer D 8 Jam 582,760.91
10 Compressor 4000/6500 L/M Jam 131,622.46
11 Concrete Mixer 0.3 - 0.6 m3 Jam 46,952.32
12 Concrete Vibrator Jam 45,728.66
13 Dump Truck 3 - 4 M3 Jam 279,325.76
14 Excavator PC 200 Jam 342,324.41
15 Flat Bed Truck 3 - 4 M3 Jam 247,086.16
16 Generator Set Jam 218,517.12
17 Motor Garder GD 511A-1/S1 Jam 429,328.58
18 Wheel Loader WA 180 Jam 340,670.48
19 ThreeWheel Roller 6 - 8 T Jam 217,600.55
20 Tandem roller 6 - 8 T Jam 247,071.56
21 P. Tire Roller 8 - 10 T Jam 343,527.99
22 Vibrator Roller BW 21 Jam 343,216.54
23 Concrete Cutter Jam 46,871.62
24 Water Tanker 3000 - 4500 L Jam 247,086.16
25 Stamper Jam 22,500.00
Harga Tertinggi Harga Rata-rata
(Rp) (Rp)

35,319.38 29,472.19
33,783.75 27,286.88
14,127.75 11,788.88
42,997.50 33,311.25
4,412,815.54 4,045,080.92
41,278.94 37,839.03
538,559.72 493,679.75
444,344.79 407,316.06
699,313.09 641,037.00
157,946.96 144,784.71
56,342.78 51,647.55
54,874.39 50,301.52
335,190.92 307,258.34
411,329.30 376,826.85
296,503.40 271,794.78
262,220.54 240,368.83
515,194.29 472,261.43
408,804.58 374,737.53
261,120.66 239,360.61
296,485.87 271,778.71
412,233.59 377,880.79
411,895.85 377,556.19
56,245.95 51,558.79
296,503.40 271,794.78
27,000.00 24,750.00

` `
DAFTAR HARGA SATUAN BAHAN DAN UPAH

LOKASI : KABUPATEN SUKOHARJO


TAHUN ANGGARAN : 2013

A. UPAH TENAGA
HARGA
NO. PEKERJA SATUAN SATUAN
Rp.
1 2 3 4
1 Pekerja hari 41,800
2 Mandor hari 57,200
3 Tukang hari 55,000
4 Kepala tukang hari 60,500
5 Operator hari 66,000
6 Pembantu operator hari 44,000
7 Sopir hari 66,000
8 Pembantu sopir hari 41,800
9 Penjaga malam hari 41,800
10 Depresiasi pompa injeksi unit 200,000
11 Alat bantu pekerjaan perpipaan set 50,000
B. MATERIAL
HARGA
NO. MATERIAL SATUAN SATUAN
Rp.
1 2 4 5
1 Tanah urug m³ 86,150
2 Pasir urug m³ 113,100
3 Pasir pasang m³ 127,000
4 Pasir Beton m³ 317,800
5 Batu bulat m³ 356,450
6 Batu belah 14 -15 m³ 356,450
7 Batu pecah 2-3 cm m³ 191,000
8 Batu pecah 3-5 cm m³ 356,450
9 Batu pecah 1-2 cm m³ 191,000
10 Batu pecah 0,5-1 cm m³ 191,000
11 Sirtu m³ 105,000
12 Agregat Kasar (Lokal) m³ 315,000
13 Agregat Halus (Lokal) m³ 315,000
14 Batu bata buah 1,125
15 Portland Cement ( PC ) kg 1,370
16 Beton K-175 Ready Mix m3 1,080,000
17 Beton K-275 Ready Mix m3 1,260,000
18 Beton K-300 Ready Mix m3 1,305,000
19 Beton K-350 Ready Mix m3 1,350,000
20 Beton K-500 Ready Mix m3 1,530,000
21 Paku kg 17,650
22 Besi beton prestress kg 16,250
23 Besi Strip kg 13,650
24 Besi Siku/profil kg 16,850
25 Baja IWF kg 17,640
26 Besi beton polos kg 18,000
27 Besi beton ulir kg 20,000
28 Kawat beton (bindrad) kg 23,000
29 Kawat las kg 20,600
30 Bolt M12 kg 18,000
31 Track Mur bh 18,000
32 Besi angkur + baut bh 17,400
33 Kayu Bengkire balok m3 9,800,000
34 Kayu terentang m3 2,575,000
35 Kayu Cetakan m3 2,575,000
36 Dolken kayu galam Ø 8 - 10 cm panjang 4 m batang 7,495
37 Multiplek tebal 9 mm lbr 124,480
38 Minyak bekisting ltr 24,750
39 Solar ltr 10,600
40 Minyak pelumas ltr 36,000
41 Air bersih m3 12,500
42 Kaporit kg 40,000
43 Seal tape bh 3,000
44 Lem PVC ltr 50,000
45 Meni besi kg 29,475
46 Cat besi kg 30,000
47 Amplas besi lbr 4,126
48 Minyak cat ltr 10,000
49 Plamur kg 17,685
50 Cat tembok kg 20,000
51 Kuas 3" bh 17,600
HARGA
NO. MATERIAL SATUAN SATUAN
Rp.
1 2 4 5
PIPA DAN ASSESORIES
PIPA PVC
1 Pipa PVC dengan tekanan 10 bar DN 25 mm SC m' 15,224
2 Pipa PVC dengan tekanan 10 bar DN 37,5 mm SC m' 24,420
3 Pipa PVC dengan tekanan 12,5 bar DN 50 mm RR m' 40,865
4 Pipa PVC dengan tekanan 12,5 bar DN 62,5 mm RR m' 57,475
5 Pipa PVC dengan tekanan 12,5 bar DN 75 mm RR m' 81,015
6 Pipa PVC dengan tekanan 12,5 bar DN 100 mm RR m' 121,132
7 Pipa PVC dengan tekanan 12,5 bar DN 150 mm RR m' 252,703
8 Pipa PVC dengan tekanan 12,5 bar DN 200 mm RR m' 411,620
7 Pipa PVC dengan tekanan 12,5 bar DN 250 mm RR m' 638,385
8 Pipa PVC dengan tekanan 12,5 bar DN 300 mm RR m' 1,012,396
9 Pipa PVC dengan tekanan 12,5 bar DN 400 mm RR m' 1,659,086

PIPA GIP
1 Pipa Galvanis Medium SNI BS 1387 - 85 Ø 37.5 mm m' 87,800
2 Pipa Galvanis Medium SNI BS 1387 - 85 Ø 50 mm m' 123,300
3 Pipa Galvanis Medium SNI BS 1387 - 85 Ø 62,5 mm m' 157,100
4 Pipa Galvanis Medium SNI BS 1387 - 85 Ø 75 mm m' 206,600
5 Pipa Galvanis Medium SNI BS 1387 - 85 Ø100 mm m' 294,400
6 Pipa Galvanis Medium SNI BS 1387 - 85 Ø125 mm m' 392,800
7 Pipa Galvanis Medium SNI BS 1387 - 85 Ø150 mm m' 470,200
8 Pipa Galvanis Medium SNI BS 1387 - 85 Ø200 mm m' 890,800
9 Pipa Galvanis Medium SNI BS 1387 - 85 Ø250 mm m' 1,116,500
10 Pipa Galvanis Medium SNI BS 1387 - 85 Ø300 mm m' 1,228,000
11 Pipa Galvanis Medium SNI BS 1387 - 85 Ø400 mm m' 1,581,000

ACCESORIES PERPIPAAN
1 Long bend 90° PVC DN 75 mm double socket RR bh 124,894.00
2 Long bend 90° PVC DN 100 mm double socket RR bh 316,393.00
3 Long bend 90° PVC DN 150 mm double socket RR bh 636,559.00
4 Long bend 90° PVC DN 200 mm double socket RR bh 1,109,823.00
5 Long bend 90° PVC DN 250 mm double socket RR bh 1,918,433.00
6 Long bend 90° PVC DN 300 mm double socket RR bh 3,182,938.00
7 Long bend 90° PVC DN 400 mm double socket RR bh 14,353,273.00
8 Long bend 45° PVC DN 100 mm double socket RR bh 289,124.00
9 Long bend 45° PVC DN 150 mm double socket RR bh 570,482.00
10 Long bend 45° PVC DN 200 mm double socket RR bh 972,818.00
11 Long bend 45° PVC DN 250 mm double socket RR bh 1,764,917.00
12 Long bend 45° PVC DN 300 mm double socket RR bh 2,895,541.00
13 Long bend 22,50° PVC DN 100 mm double socket RR bh 267,564.00
14 Long bend 22,50° PVC DN 250 mm double socket RR bh 1,504,701.00
15 Long bend 11,25° PVC DN 100 mm double socket RR bh 251,768.00
16 Long bend 11,25° PVC DN 75 mm double socket RR bh 95,865.00
17 Long bend 11,25° PVC DN 150 mm double socket RR bh 469,535.00
18 Long bend 11,25° PVC DN 200 mm double socket RR bh 769,219.00
19 Long bend 11,25° PVC DN 250 mm double socket RR bh 1,327,359.00
20 Long bend 11,25° PVC DN 300 mm double socket RR bh 2,103,475.00
21 Tee All Flange CI. Ø 100 . 75 mm bh 433,620.00
22 Tee All Flange CI. Ø 250 .100 mm bh 1,395,350.00
23 Tee All Flange CI. Ø 300. 200 mm bh 1,860,430.00
24 Tee all socket. PVC RRJ SNI DN 400 x 300 mm bh 7,215,450.00
25 Tee all socket. PVC RRJ SNI DN 300 x 100 mm bh 3,112,230.00
26 Tee all socket. PVC RRJ SNI DN 200 x 150 mm bh 1,678,600.00
27 Tee all socket. PVC RRJ SNI DN 200 x 100 mm bh 1,390,950.00
28 Tee all socket. PVC RRJ SNI DN 100 x 100 mm bh 436,194.00
29 Tee all socket. PVC RRJ SNI DN 200 x 75 mm bh 1,443,695.00
HARGA
NO. MATERIAL SATUAN SATUAN
Rp.
1 2 4 5
30 Tee all socket. PVC RRJ SNI DN 100 x 75 mm bh 483,087.00
31 Tee all socket. PVC RRJ SNI DN 150 x 150 mm bh 810,326.00
32 Tee all socket. PVC RRJ SNI DN 150 x 100 mm bh 703,043.00
33 Reducer PVC SNI DN 400 x 100 mm 1,732,500.00
34 Reducer PVC SNI DN 200 x 150 mm 730,257.00
35 Reducer PVC SNI DN 200 x 100 mm 1,056,000.00
36 Reducer PVC SNI DN 150 x 100 mm 401,027.00

37 All flange bend 90° DN 75 mm (CI) bh 260,000.00


38 All flange bend 90° DN 100 mm (CI) bh 332,000.00
39 All flange bend 90° DN 250 mm (CI) bh 588,500.00
40 All flange bend 90° DN 300 mm (CI) bh 1,938,475.00
41 All flange bend 45° x 100 mm (CI) bh 332,000.00
42 All flange bend 45° x 150 mm (CI) bh 538,890.00
43 All flange bend 45° x 200 mm (CI) bh 656,535.00
44 All flange bend 45° x 250 mm (CI) bh 566,500.00
45 All flange bend 45° x 300 mm (CI) bh 1,408,990.00
46 Box Air valve 50 x 50 unit 300,000.00
47 Bend las 22,5° x 100 bh 121,000.00
48 Bend las 22,5° x 250 bh 385,000.00
49 All flange Gate valve DN 100 mm (PN 10) bh 1,210,000.00
50 All flange Gate valve DN 250 mm (PN 10) bh 5,225,000.00
51 All flange Gate valve DN 300 mm (PN 10) bh 7,601,418.00
52 Flange las DN 100 mm (PN 10) bh 88,000.00
53 Flange las DN 150 mm (PN 10) bh 184,360.00
54 Flange las DN 200 mm (PN 10) bh 225,940.00
55 Flange las DN 250 mm (PN 10) bh 364,100.00
56 Flange las DN 300 mm (PN 10) bh 399,630.00
57 Flange socket DN 100 mm (PVC) bh 520,850.00
58 Flange socket DN 250 mm (PVC) bh 1,998,425.00
59 Flange Socket DN 100 mm (CI) bh 608,160.00
60 Flange Socket DN 200 mm (CI) bh 590,881.50
61 Flange Socket DN 250 mm (CI) bh 3,407,860.00
62 Flange Socket DN 300 mm (CI) bh 4,424,266.00
63 Flange Spigot DN 300 mm (CI) bh 4,147,000.00
64 Flange Spigot DN 100 mm (CI) bh 563,728.00
65 Street Box DN 100 mm unit 126,500.00
66 Street Box DN 250 mm unit 506,000.00
67 Street Box DN 300 mm unit 715,000.00
68 Air Valve DN 25 mm lengkap unit 330,000.00
69 Double Nipple DN 25 mm bh 6,050.00
70 Doop RR PVC DN 100 mm bh 56,628.00
71 Doop RR PVC DN 200 mm bh 335,742.00
72 Doop RR PVC DN 250 mm bh 634,007.00
73 Karet packing DN 100 mm (t = 5 mm) bh 15,000.00
74 Karet packing DN 250 mm (t = 5 mm) bh 25,000.00
75 Water Meter Cast Iron 100 mm unit 2,860,000.00
76 Water Meter Cast Iron 250 mm unit 12,100,000.00
ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN : DED PEMBANGUNAN SPAM IKK GATAK

LOKASI : KABUPATEN SUKOHARJO


TAHUN ANGGARAN : 2013

6. Penetapan Indeks Harga Satuan Pekerjaan Tanah (03-2835-2008)

1 Menggali 1 m3 tanah biasa sedalam 1 meter

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Pekerja OH 0.750 41,800.00 31,350.00
Tenaga Kerja
Mandor OH 0.025 57,200.00 1,430.00
Jumlah Harga Per Satuan Pekerjaan 32,780.00

2 Menggali 1 m3 tanah biasa sedalam 2 meter

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Pekerja OH 0.900 41,800.00 37,620.00
Tenaga Kerja
Mandor OH 0.045 57,200.00 2,574.00
Jumlah Harga Per Satuan Pekerjaan 40,194.00
3 Menggali 1 m3 tanah keras sedalam 1 meter

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Pekerja OH 1.000 41,800.00 41,800.00
Tenaga Kerja
Mandor OH 0.032 57,200.00 1,830.40
Jumlah Harga Per Satuan Pekerjaan 43,630.40

4 Menggali 1 m3 tanah cadas sedalam 1 meter

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Pekerja OH 1.500 41,800.00 62,700.00
Tenaga Kerja
Mandor OH 0.060 57,200.00 3,432.00
Jumlah Harga Per Satuan Pekerjaan 66,132.00

5 Mengurug kembali 1 m3 galian

Mengurug kembali 1 m3 galian dihitung dari 1/3 kali dari harga indeks pekerjaan galian.

6 Memadatkan 1 m3 tanah (per 20 cm)

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Pekerja OH 0.500 41,800.00 20,900.00
Tenaga Kerja
Mandor OH 0.050 57,200.00 2,860.00
Jumlah Harga Per Satuan Pekerjaan 23,760.00

7 Mengurug 1 m3 pasir urug

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Bahan Pasir Urug m3 1.200 113,100.00 135,720.00
Pekerja OH 0.300 41,800.00 12,540.00
Tenaga Kerja
Tenaga Kerja
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 148,832.00

8 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Bahan Sirtu m3 1.200 105,000.00 126,000.00
Tenaga Kerja Pekerja OH 0.250 41,800.00 10,450.00
Mandor OH 0.025 57,200.00 1,430.00
Jumlah Harga Per Satuan Pekerjaan 137,880.00

9 Mengurug 1 m3 dengan tanah urug padat bahan didatangkan

Harga Satuan
Kebutuhan Satuan Indeks Jumlah (Rp.)
Bahan / Upah
Bahan tanah urug m3 1.200 86,150.00 103,380.00
Tenaga Kerja Pekerja OH 0.250 41,800.00 10,450.00
Mandor OH 0.025 57,200.00 1,430.00
Jumlah Harga Per Satuan Pekerjaan 115,260.00

6 Penetapan indeks harga satuan pekerjaan pondasi (S03-2836-2008)

10 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP

Kebutuhan Satuan Indeks Harga Satuan Jumlah


Bahan / Upah (Rp.)
(Rp.)
Bahan Batu belah 15cm/20cm m3 1.200 356,450.00 427,740.00
PC kg 202.000 1,370.00 276,740.00
PP m3 0.485 127,000.00 61,595.00
Tenaga Kerja Pekerja OH 1.500 41,800.00 62,700.00
tukang batu OH 0.600 55,000.00 33,000.00
Kepala tukang OH 0.060 60,500.00 3,630.00
Mandor OH 0.075 57,200.00 4,290.00
Jumlah Harga Per Satuan Pekerjaan 869,695.00

11 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP

Kebutuhan Satuan Indeks Harga Satuan Jumlah


Bahan / Upah (Rp.)
(Rp.)
Bahan Batu belah 15cm/20cm m3 1.200 356,450.00 427,740.00
PC kg 163.000 1,370.00 223,310.00
PP m3 0.520 127,000.00 66,040.00
Tenaga Kerja Pekerja OH 1.500 41,800.00 62,700.00
tukang batu OH 0.600 55,000.00 33,000.00
Kepala tukang OH 0.060 60,500.00 3,630.00
Mandor OH 0.075 57,200.00 4,290.00
Jumlah Harga Per Satuan Pekerjaan 820,710.00

12 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Batu belah 15cm/20cm m3 1.200 356,450.00 427,740.00
Bahan Portland cement kg 136.000 1,370.00 186,320.00
Pasir Pasang m3 0.544 127,000.00 69,088.00
Pekerja OH 1.500 41,800.00 62,700.00

Tenaga Kerja
tukang batu OH 0.600 55,000.00 33,000.00
Tenaga Kerja
Kepala tukang OH 0.060 60,500.00 3,630.00
Mandor OH 0.075 57,200.00 4,290.00
Jumlah Harga Per Satuan Pekerjaan 786,768.00

13 Memasang 1 m3 batu kosong (aanstamping)

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Batu belah 15cm/20cm m3 1.200 356,450.00 427,740.00
Bahan
Pasir Urug m3 0.432 113,100.00 48,859.20
Pekerja OH 0.780 41,800.00 32,604.00
tukang batu OH 0.390 55,000.00 21,450.00
Tenaga Kerja
Kepala tukang OH 0.039 60,500.00 2,359.50
Mandor OH 0.039 57,200.00 2,230.80
Jumlah Harga Per Satuan Pekerjaan 535,243.50

6 Pekerjaan Plesteran

14 1 m2 Plesteran 1 pc : 3 Pp, tebal 15 mm

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 7.776 1,370.00 10,653.12
Bahan
Pasir Pasang m3
0.023 127,000.00 2,921.00
Pekerja OH 0.200 41,800.00 8,360.00
tukang batu OH 0.150 55,000.00 8,250.00
Tenaga
Kepala tukang OH 0.015 60,500.00 907.50
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 31,663.62

15 1 m2 Plesteran 1 pc : 4 Pp, tebal 15 mm

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 6.240 1,370.00 8,548.80
Bahan
Pasir Pasang m3 0.024 127,000.00 3,048.00
Pekerja OH 0.200 41,800.00 8,360.00
tukang batu OH 0.150 55,000.00 8,250.00
Tenaga
Kepala tukang OH 0.015 60,500.00 907.50
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 29,686.30

16 1 m² Finishing Siar pas. Batu Kali Adukan, 1 Pc : 2 Pp

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 6.340 1,370.00 8,685.80
Bahan
Pasir Pasang m3 0.012 127,000.00 1,524.00
Pekerja OH 0.300 41,800.00 12,540.00
tukang batu OH 0.140 55,000.00 7,700.00
Tenaga
Kepala tukang OH 0.014 60,500.00 847.00
Mandor OH 0.015 57,200.00 858.00
Jumlah Harga Per Satuan Pekerjaan 32,154.80
17 1 m² acian

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Bahan Portland cement kg 3.250 1,370.00 4,452.50
Pekerja OH 0.150 41,800.00 6,270.00
tukang batu OH 0.100 55,000.00 5,500.00
Tenaga
Kepala tukang OH 0.010 60,500.00 605.00
Mandor OH 0.008 57,200.00 457.60
Jumlah Harga Per Satuan Pekerjaan 17,285.10

6 Penetapan indeks harga satuan pekerjaan beton (03-7394-2008)

18 Membuat 1m3 Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 230 1,370.00 315,100.00
PB kg 893 227.00 202,711.00
Bahan
KR (maksimum 30 mm) kg 1,027 141.48 145,301.48
Air Liter 200 12.50 2,500.00
Pekerja OH 1.200 41,800.00 50,160.00
Tukang batu OH 0.200 55,000.00 11,000.00
Tenaga Kerja
Kepala tukang OH 0.020 60,500.00 1,210.00
Mandor OH 0.006 57,200.00 343.20
Jumlah Harga Per Satuan Pekerjaan 728,325.68

19 Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K 125), Slump (12 ± 2) cm, w/c = 0,78

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 276 1,370.00 378,120.00
PB kg 828 227.00 187,956.00
Bahan
KR (maksimum 30 mm) kg 1,012 141.48 143,179.26
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 802,479.36

20 Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K 150), Slump (12 ± 2) cm, w/c = 0,72

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 299 1,370.00 409,630.00
PB kg 799 227.00 181,373.00
Bahan
KR (maksimum 30 mm) kg 1,017 141.48 143,886.67
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 828,113.77
CATATAN :
Bobot isi pasir = 1,400 kg/m3, Bobot isi kerikil 1,350 kg/m3, bukling factor pasir = 20 %

21 Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, w/c = 0,66

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 326 1,370.00 446,620.00
PB kg 760 227.00 172,520.00
Bahan
KR (maksimum 30 mm) kg 1,029 141.48 145,584.44
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 857,948.54

22 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, w/c = 0,61

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 352 1,370.00 482,240.00
PB kg 731 227.00 165,937.00
Bahan
KR (maksimum 30 mm) kg 1,031 141.48 145,867.41
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 887,268.51

23 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, w/c = 0,58

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 371 1,370.00 508,270.00
PB kg 698 227.00 158,446.00
Bahan
KR (maksimum 30 mm) kg 1,047 141.48 148,131.11
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 908,071.21

24 Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, w/c = 0,56

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 384 1,370.00 526,080.00
PB kg 692 227.00 157,084.00
Bahan
KR (maksimum 30 mm) kg 1,039 141.48 146,999.26
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Tenaga Kerja

Mandor OH 0.083 57,200.00 4,747.60


Jumlah Harga Per Satuan Pekerjaan 923,387.36

25 Membuat 1 m3 beton mutu f'c = 24,0 Mpa (K 275), Slump (12 ± 2) cm, w/c = 0,53

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 406 1,370.00 556,220.00
PB kg 684 227.00 155,268.00
Bahan
KR (maksimum 30 mm) kg 1,026 141.48 145,160.00
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 949,872.10

26 Membuat 1 m3 beton mutu f'c = 26,4 Mpa (K 300), Slump (12 ± 2) cm, w/c = 0,52

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 413 1,370.00 565,810.00
PB kg 681 227.00 154,587.00
Bahan
KR (maksimum 30 mm) kg 1,021 141.48 144,452.59
Air Liter 215 12.50 2,687.50
Pekerja OH 1.650 41,800.00 68,970.00
Tukang batu OH 0.275 55,000.00 15,125.00
Tenaga Kerja
Kepala tukang OH 0.028 60,500.00 1,694.00
Mandor OH 0.083 57,200.00 4,747.60
Jumlah Harga Per Satuan Pekerjaan 958,073.69

27 Membuat 1 m3 Beton K-175 readymix

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Bahan Adukan beton K-175 ready mix m3 1.000 1,080,000.00 1,080,000.00
Pekerja OH 0.057 41,800.00 2,378.42
Tenaga Kerja Tukang batu OH 0.285 55,000.00 15,647.50
Mandor OH 0.569 57,200.00 32,541.08
Concrete vibrator jam 0.057 50,301.52 2,862.16
Peralatan
Alat bantu set 0.100 50,000.00 5,000.00
Jumlah Harga Per Satuan Pekerjaan 1,138,429.16

28 Membuat 1 m3 Beton K-350 readymix

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Bahan Adukan beton K-350 ready mix m3 1.000 1,350,000.00 1,350,000.00
Pekerja OH 0.057 41,800.00 2,378.42
Tenaga Kerja Tukang batu OH 0.341 55,000.00 18,777.00
Mandor OH 0.683 57,200.00 39,050.44
Concrete vibrator jam 0.057 50,301.52 2,862.16
Peralatan
Alat bantu set 0.100 50,000.00 5,000.00
Jumlah Harga Per Satuan Pekerjaan 1,418,068.02
29 Membuat 1 m3 Beton K-500 readymix

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Bahan Adukan beton K-500 ready mix m3 1.000 1,530,000.00 1,530,000.00
Pekerja OH 0.057 41,800.00 2,378.42
Tenaga Kerja Tukang batu OH 0.455 55,000.00 25,036.00
Mandor OH 0.910 57,200.00 52,069.16
Concrete vibrator jam 0.057 50,301.52 2,862.16
Peralatan
Alat bantu set 0.100 50,000.00 5,000.00
Jumlah Harga Per Satuan Pekerjaan 1,617,345.74

30 Pembongkaran 1 m3 Beton (dengan alat)

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Pekerja OH 1.786 41,800.00 74,642.26
Tenaga Kerja
Mandor OH 0.149 57,200.00 8,511.36
Jack hammer jam 1.042 32,633.70 33,994.53
Compressor 4000-6500 ℓ\m jam 1.042 131,689.80 137,181.26
Peralatan Wheel loader 1,0-1,6 m³ jam 0.010 299,772.00 3,027.70
Dump truck 7,5 ton jam 0.192 219,151.90 41,967.59
Alat bantu set 0.100 50,000.00 5,000.00
Jumlah Harga Per Satuan Pekerjaan 304,324.70

31 Pembongkaran 1 m3 Pasangan batu (dengan alat)

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Pekerja OH 0.893 41,800.00 37,323.22
Tenaga Kerja
Mandor OH 0.074 57,200.00 4,255.68
Jack hammer jam 0.521 32,633.70 16,995.63
Compressor 4000-6500 ℓ\m jam 0.521 131,689.80 68,584.05
Peralatan Wheel loader 1,0-1,6 m³ jam 0.010 299,772.00 3,027.70
Dump truck 7,5 ton jam 0.192 219,151.90 41,967.59
Alat bantu set 0.100 50,000.00 5,000.00
Jumlah Harga Per Satuan Pekerjaan 177,153.86

32 Pembongkaran 1 m3 jalan aspal (manual)


di hitung
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Pekerja OH 1.589 41,800.00 66,431.61
Tenaga Kerja
Mandor OH 0.119 57,200.00 6,809.09
Jack hammer jam 0.833 32,633.70 27,195.62
Compressor 4000-6500 ℓ\m jam 0.833 131,689.80 109,745.01
Peralatan Wheel loader 1,0-1,6 m³ jam 0.008 299,772.00 2,422.16
Dump truck 7,5 ton jam 0.153 219,151.90 33,574.07
Alat bantu set 0.100 50,000.00 5,000.00
Jumlah Harga Per Satuan Pekerjaan 251,177.56
33 Pembesian 10 kg dengan besi polos

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Besi beton (polos) kg 10.500 18,000.00 189,000.00
Bahan
Kawat beton kg 0.150 23,000.00 3,450.00
Pekerja OH 0.070 41,800.00 2,926.00
tukang besi OH 0.070 55,000.00 3,850.00
Tenaga Kerja
Kepala tukang OH 0.007 60,500.00 423.50
Mandor OH 0.004 57,200.00 228.80
Jumlah Harga Per Satuan Pekerjaan ( per 10 kg) 199,878.30
Jumlah Harga Per Satuan Pekerjaan ( per 1 kg) 19,987.83

34 Pembesian 10 kg dengan besi ulir

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Besi beton (ulir) kg 10.500 20,000.00 210,000.00
Bahan
Kawat beton kg 0.150 23,000.00 3,450.00
Pekerja OH 0.070 41,800.00 2,926.00
tukang besi OH 0.070 55,000.00 3,850.00
Tenaga Kerja
Kepala tukang OH 0.007 60,500.00 423.50
Mandor OH 0.004 57,200.00 228.80
Jumlah Harga Per Satuan Pekerjaan ( per 10 kg) 220,878.30
Jumlah Harga Per Satuan Pekerjaan ( per 1 kg) 22,087.83

35 Memasang 1 m2 bekisting untuk lantai

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
50% Kayu kelas III m3 0.040 1,287,500.000 51,500.00
Paku 5 cm - 12 cm Kg 0.400 17,650.000 7,060.00
Minyak bekisting Liter 0.200 24,750.000 4,950.00
50% Bahan Balok kayu kelas II m3 0.015 1,287,500.000 19,312.50
50% Multyplex tebal 9 mm Lembar 0.350 62,240.000 21,784.00

Dolken kayu Ø (8 - 10) cm, panjang 4 m Batang 6.000 3,747.50 22,485.00


50%
Pekerja OH 0.660 41,800.00 27,588.00
tukang besi OH 0.330 55,000.00 18,150.00
Tenaga Kerja
Kepala tukang OH 0.033 60,500.00 1,996.50
Mandor OH 0.033 57,200.00 1,887.60
Jumlah Harga Per Satuan Pekerjaan 176,713.60
36 Memasang 1 m2 bekisting untuk dinding

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
50% Kayu kelas III m3 0.030 1,287,500.000 38,625.00
Paku 5 cm - 12 cm Kg 0.400 17,650.000 7,060.00
Minyak bekisting Liter 0.200 24,750.000 4,950.00
50% Balok kayu kelas II m3 0.020 1,287,500.000 25,750.00
50% Bahan Playwood tebal 9 mm Lembar 0.350 62,240.000 21,784.00
Dolken kayu galam, Ø (8 - 10) cm,
Batang 3.000 3,747.50 11,242.50
50% panjang 4 m
Formite / penjaga jarakBekisting /
Buah 4.000 1,500.00 6,000.00
spacer
Pekerja OH 0.660 41,800.00 27,588.00
tukang besi OH 0.330 55,000.00 18,150.00
Tenaga Kerja
Kepala tukang OH 0.033 60,500.00 1,996.50
Mandor OH 0.033 57,200.00 1,887.60
Jumlah Harga Per Satuan Pekerjaan 165,033.60

37 Memasang 1 m2 bekisting untuk pondasi

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
50% Kayu kelas III m3 0.040 1,287,500.000 51,500.00
Bahan Paku 5 cm - 10 cm Kg 0.300 17,650.000 5,295.00
Minyak bekisting Liter 0.100 24,750.000 2,475.00
Pekerja OH 0.520 41,800.00 21,736.00
tukang besi OH 0.260 55,000.00 14,300.00
Tenaga Kerja
Kepala tukang OH 0.026 60,500.00 1,573.00
Mandor OH 0.026 57,200.00 1,487.20
Jumlah Harga Per Satuan Pekerjaan 98,366.20

6 Penetapan Indeks Harga Satuan Pekerjaan Besi dan Alumunium (03-7393-2008)

38 Memasang 1 kg besi profil

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Besi profil Kg 1.150 16,850.00 19,377.50
Bahan
Meni besi Kg 0.060 29,475.00 1,768.50
Pekerja OH 0.060 41,800.00 2,508.00
Tukang las OH 0.060 55,000.00 3,300.00
Tenaga Kerja
Kepala tukang OH 0.006 60,500.00 363.00
Mandor OH 0.003 57,200.00 171.60
Jumlah Harga Per Satuan Pekerjaan 27,488.60

39 Memasang 1 kg Rangka Baja IWF

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Bahan Besi baja IWF Kg 1.150 17,640.00 20,286.00
Pekerja OH 0.060 41,800.00 2,508.00
Tukang las OH 0.060 55,000.00 3,300.00
Tenaga Kerja
Kepala tukang OH 0.006 60,500.00 363.00
Tenaga Kerja

Mandor OH 0.003 57,200.00 171.60


Jumlah Harga Per Satuan Pekerjaan 26,628.60

40 Perakitan (Erection) 1 kg kuda- kuda baja

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Solar lt 1.000 10,600.00 10,600.00
Bahan
Minyak pelumas lt 0.100 36,000.00 3,600.00
Pekerja OH 1.050 41,800.00 43,890.00
Tukang besi OH 1.050 55,000.00 57,750.00
Tenaga Kerja
Kepala tukang OH 0.105 60,500.00 6,352.50
Mandor OH 0.005 57,200.00 297.44
Alat Sewa Alat jam 0.008 350,000.00 2,800.00
Jumlah Harga Per Satuan Pekerjaan (100kg) 125,289.94
Jumlah Harga Per Satuan Pekerjaan (1kg) 1,252.90

6 Penetapan Indeks Harga Satuan Pekerjaan Plesteran (03-2837-2008)

41 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm (plesteran beton)

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 10.224 1,370.00 14,006.88
Bahan
Pasir Pasang (Muntilan) m3 0.020 317,800.00 6,356.00
Pekerja OH 0.200 41,800.00 8,360.00
Tukang batu OH 0.150 55,000.00 8,250.00
Tenaga Kerja
Kepala tukang OH 0.015 60,500.00 907.50
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 38,452.38

42 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 7.776 1,370.00 10,653.12
Bahan
Pasir Pasang m3 0.023 127,000.00 2,921.00
Pekerja OH 0.200 41,800.00 8,360.00
Tukang batu OH 0.150 55,000.00 8,250.00
Tenaga Kerja
Kepala tukang OH 0.015 60,500.00 907.50
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 31,663.62

43 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 6.240 1,370.00 8,548.80
Bahan
Pasir Pasang m3
0.024 127,000.00 3,048.00
Pekerja OH 0.200 41,800.00 8,360.00
Tukang batu OH 0.150 55,000.00 8,250.00
Tenaga Kerja
Kepala tukang OH 0.015 60,500.00 907.50
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 29,686.30
44 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Portland cement kg 5.184 1,370.00 7,102.08
Bahan
Pasir Pasang m3 0.026 127,000.00 3,302.00
Pekerja OH 0.200 41,800.00 8,360.00
Tukang batu OH 0.150 55,000.00 8,250.00
Tenaga Kerja
Kepala tukang OH 0.015 60,500.00 907.50
Mandor OH 0.010 57,200.00 572.00
Jumlah Harga Per Satuan Pekerjaan 28,493.58

45 Memasang 1 m2 plesteran skoning 1 PC : 2 PP, lebar 10 mm

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 0.500 1,370.00 685.00
Bahan
PP muntilan m3
0.013 317,800.00 4,131.40
Pekerja OH 0.057 41,800.00 2,382.60
Tukang batu OH 0.380 55,000.00 20,900.00
Tenaga Kerja
Kepala tukang OH 0.038 60,500.00 2,299.00
Mandor OH 0.003 57,200.00 171.60
Jumlah Harga Per Satuan Pekerjaan 30,569.60

46 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
PC kg 6.340 1,370.00 8,685.80
Bahan
PP m3 0.012 127,000.00 1,524.00
Pekerja OH 0.300 41,800.00 12,540.00
Tukang batu OH 0.140 55,000.00 7,700.00
Tenaga Kerja
Kepala tukang OH 0.014 60,500.00 847.00
Mandor OH 0.015 57,200.00 858.00
Jumlah Harga Per Satuan Pekerjaan 32,154.80

47 Memasang 1 m3 Lapis Pondasi Agregat Kelas B (manual)

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Agregat Kasar (Lokal) M3 0.420 315,000.00 132,300.00
Bahan Agregat Halus (Lokal) M3 0.240 315,000.00 75,600.00
Sirtu M3 0.540 105,000.00 56,700.00
Pekerja jam 0.250 5,971.43 1,492.19
Tenaga
Mandor jam 0.036 8,171.43 291.71
Wheel Loader jam 0.036 374,737.53 13,377.51
Dump Truck jam 0.145 307,258.34 44,609.72
Alat
Three Wheel Roller 6 - 8 T jam 0.018 239,360.61 4,272.39
Alat Bantu Ls 1.000 500.00 500.00
Jumlah Harga Per Satuan Pekerjaan 329,143.52
48 1 m' Pengadaan dan Pemancangan Kayu Ulin

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Ulin 10/10 M3 0.010 #REF! #REF!
Bahan Ulin 5/10 ( Sunduk) M3 0.003 #REF! #REF!
Ulin 2/20 ( Kalang) M3 0.002 #REF! #REF!
Pekerja jam 2.500 5,971.43 14,928.57
Tenaga Tukang jam 0.250 7,857.14 1,964.29
Mandor jam 0.250 8,171.43 2,042.86
Alat Alat Bantu Ls 1.000 1,000.00 1,000.00
Jumlah Harga Per Satuan Pekerjaan #REF!

49 1 m' Pemancangan Kayu Ulin

Harga Satuan Jumlah


Kebutuhan Satuan Indeks Bahan / Upah (Rp.)
(Rp.)
Pekerja jam 2.500 5,971.43 14,928.57
Tenaga Tukang jam 0.250 7,857.14 1,964.29
Mandor jam 0.250 8,171.43 2,042.86
Alat Alat Bantu Ls 1.000 1,000.00 1,000.00
Jumlah Harga Per Satuan Pekerjaan 19,935.71
DAFTAR ANALISA PEKERJAAN PERPIPAAN

PEKERJAAN : DED PEMBANGUNAN SPAM IKK GATAK


LOKASI : KABUPATEN SUKOHARJO

TAHUN ANGGA : 2013

NO. HARGA UPAH HARGA JUMLAH


KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
I PENGADAAN DAN PEMASANGAN PIPA
Hitung.P.01 Pengadaan dan Pemasangan Pipa PVC ND 50 mm (SCJ), S-10 (PN 10) per m'
1.0000 m' Pipa PVC ND 50 mm (SCJ), S -12.5 (PN 10) 24,420.00 24,420.00 24,420.00
0.0350 Pekerja 41,800.00 1,463.00 1,463.00
0.0250 Tukang Pipa 55,000.00 1,375.00 1,375.00
0.0025 Mandor 57,200.00 143.00 143.00
1.0000 Ls Alat Bantu 500.00 500.00 500.00
2,981.00 24,920.00 27,901.00

Hitung.P.02 Pengadaan dan Pemasangan Pipa PVC ND 75 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 75 mm (RRJ), (S-10 - 12,5 bar) 57,475.00 57,475.00 57,475.00
0.0350 Pekerja 41,800.00 1,463.00 1,463.00
0.0250 Tukang Pipa 55,000.00 1,375.00 1,375.00
0.0025 Kepala Tukang Pipa 60,500.00 151.25 151.25
0.0075 Mandor 57,200.00 429.00 429.00
1.0000 Ls Alat Bantu 1,000.00 1,000.00 1,000.00
3,418.25 58,475.00 61,893.25

Hitung.P.03 Pengadaan dan Pemasangan Pipa PVC ND 100 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 100 mm (RRJ), (S-10 - 12,5 bar) 121,132.00 121,132.00 121,132.00
0.2550 Pekerja 41,800.00 10,659.00 10,659.00
0.0850 Tukang Pipa 55,000.00 4,675.00 4,675.00
0.0080 Kepala Tukang Pipa 60,500.00 484.00 484.00
0.0120 Mandor 57,200.00 686.40 686.40
1.0000 Ls Alat Bantu 1,500.00 1,500.00 1,500.00
16,504.40 122,632.00 139,136.40

Hitung.P.04 Pengadaan dan Pemasangan Pipa PVC ND 150 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 150 mm (RRJ), (S-10 - 12,5 bar) 252,703.00 252,703.00 252,703.00
0.2500 Pekerja 41,800.00 10,450.00 10,450.00
0.1700 Tukang Pipa 55,000.00 9,350.00 9,350.00
0.0170 Kepala Tukang Pipa 60,500.00 1,028.50 1,028.50
0.0170 Mandor 57,200.00 972.40 972.40
1.0000 Ls Alat Bantu 2,000.00 2,000.00 2,000.00
21,800.90 254,703.00 276,503.90

Hitung.P.05 Pengadaan dan Pemasangan Pipa PVC ND 200 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 200 mm (RRJ), (S-10 - 12,5 bar) 411,620.00 411,620.00 411,620.00
0.3000 Pekerja 41,800.00 12,540.00 12,540.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0220 Mandor 57,200.00 1,258.40 1,258.40
1.0000 Ls Alat Bantu 2,500.00 2,500.00 2,500.00
26,008.40 414,120.00 440,128.40

Hitung.P.06 Pengadaan dan Pemasangan Pipa PVC ND 250 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 250 mm (RRJ), (S-10 - 12,5 bar) 638,385.00 638,385.00 638,385.00
0.3500 Pekerja 41,800.00 14,630.00 14,630.00
0.2300 Tukang Pipa 55,000.00 12,650.00 12,650.00
0.0230 Kepala Tukang Pipa 60,500.00 1,391.50 1,391.50
0.0270 Mandor 57,200.00 1,544.40 1,544.40
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
1.0000 Ls Alat Bantu 3,000.00 3,000.00 3,000.00
30,215.90 641,385.00 671,600.90

Hitung.P.07 Pengadaan dan Pemasangan Pipa PVC ND 300 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 300 mm (RRJ), (S-10 - 12,5 bar) 1,012,396.00 1,012,396.00 1,012,396.00
0.4000 Pekerja 41,800.00 16,720.00 16,720.00
0.2600 Tukang Pipa 55,000.00 14,300.00 14,300.00
0.0260 Kepala Tukang Pipa 60,500.00 1,573.00 1,573.00
0.0320 Mandor 57,200.00 1,830.40 1,830.40
1.0000 Ls Alat Bantu 3,000.00 3,000.00 3,000.00
34,423.40 1,015,396.00 1,049,819.40

Hitung.P.08 Pengadaan dan Pemasangan Pipa PVC ND 400 mm (RRJ), (S-10 - 12,5 bar) per m'
1.0000 m' Pipa PVC ND 400 mm (RRJ), (S-10 - 12,5 bar) 1,659,086.00 1,659,086.00 1,659,086.00
0.5000 Pekerja 41,800.00 20,900.00 20,900.00
0.3200 Tukang Pipa 55,000.00 17,600.00 17,600.00
0.0320 Kepala Tukang Pipa 60,500.00 1,936.00 1,936.00
0.0420 Mandor 57,200.00 2,402.40 2,402.40
1.0000 Ls Alat Bantu 3,000.00 3,000.00 3,000.00
42,838.40 1,662,086.00 1,704,924.40

Hitung.P.09 Pengadaan dan Pemasangan Pipa GI ND 75 mm per m'


1.0000 m' Pipa GI F 75 mm 206,600.00 206,600.00 206,600.00
0.1547 kg kawat las 20,600.00 3,186.82 3,186.82
0.7441 lt solar 10,600.00 7,887.46 7,887.46
0.1170 lot Mesin las 33,311.25 3,897.42 3,897.42
0.2330 lot Alat bantu 50,000.00 11,650.00 11,650.00
0.2330 Pekerja 41,800.00 9,739.40 9,739.40
0.1170 Tukang Las 55,000.00 6,435.00 6,435.00
0.1170 Tukang Pipa 55,000.00 6,435.00 6,435.00
0.0117 Kepala Tukang Pipa 60,500.00 707.85 707.85
0.0350 Mandor 57,200.00 2,002.00 2,002.00
0.1000 Biaya Overhead Pemasangan 25,319.25 2,531.93 2,531.93
27,851.18 233,221.70 261,072.87
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Hitung.P.10 Pengadaan dan Pemasangan Pipa GI ND 100 mm per m'
1.0000 m' Pipa GI F 100 mm 294,400.00 294,400.00 294,400.00
0.1768 kg kawat las 20,600.00 3,642.08 3,642.08
0.8504 lt solar 10,600.00 9,014.24 9,014.24
0.1340 lot Mesin las 33,311.25 4,463.71 4,463.71
0.2660 lot Alat bantu 50,000.00 13,300.00 13,300.00
0.2660 Pekerja 41,800.00 11,118.80 11,118.80
0.1340 Tukang Las 55,000.00 7,370.00 7,370.00
0.1340 Tukang Pipa 55,000.00 7,370.00 7,370.00
0.0134 Kepala Tukang Pipa 60,500.00 810.70 810.70
0.0400 Mandor 57,200.00 2,288.00 2,288.00
0.1000 Biaya Overhead Pemasangan 28,957.50 2,895.75 2,895.75
31,853.25 324,820.03 356,673.28

Hitung.P.11 Pengadaan dan Pemasangan Pipa GI ND 150 mm per m'


1.0000 m' Pipa GI F 150 mm 470,200.00 470,200.00 470,200.00
0.1768 kg kawat las 20,600.00 3,642.08 3,642.08
0.8504 lt solar 10,600.00 9,014.24 9,014.24
0.1667 lot Mesin las 33,311.25 5,552.99 5,552.99
0.3333 lot Alat bantu 50,000.00 16,665.00 16,665.00
0.3333 Pekerja 41,800.00 13,931.94 13,931.94
0.1667 Tukang Las 55,000.00 9,168.50 9,168.50
0.1667 Tukang Pipa 55,000.00 9,168.50 9,168.50
0.0167 Kepala Tukang Pipa 60,500.00 1,010.35 1,010.35
0.0500 Mandor 57,200.00 2,860.00 2,860.00
0.1000 Biaya Overhead Pemasangan 36,139.29 3,613.93 3,613.93
39,753.22 505,074.31 544,827.52

Hitung.P.12 Pengadaan dan Pemasangan Pipa GI ND 200 mm per m'


1.0000 m' Pipa GI F 200 mm 890,800.00 890,800.00 890,800.00
0.1768 kg kawat las 20,600.00 3,642.08 3,642.08
0.8504 lt solar 10,600.00 9,014.24 9,014.24
0.1667 lot Mesin las 33,311.25 5,552.99 5,552.99
0.3333 lot Alat bantu 50,000.00 16,665.00 16,665.00
0.3333 Pekerja 41,800.00 13,931.94 13,931.94
0.1667 Tukang Las 55,000.00 9,168.50 9,168.50
0.1667 Tukang Pipa 55,000.00 9,168.50 9,168.50
0.0167 Kepala Tukang Pipa 60,500.00 1,010.35 1,010.35
0.0500 Mandor 57,200.00 2,860.00 2,860.00
0.1000 Biaya Overhead Pemasangan 36,139.29 3,613.93 3,613.93
39,753.22 925,674.31 965,427.52

Hitung.P.13 Pengadaan dan Pemasangan Pipa GI ND 250 mm per m'


1.0000 m' Pipa GI F 250 mm 1,116,500.00 1,116,500.00 1,116,500.00
0.2100 kg kawat las 20,600.00 4,324.97 4,324.97
1.0099 lt solar 10,600.00 10,704.41 10,704.41
0.1340 lot Mesin las 33,311.25 4,463.71 4,463.71
0.3160 lot Alat bantu 50,000.00 15,800.00 15,800.00
0.3160 Pekerja 41,800.00 13,208.80 13,208.80
0.1340 Tukang Las 55,000.00 7,370.00 7,370.00
0.1340 Tukang Pipa 55,000.00 7,370.00 7,370.00
0.0130 Kepala Tukang Pipa 60,500.00 786.50 786.50
0.0480 Mandor 57,200.00 2,745.60 2,745.60
0.1000 Biaya Overhead Pemasangan 31,480.90 3,148.09 3,148.09
34,628.99 1,151,793.09 1,186,422.08

Hitung.P.14 Pengadaan dan Pemasangan Pipa GI ND 300 mm per m'


1.0000 m' Pipa GI F 300 mm 1,228,000.00 1,228,000.00 1,228,000.00
0.2210 kg kawat las 20,600.00 4,552.60 4,552.60
1.0630 lt solar 10,600.00 11,267.80 11,267.80
0.0620 lot Mesin las 33,311.25 2,065.30 2,065.30
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.3160 lot Alat bantu 50,000.00 15,800.00 15,800.00
0.3333 Pekerja 41,800.00 13,931.94 13,931.94
0.1667 Tukang Las 55,000.00 9,168.50 9,168.50
0.1667 Tukang Pipa 55,000.00 9,168.50 9,168.50
0.0167 Kepala Tukang Pipa 60,500.00 1,010.35 1,010.35
0.0500 Mandor 57,200.00 2,860.00 2,860.00
0.1000 Biaya Overhead Pemasangan 36,139.29 3,613.93 3,613.93
39,753.22 1,261,685.70 1,301,438.92

Hitung.P.15 Pengadaan dan Pemasangan Pipa GI ND 400 mm per m'


1.0000 m' Pipa GI F 400 mm 1,581,000.00 1,581,000.00 1,581,000.00
0.2210 kg kawat las 20,600.00 4,552.60 4,552.60
1.0630 lt solar 10,600.00 11,267.80 11,267.80
0.0620 lot Mesin las 33,311.25 2,065.30 2,065.30
0.3160 lot Alat bantu 50,000.00 15,800.00 15,800.00
0.3333 Pekerja 41,800.00 13,931.94 13,931.94
0.1667 Tukang Las 55,000.00 9,168.50 9,168.50
0.1667 Tukang Pipa 55,000.00 9,168.50 9,168.50
0.0167 Kepala Tukang Pipa 60,500.00 1,010.35 1,010.35
0.0500 Mandor 57,200.00 2,860.00 2,860.00
0.1000 Biaya Overhead Pemasangan 36,139.29 3,613.93 3,613.93
39,753.22 1,614,685.70 1,654,438.92

II PENCUCIAN DAN PENGETESAN PIPA


Hitung.P.16 Pencucian Pipa ND 50 mm per m'
0.0039 m3 Air 12,500.00 49.06 49.06
0.0001 kg Kaporit 40,000.00 2.62 2.62
0.0025 lot alat bantu 50,000.00 125.00 125.00
0.0100 Pekerja 41,800.00 418.00 418.00
0.0100 Tukang Pipa 55,000.00 550.00 550.00
0.0050 Kepala Tukang Pipa 60,500.00 302.50 302.50
0.0050 Mandor 57,200.00 286.00 286.00
1,556.50 176.68 1,733.18

Hitung.P.17 Pencucian Pipa ND 75 mm per m'


0.0088 m3 Air 12,500.00 110.39 110.39
0.0001 kg Kaporit 40,000.00 5.89 5.89
0.0038 lot alat bantu 50,000.00 187.50 187.50
0.0125 Pekerja 41,800.00 522.50 522.50
0.0125 Tukang Pipa 55,000.00 687.50 687.50
0.0053 Kepala Tukang Pipa 60,500.00 317.63 317.63
0.0053 Mandor 57,200.00 300.30 300.30
1,827.93 303.78 2,131.70

Hitung.P.18 Pencucian Pipa ND 100 mm per m'


0.0157 m3 Air 12,500.00 196.25 196.25
0.0003 kg Kaporit 40,000.00 10.47 10.47
0.0050 lot alat bantu 50,000.00 250.00 250.00
0.0150 Pekerja 41,800.00 627.00 627.00
0.0150 Tukang Pipa 55,000.00 825.00 825.00
0.0055 Kepala Tukang Pipa 60,500.00 332.75 332.75
0.0055 Mandor 57,200.00 314.60 314.60
2,099.35 456.72 2,556.07

Hitung.P.19 Pencucian Pipa ND 150 mm per m'


0.0353 m3 Air 12,500.00 441.56 441.56
0.0006 kg Kaporit 40,000.00 23.55 23.55
0.0050 lot alat bantu 50,000.00 250.00 250.00
0.0150 Pekerja 41,800.00 627.00 627.00
0.0150 Tukang Pipa 55,000.00 825.00 825.00
0.0055 Kepala Tukang Pipa 60,500.00 332.75 332.75
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.0055 Mandor 57,200.00 314.60 314.60
2,099.35 715.11 2,814.46

Hitung.P.20 Pencucian Pipa ND 200 mm per m'


0.0628 m3 Air 12,500.00 785.00 785.00
0.0010 kg Kaporit 40,000.00 41.87 41.87
0.0050 lot alat bantu 50,000.00 250.00 250.00
0.0150 Pekerja 41,800.00 627.00 627.00
0.0150 Tukang Pipa 55,000.00 825.00 825.00
0.0055 Kepala Tukang Pipa 60,500.00 332.75 332.75
0.0055 Mandor 57,200.00 314.60 314.60
2,099.35 1,076.87 3,176.22
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Hitung.P.21 Pencucian Pipa ND 250 mm per m'
0.0981 m3 Air 12,500.00 1,226.56 1,226.56
0.0016 kg Kaporit 40,000.00 65.42 65.42
0.0125 lot alat bantu 50,000.00 625.00 625.00
0.0225 Pekerja 41,800.00 940.50 940.50
0.0225 Tukang Pipa 55,000.00 1,237.50 1,237.50
0.0068 Kepala Tukang Pipa 60,500.00 408.38 408.38
0.0068 Mandor 57,200.00 386.10 386.10
2,972.48 1,916.98 4,889.45

Hitung.P.22 Pencucian Pipa ND 300 mm per m'


0.1413 m3 Air 12,500.00 1,766.25 1,766.25
0.0024 kg Kaporit 40,000.00 94.20 94.20
0.0125 lot alat bantu 50,000.00 625.00 625.00
0.0400 Pekerja 41,800.00 1,672.00 1,672.00
0.0200 Tukang Pipa 55,000.00 1,100.00 1,100.00
0.0020 Kepala Tukang Pipa 60,500.00 121.00 121.00
0.0060 Mandor 57,200.00 343.20 343.20
3,236.20 2,485.45 5,721.65

Hitung.P.23 Pencucian Pipa ND 400 mm per m'


0.2512 m3 Air 12,500.00 3,140.00 3,140.00
0.0042 kg Kaporit 40,000.00 167.47 167.47
0.0125 lot alat bantu 50,000.00 625.00 625.00
0.0476 Pekerja 41,800.00 1,989.68 1,989.68
0.0238 Tukang Pipa 55,000.00 1,309.00 1,309.00
0.0024 Kepala Tukang Pipa 60,500.00 145.20 145.20
0.0071 Mandor 57,200.00 406.12 406.12
3,850.00 3,932.47 7,782.47

Hitung.P.24 Pengetesan Pipa ND 50 mm per m'


0.0024 m3 Air 12,500.00 29.44 29.44
0.0025 lot alat bantu 50,000.00 125.00 125.00
0.0100 Pekerja 41,800.00 104.50 104.50
0.0100 Tukang Pipa 55,000.00 550.00 550.00
0.0050 Kepala Tukang Pipa 60,500.00 605.00 605.00
0.0050 Mandor 57,200.00 286.00 286.00
1,545.50 154.44 1,699.94

Hitung.P.25 Pengetesan Pipa ND 75 mm per m'


0.0053 m3 Air 12,500.00 66.23 66.23
0.0038 lot alat bantu 50,000.00 187.50 187.50
0.0125 Pekerja 41,800.00 522.50 522.50
0.0125 Tukang Pipa 55,000.00 687.50 687.50
0.0053 Kepala Tukang Pipa 60,500.00 317.63 317.63
0.0053 Mandor 57,200.00 300.30 300.30
1,827.93 253.73 2,081.66

Hitung.P26 Pengetesan Pipa ND 100 mm per m'


0.0094 m3 Air 12,500.00 117.75 117.75
0.0050 lot alat bantu 50,000.00 250.00 250.00
0.0150 Pekerja 41,800.00 627.00 627.00
0.0150 Tukang Pipa 55,000.00 825.00 825.00
0.0055 Kepala Tukang Pipa 60,500.00 332.75 332.75
0.0055 Mandor 57,200.00 314.60 314.60
2,099.35 367.75 2,467.10

Hitung.P.27 Pengetesan Pipa ND 150 mm per m'


0.0212 m3 Air 12,500.00 264.94 264.94
0.0050 lot alat bantu 50,000.00 250.00 250.00
0.0150 Pekerja 41,800.00 627.00 627.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.0150 Tukang Pipa 55,000.00 825.00 825.00
0.0055 Kepala Tukang Pipa 60,500.00 332.75 332.75
0.0055 Mandor 57,200.00 314.60 314.60
2,099.35 514.94 2,614.29

Hitung.P.28 Pengetesan Pipa ND 200 mm per m'


0.0377 m3 Air 12,500.00 471.00 471.00
0.0050 lot alat bantu 50,000.00 250.00 250.00
0.0188 Pekerja 41,800.00 783.75 783.75
0.0188 Tukang Pipa 55,000.00 1,031.25 1,031.25
0.0061 Kepala Tukang Pipa 60,500.00 370.56 370.56
0.0061 Mandor 57,200.00 350.35 350.35
2,535.91 721.00 3,256.91

Hitung.P.29 Pengetesan Pipa ND 250 mm per m'


0.0589 m3 Air 12,500.00 735.94 735.94
0.0125 lot alat bantu 50,000.00 625.00 625.00
0.0225 Pekerja 41,800.00 940.50 940.50
0.0225 Tukang Pipa 55,000.00 1,237.50 1,237.50
0.0068 Kepala Tukang Pipa 60,500.00 408.38 408.38
0.0068 Mandor 57,200.00 386.10 386.10
2,972.48 1,360.94 4,333.41

Hitung.P.30 Pengetesan Pipa ND 300 mm per m'


0.0848 m3 Air 12,500.00 1,059.75 1,059.75
0.0125 lot alat bantu 50,000.00 625.00 625.00
0.0263 Pekerja 41,800.00 1,097.25 1,097.25
0.0263 Tukang Pipa 55,000.00 1,443.75 1,443.75
0.0074 Kepala Tukang Pipa 60,500.00 446.19 446.19
0.0074 Mandor 57,200.00 421.85 421.85
3,409.04 1,684.75 5,093.79

Hitung.P.31 Pengetesan Pipa ND 400 mm per m'


0.1507 m3 Air 12,500.00 1,884.00 1,884.00
0.0125 lot alat bantu 50,000.00 625.00 625.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.0300 Tukang Pipa 55,000.00 1,650.00 1,650.00
0.0080 Kepala Tukang Pipa 60,500.00 484.00 484.00
0.0080 Mandor 57,200.00 457.60 457.60
3,845.60 2,509.00 6,354.60

IV PENGADAAN DAN PEMASANGAN BEND (termasuk mur baut dan packing)


CI
Taksir Bend All Flange CI F 75 mm x 90 O
1.0000 bh Bend All Flange CI F 75 mm x 90O 260,000.00 260,000.00 260,000.00
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
0.1000 Biaya Overhead Pemasangan 8,751.60 875.16 875.16
8,751.60 264,000.00 272,751.60
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Taksir Bend All Flange CI F 100 mm x 90 O
1.0000 bh Bend All Flange CI F 100 mm x 90O 332,000.00 332,000.00 332,000.00
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
0.1000 Biaya Overhead Pemasangan 8,751.60 875.16 875.16
8,751.60 336,000.00 344,751.60

Taksir Bend All Flange CI F 250 mm x 90 O


1.0000 bh Bend AF F 250 mm x 90O 588,500.00 588,500.00 588,500.00
0.1200 lot Alat bantu 50,000.00 6,000.00 6,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0150 Mandor 57,200.00 858.00 858.00
0.1000 Biaya Overhead Pemasangan 15,576.00 1,557.60 1,557.60
15,576.00 594,500.00 610,076.00

Taksir Bend All Flange CI F 300 mm x 90 O


1.0000 bh Bend AF F 300 mm x 90O 1,938,475.00 1,938,475.00 1,938,475.00
0.1200 lot Alat bantu 50,000.00 6,000.00 6,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0150 Mandor 57,200.00 858.00 858.00
0.1000 Biaya Overhead Pemasangan 15,576.00 1,557.60 1,557.60
15,576.00 1,944,475.00 1,960,051.00

Taksir Bend All Flange CI F 100 mm x 45 O


1.0000 bh Bend AF F 100 mm x 45O 332,000.00 332,000.00 332,000.00
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
0.1000 Biaya Overhead Pemasangan 8,751.60 875.16 875.16
8,751.60 336,000.00 344,751.60

Taksir Bend All Flange CI F 150 mm x 45 O


1.0000 bh Bend AF F 150 mm x 45O 538,890.00 538,890.00 538,890.00
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
0.1000 Biaya Overhead Pemasangan 8,751.60 875.16 875.16
8,751.60 542,890.00 551,641.60

Taksir Bend All Flange CI F 200 mm x 45 O


1.0000 bh Bend AF F 200 mm x 45O 590,881.50 590,881.50 590,881.50
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
0.1000 Biaya Overhead Pemasangan 8,751.60 875.16 875.16
8,751.60 594,881.50 603,633.10

Taksir Bend All Flange CI F 250 mm x 45 O


NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
1.0000 bh Bend AF F 250 mm x 45O 566,500.00 566,500.00 566,500.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
0.1000 Biaya Overhead Pemasangan 23,894.20 2,389.42 2,389.42
23,894.20 576,500.00 600,394.20

Taksir Bend All Flange CI F 300 mm x 45 O


1.0000 bh Bend AF F 300 mm x 45O 4,424,266.00 4,424,266.00 4,424,266.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
0.1000 Biaya Overhead Pemasangan 23,894.20 2,389.42 2,389.42
23,894.20 4,434,266.00 4,458,160.20

PVC
Taksir Bend PVC F 75 mm x 90O
1.0000 bh Bend PVC F 75 mm x 90O 124,894.00 124,894.00 124,894.00
0.0200 lot Alat bantu 50,000.00 1,000.00 1,000.00
0.0200 Pekerja 41,800.00 836.00 836.00
0.1000 Tukang Pipa 55,000.00 5,500.00 5,500.00
0.0100 Kepala Tukang Pipa 60,500.00 605.00 605.00
0.0020 Mandor 57,200.00 114.40 114.40
7,055.40 125,894.00 132,949.40

Taksir Bend PVC F 100 mm x 90O


1.0000 bh Bend PVC F 100 mm x 90O 316,393.00 316,393.00 316,393.00
0.0300 lot Alat bantu 50,000.00 1,500.00 1,500.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
8,751.60 317,893.00 326,644.60

Taksir Bend PVC F 150 mm x 90O


1.0000 bh Bend PVC F 150 mm x 90O 636,559.00 636,559.00 636,559.00
1.8132 lot Alat bantu 50,000.00 90,660.00 90,660.00
1.8132 Pekerja 41,800.00 75,791.76 75,791.76
0.9041 Tukang Pipa 55,000.00 49,725.50 49,725.50
0.0859 Kepala Tukang Pipa 60,500.00 5,196.95 5,196.95
0.2677 Mandor 57,200.00 15,312.44 15,312.44
146,026.65 727,219.00 873,245.65

Taksir Bend PVC F 200 mm x 90O


1.0000 bh Bend PVC F 200 mm x 90O 1,109,823.00 1,109,823.00 1,109,823.00
1.8132 lot Alat bantu 50,000.00 90,660.00 90,660.00
1.8132 Pekerja 41,800.00 75,791.76 75,791.76
0.9041 Tukang Pipa 55,000.00 49,725.50 49,725.50
0.0859 Kepala Tukang Pipa 60,500.00 5,196.95 5,196.95
0.2677 Mandor 57,200.00 15,312.44 15,312.44
146,026.65 1,200,483.00 1,346,509.65
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Taksir Bend PVC F 250 mm x 90O
1.0000 bh Bend PVC F 250 mm x 90O 1,918,433.00 1,918,433.00 1,918,433.00
0.0600 lot Alat bantu 50,000.00 3,000.00 3,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0150 Mandor 57,200.00 858.00 858.00
15,576.00 1,921,433.00 1,937,009.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6

Taksir Bend PVC F 300 mm x 90O


1.0000 bh Bend PVC F 300 mm x 90O 3,182,938.00 3,182,938.00 3,182,938.00
0.0600 lot Alat bantu 50,000.00 3,000.00 3,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0150 Mandor 57,200.00 858.00 858.00
15,576.00 3,185,938.00 3,201,514.00

Taksir Bend PVC F 400 mm x 90O


1.0000 bh Bend PVC F 400 mm x 90O ### ### 14,353,273.00
0.0600 lot Alat bantu 50,000.00 3,000.00 3,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0150 Mandor 57,200.00 858.00 858.00
15,576.00 ### 14,371,849.00

Taksir Bend PVC F 100 mm x 45O


1.0000 bh Bend PVC F 100 mm x 45O 289,124.00 289,124.00 289,124.00
0.0300 lot Alat bantu 50,000.00 1,500.00 1,500.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
8,751.60 290,624.00 299,375.60

Taksir Bend PVC F 150 mm x 45O


1.0000 bh Bend PVC F 150 mm x 45O 538,890.00 538,890.00 538,890.00
0.0300 lot Alat bantu 50,000.00 1,500.00 1,500.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
8,751.60 540,390.00 549,141.60

Taksir Bend PVC F 200 mm x 45O


1.0000 bh Bend PVC F 200 mm x 45O 656,535.00 656,535.00 656,535.00
0.0300 lot Alat bantu 50,000.00 1,500.00 1,500.00
0.0300 Pekerja 41,800.00 1,254.00 1,254.00
0.1200 Tukang Pipa 55,000.00 6,600.00 6,600.00
0.0120 Kepala Tukang Pipa 60,500.00 726.00 726.00
0.0030 Mandor 57,200.00 171.60 171.60
8,751.60 658,035.00 666,786.60

Taksir Bend PVC F 250 mm x 45O


1.0000 bh Bend PVC F 250 mm x 45O 566,500.00 566,500.00 566,500.00
0.0600 lot Alat bantu 50,000.00 3,000.00 3,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
0.0150 Mandor 57,200.00 858.00 858.00
15,576.00 569,500.00 585,076.00

Taksir Bend PVC F 300 mm x 45O


1.0000 bh Bend PVC F 300 mm x 45O 1,408,990.00 1,408,990.00 1,408,990.00
0.0600 lot Alat bantu 50,000.00 3,000.00 3,000.00
0.0600 Pekerja 41,800.00 2,508.00 2,508.00
0.2000 Tukang Pipa 55,000.00 11,000.00 11,000.00
0.0200 Kepala Tukang Pipa 60,500.00 1,210.00 1,210.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.0150 Mandor 57,200.00 858.00 858.00
15,576.00 1,411,990.00 1,427,566.00

Taksir Bend PVC F 100 mm x 22.5O


1.0000 bh Bend PVC F 100 mm x 22.5O 267,564.00 267,564.00 267,564.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 272,664.00 296,558.20

Taksir Bend PVC F 250 mm x 22.5O


1.0000 bh Bend PVC F 250 mm x 22.5O 1,504,701.00 1,504,701.00 1,504,701.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 1,509,801.00 1,533,695.20

Taksir Bend PVC F 100 mm x 11.25O


1.0000 bh Bend PVC F 100 mm x 11.25O 251,768.00 251,768.00 251,768.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 256,868.00 280,762.20

Taksir Bend PVC F 75 mm x 11.25O


1.0000 bh Bend PVC F 75 mm x 11.25O 95,865.00 95,865.00 95,865.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 100,965.00 124,859.20

Taksir Bend PVC F 150 mm x 11.25O


1.0000 bh Bend PVC F 150 mm x 11.25O 469,535.00 469,535.00 469,535.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 474,635.00 498,529.20

Taksir Bend PVC F 200 mm x 11.25O


1.0000 bh Bend PVC F 200 mm x 11.25O 769,219.00 769,219.00 769,219.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 774,319.00 798,213.20

Taksir Bend PVC F 250 mm x 11.25O


1.0000 bh Bend PVC F 250 mm x 11.25O 1,327,359.00 1,327,359.00 1,327,359.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 1,332,459.00 1,356,353.20

Taksir Bend PVC F 300 mm x 11.25O


1.0000 bh Bend PVC F 300 mm x 11.25O 2,103,475.00 2,103,475.00 2,103,475.00
0.1020 lot Alat bantu 50,000.00 5,100.00 5,100.00
0.1020 Pekerja 41,800.00 4,263.60 4,263.60
0.3000 Tukang Pipa 55,000.00 16,500.00 16,500.00
0.0300 Kepala Tukang Pipa 60,500.00 1,815.00 1,815.00
0.0230 Mandor 57,200.00 1,315.60 1,315.60
23,894.20 2,108,575.00 2,132,469.20
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
V PENGADAAN DAN PEMASANGAN VALVE

Taksir Gate Valve All Flange F 100 mm


1.0000 bh Gate Valve All Flange F 100 mm 1,210,000.00 1,210,000.00 1,210,000.00
0.2880 lot Alat bantu 50,000.00 14,400.00 14,400.00
0.2880 Pekerja 41,800.00 12,038.40 12,038.40
0.1440 Tukang Pipa 55,000.00 7,920.00 7,920.00
0.0144 Kepala Tukang Pipa 60,500.00 871.20 871.20
0.0144 Mandor 57,200.00 823.68 823.68
0.1000 Biaya Overhead Pemasangan 21,653.28 2,165.33 2,165.33
23,818.61 1,224,400.00 1,248,218.61

Taksir Gate Valve All Flange F 250 mm


1.0000 bh Gate Valve All Flange F 250 mm 5,225,000.00 5,225,000.00 5,225,000.00
0.4977 lot Alat bantu 50,000.00 24,885.00 24,885.00
0.4977 Pekerja 41,800.00 20,803.86 20,803.86
0.2489 Tukang Pipa 55,000.00 13,686.75 13,686.75
0.0249 Kepala Tukang Pipa 60,500.00 1,505.54 1,505.54
0.0249 Mandor 57,200.00 1,423.42 1,423.42
0.1000 Biaya Overhead Pemasangan 37,419.57 3,741.96 3,741.96
41,161.53 5,249,885.00 5,291,046.53

Taksir Gate Valve All Flange F 300 mm


1.0000 bh Gate Valve All Flange F 300 mm 7,601,418.00 7,601,418.00 7,601,418.00
0.4977 lot Alat bantu 50,000.00 24,885.00 24,885.00
0.4977 Pekerja 41,800.00 20,803.86 20,803.86
0.2489 Tukang Pipa 55,000.00 13,686.75 13,686.75
0.0249 Kepala Tukang Pipa 60,500.00 1,505.54 1,505.54
0.0249 Mandor 57,200.00 1,423.42 1,423.42
0.1000 Biaya Overhead Pemasangan 37,419.57 3,741.96 3,741.96
41,161.53 7,626,303.00 7,667,464.53

VI PENGADAAN DAN PEMASANGAN WATER METER

Taksir Water Meter All Flange F 100 mm


1.0000 bh Water Meter All Flange F 100 mm 2,860,000.00 2,860,000.00 2,860,000.00
0.2880 lot Alat bantu 50,000.00 14,400.00 14,400.00
0.2880 Pekerja 41,800.00 12,038.40 12,038.40
0.1440 Tukang Pipa 55,000.00 7,920.00 7,920.00
0.0144 Kepala Tukang Pipa 60,500.00 871.20 871.20
0.0144 Mandor 57,200.00 823.68 823.68
0.1000 Biaya Overhead Pemasangan 21,653.28 2,165.33 2,165.33
23,818.61 2,874,400.00 2,898,218.61

Taksir Water Meter All Flange F 250 mm


1.0000 bh Water Meter All Flange F 250 mm ### ### 12,100,000.00
0.4977 lot Alat bantu 50,000.00 24,885.00 24,885.00
0.4977 Pekerja 41,800.00 20,803.86 20,803.86
0.2489 Tukang Pipa 55,000.00 13,686.75 13,686.75
0.0249 Kepala Tukang Pipa 60,500.00 1,505.54 1,505.54
0.0249 Mandor 57,200.00 1,423.42 1,423.42
0.1000 Biaya Overhead Pemasangan 37,419.57 3,741.96 3,741.96
41,161.53 ### 12,166,046.53

VIII PENGADAAN DAN PEMASANGAN FLANGE


Taksir Las Flange F 100 mm
1.0000 bh Las Flange F 100 mm 88,000.00 88,000.00 88,000.00
1.7100 kg kawat las 20,600.00 35,226.00 35,226.00
0.6601 lt solar 10,600.00 6,997.06 6,997.06
0.2220 lot Mesin las 33,311.25 7,395.10 7,395.10
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.4450 Pekerja 41,800.00 18,601.00 18,601.00
0.2220 Tukang Las 55,000.00 12,210.00 12,210.00
0.2220 Tukang Pipa 55,000.00 12,210.00 12,210.00
0.0220 Kepala Tukang Pipa 60,500.00 1,331.00 1,331.00
0.0670 Mandor 57,200.00 3,832.40 3,832.40
0.1000 Biaya Overhead Pemasangan 48,184.40 4,818.44 4,818.44
53,002.84 141,618.16 194,621.00

Taksir Las Flange F 150 mm


1.0000 bh Las Flange F 150 mm 184,360.00 184,360.00 184,360.00
1.7100 kg kawat las 20,600.00 35,226.00 35,226.00
0.6601 lt solar 10,600.00 6,997.06 6,997.06
0.2220 lot Mesin las 33,311.25 7,395.10 7,395.10
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.4450 Pekerja 41,800.00 18,601.00 18,601.00
0.2220 Tukang Las 55,000.00 12,210.00 12,210.00
0.2220 Tukang Pipa 55,000.00 12,210.00 12,210.00
0.0220 Kepala Tukang Pipa 60,500.00 1,331.00 1,331.00
0.0670 Mandor 57,200.00 3,832.40 3,832.40
0.1000 Biaya Overhead Pemasangan 48,184.40 4,818.44 4,818.44
53,002.84 237,978.16 290,981.00

Taksir Las Flange F 200 mm


1.0000 bh Las Flange F 200 mm 225,940.00 225,940.00 225,940.00
1.7100 kg kawat las 20,600.00 35,226.00 35,226.00
0.6601 lt solar 10,600.00 6,997.06 6,997.06
0.2220 lot Mesin las 33,311.25 7,395.10 7,395.10
0.0800 lot Alat bantu 50,000.00 4,000.00 4,000.00
0.4450 Pekerja 41,800.00 18,601.00 18,601.00
0.2220 Tukang Las 55,000.00 12,210.00 12,210.00
0.2220 Tukang Pipa 55,000.00 12,210.00 12,210.00
0.0220 Kepala Tukang Pipa 60,500.00 1,331.00 1,331.00
0.0670 Mandor 57,200.00 3,832.40 3,832.40
0.1000 Biaya Overhead Pemasangan 48,184.40 4,818.44 4,818.44
53,002.84 279,558.16 332,561.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Taksir Las Flange F 250 mm
1.0000 bh Las Flange F 250 mm 364,100.00 364,100.00 364,100.00
4.1000 kg kawat las 20,600.00 84,460.00 84,460.00
1.9601 lt solar 10,600.00 20,777.06 20,777.06
0.2520 lot Mesin las 33,311.25 8,394.44 8,394.44
0.9500 lot Alat bantu 50,000.00 47,500.00 47,500.00
0.5050 Pekerja 41,800.00 21,109.00 21,109.00
0.2520 Tukang Las 55,000.00 13,860.00 13,860.00
0.2520 Tukang Pipa 55,000.00 13,860.00 13,860.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0750 Mandor 57,200.00 4,290.00 4,290.00
0.1000 Biaya Overhead Pemasangan 54,631.50 5,463.15 5,463.15
60,094.65 525,231.50 585,326.15

Taksir Las Flange F 300 mm


1.0000 bh Las Flange F 300 mm 399,630.00 399,630.00 399,630.00
4.1000 kg kawat las 20,600.00 84,460.00 84,460.00
1.9601 lt solar 10,600.00 20,777.06 20,777.06
0.2520 lot Mesin las 33,311.25 8,394.44 8,394.44
0.9500 lot Alat bantu 50,000.00 47,500.00 47,500.00
0.5050 Pekerja 41,800.00 21,109.00 21,109.00
0.2520 Tukang Las 55,000.00 13,860.00 13,860.00
0.2520 Tukang Pipa 55,000.00 13,860.00 13,860.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0750 Mandor 57,200.00 4,290.00 4,290.00
0.1000 Biaya Overhead Pemasangan 54,631.50 5,463.15 5,463.15
60,094.65 560,761.50 620,856.15

IX PENGADAAN DAN PEMASANGAN TEE DAN REDUSER


GI DAN PVC
Taksir Tee All Flange CI F 100 x 75 mm
1.0000 bh Tee All Flange CI F 100 x 75 mm 433,620.00 433,620.00 433,620.00
0.1000 lot Alat bantu 50,000.00 5,000.00 5,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 438,620.00 461,313.55

Taksir Tee All Flange CI F 250 x 100 mm


1.0000 bh Tee All Flange CI F 250 x 100 mm 1,395,350.00 1,395,350.00 1,395,350.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,405,350.00 1,428,043.55

Taksir Tee All Flange CI F 300 x 200 mm


1.0000 bh Tee All Flange CI F 300 x 200 mm 1,860,430.00 1,860,430.00 1,860,430.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,870,430.00 1,893,123.55

Taksir Tee all socket. PVC RRJ SNI DN 400 x 300 mm


NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
1.0000 bh Tee all socket. PVC RRJ SNI DN 400 x 300 mm 7,215,450.00 7,215,450.00 7,215,450.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 7,225,450.00 7,248,143.55

Taksir Tee all socket. PVC RRJ SNI DN 300 x 100 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 300 x 100 mm 3,112,230.00 3,112,230.00 3,112,230.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 3,122,230.00 3,144,923.55

Taksir Tee all socket. PVC RRJ SNI DN 200 x 150 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 200 x 150 mm 1,678,600.00 1,678,600.00 1,678,600.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,688,600.00 1,711,293.55

Taksir Tee all socket. PVC RRJ SNI DN 200 x 100 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 200 x 100 mm 1,390,950.00 1,390,950.00 1,390,950.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,400,950.00 1,423,643.55

Taksir Tee all socket. PVC RRJ SNI DN 100 x 100 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 100 x 100 mm 436,194.00 436,194.00 436,194.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 446,194.00 468,887.55

Taksir Tee all socket. PVC RRJ SNI DN 200 x 75 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 200 x 75 mm 1,443,695.00 1,443,695.00 1,443,695.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,453,695.00 1,476,388.55

Taksir Tee all socket. PVC RRJ SNI DN 100 x 75 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 100 x 75 mm 483,087.00 483,087.00 483,087.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 493,087.00 515,780.55

Taksir Tee all socket. PVC RRJ SNI DN 150 x 150 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 150 x 150 mm 810,326.00 810,326.00 810,326.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 820,326.00 843,019.55

Taksir Tee all socket. PVC RRJ SNI DN 150 x 100 mm


1.0000 bh Tee all socket. PVC RRJ SNI DN 150 x 100 mm 703,043.00 703,043.00 703,043.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 713,043.00 735,736.55

Taksir Reducer PVC SNI DN 400 x 100 mm


1.0000 bh Reducer PVC SNI DN 400 x 100 mm 1,732,500.00 1,732,500.00 1,732,500.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,742,500.00 1,765,193.55

Taksir Reducer PVC SNI DN 200 x 150 mm


1.0000 bh Reducer PVC SNI DN 200 x 150 mm 730,257.00 730,257.00 730,257.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 740,257.00 762,950.55

Taksir Reducer PVC SNI DN 200 x 100 mm


1.0000 bh Reducer PVC SNI DN 200 x 100 mm 1,056,000.00 1,056,000.00 1,056,000.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 1,066,000.00 1,088,693.55

Taksir Reducer PVC SNI DN 150 x 100 mm


1.0000 bh Reducer PVC SNI DN 150 x 100 mm 401,027.00 401,027.00 401,027.00
0.2000 lot Alat bantu 50,000.00 10,000.00 10,000.00
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.2500 Tukang Pipa 55,000.00 13,750.00 13,750.00
0.0250 Kepala Tukang Pipa 60,500.00 1,512.50 1,512.50
0.0025 Mandor 57,200.00 143.00 143.00
0.1000 Biaya Overhead Pemasangan 20,630.50 2,063.05 2,063.05
22,693.55 411,027.00 433,720.55

X PENGADAAN DAN PEMASANGAN ACCESSORIES LAIN


Taksir Flange Socket PVC F 100 mm
1.0000 bh Flange Socket PVC F 100 mm 520,850.00 520,850.00 520,850.00
0.3500 lot Alat bantu 50,000.00 17,500.00 17,500.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.3500 Tukang Pipa 55,000.00 19,250.00 19,250.00
0.0350 Kepala Tukang Pipa 60,500.00 2,117.50 2,117.50
0.0040 Mandor 57,200.00 228.80 228.80
0.1000 Biaya Overhead Pemasangan 26,821.30 2,682.13 2,682.13
29,503.43 538,350.00 567,853.43

Taksir Flange Socket PVC F 250 mm


1.0000 bh Flange Socket PVC F 250 mm 1,998,425.00 1,998,425.00 1,998,425.00
0.3500 lot Alat bantu 50,000.00 17,500.00 17,500.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.3500 Tukang Pipa 55,000.00 19,250.00 19,250.00
0.0350 Kepala Tukang Pipa 60,500.00 2,117.50 2,117.50
0.0040 Mandor 57,200.00 228.80 228.80
0.1000 Biaya Overhead Pemasangan 26,821.30 2,682.13 2,682.13
29,503.43 2,015,925.00 2,045,428.43
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Taksir Flange Socket CI F 100 mm
1.0000 bh Flange Socket CI F 100 mm 608,160.00 608,160.00 608,160.00
0.3500 lot Alat bantu 50,000.00 17,500.00 17,500.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.3500 Tukang Pipa 55,000.00 19,250.00 19,250.00
0.0350 Kepala Tukang Pipa 60,500.00 2,117.50 2,117.50
0.0040 Mandor 57,200.00 228.80 228.80
0.1000 Biaya Overhead Pemasangan 26,821.30 2,682.13 2,682.13
29,503.43 625,660.00 655,163.43

Taksir Flange Socket CI F 250 mm


1.0000 bh Flange Socket CI F 250 mm 3,407,860.00 3,407,860.00 3,407,860.00
0.3500 lot Alat bantu 50,000.00 17,500.00 17,500.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.3500 Tukang Pipa 55,000.00 19,250.00 19,250.00
0.0350 Kepala Tukang Pipa 60,500.00 2,117.50 2,117.50
0.0040 Mandor 57,200.00 228.80 228.80
0.1000 Biaya Overhead Pemasangan 26,821.30 2,682.13 2,682.13
29,503.43 3,425,360.00 3,454,863.43

Taksir Flange Spigot CI F 300 mm


1.0000 bh Flange Spigot CI F 250 mm 4,147,000.00 4,147,000.00 4,147,000.00
0.3500 lot Alat bantu 50,000.00 17,500.00 17,500.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.3500 Tukang Pipa 55,000.00 19,250.00 19,250.00
0.0350 Kepala Tukang Pipa 60,500.00 2,117.50 2,117.50
0.0040 Mandor 57,200.00 228.80 228.80
0.1000 Biaya Overhead Pemasangan 26,821.30 2,682.13 2,682.13
29,503.43 4,164,500.00 4,194,003.43

Taksir Flange Spigot CI F 100 mm


1.0000 bh Flange Spigot CI F 250 mm 563,728.00 563,728.00 563,728.00
0.3500 lot Alat bantu 50,000.00 17,500.00 17,500.00
0.1250 Pekerja 41,800.00 5,225.00 5,225.00
0.3500 Tukang Pipa 55,000.00 19,250.00 19,250.00
0.0350 Kepala Tukang Pipa 60,500.00 2,117.50 2,117.50
0.0040 Mandor 57,200.00 228.80 228.80
0.1000 Biaya Overhead Pemasangan 26,821.30 2,682.13 2,682.13
29,503.43 581,228.00 610,731.43

Taksir Dop PVC F 100 mm


1.0000 bh Dop PVC F 100 mm 56,628.00 56,628.00 56,628.00
0.0325 lot Alat bantu 50,000.00 1,625.00 1,625.00
0.0800 Pekerja 41,800.00 3,344.00 3,344.00
0.0165 Mandor 57,200.00 943.80 943.80
4,287.80 58,253.00 62,540.80

Taksir Dop PVC F 200 mm


1.0000 bh Dop PVC F 200 mm 335,742.00 335,742.00 335,742.00
0.0325 lot Alat bantu 50,000.00 1,625.00 1,625.00
0.0800 Pekerja 41,800.00 3,344.00 3,344.00
0.0165 Mandor 57,200.00 943.80 943.80
4,287.80 337,367.00 341,654.80

Taksir Dop PVC F 250 mm


1.0000 bh Dop PVC F 250 mm 634,007.00 634,007.00 634,007.00
0.0325 lot Alat bantu 50,000.00 1,625.00 1,625.00
0.0800 Pekerja 41,800.00 3,344.00 3,344.00
0.0165 Mandor 57,200.00 943.80 943.80
4,287.80 635,632.00 639,919.80
NO. HARGA UPAH HARGA JUMLAH
KODE JENIS PEKERJAAN SATUAN KERJA BAHAN
ANALISA Rp Rp Rp Rp
1 2 3 4 5 6
Taksir Air Valve Ø 25 mm
1.0000 bh Air Valve Ø 25 mm 330,000.00 330,000.00 330,000.00
0.3000 lot Alat bantu 50,000.00 15,000.00 15,000.00
0.3000 Pekerja 41,800.00 12,540.00 12,540.00
0.1500 Tukang Pipa 55,000.00 8,250.00 8,250.00
0.0150 Kepala Tukang Pipa 60,500.00 907.50 907.50
0.0150 Mandor 57,200.00 858.00 858.00
0.1000 Biaya Overhead Pemasangan 22,555.50 2,255.55 2,255.55
22,555.50 345,000.00 369,811.05

Taksir Thrust Block K-225 -ND 100 mm


0.0640 m3 Beton K-225 908,071.21 58,116.56 58,116.56
0.3840 Pekerja 41,800.00 16,051.20 16,051.20
0.0640 Tukang batu 55,000.00 3,520.00 3,520.00
0.0064 Kepala Tukang batu 60,500.00 387.20 387.20
0.0192 Mandor 57,200.00 1,098.24 1,098.24
21,056.64 58,116.56 79,173.20

Taksir Thrust Block K-225 -ND 250 mm


0.1250 m3 Beton K-225 908,071.21 113,508.90 113,508.90
0.7500 Pekerja 41,800.00 31,350.00 31,350.00
0.1250 Tukang batu 55,000.00 6,875.00 6,875.00
0.0125 Kepala Tukang batu 60,500.00 756.25 756.25
0.0375 Mandor 57,200.00 2,145.00 2,145.00
41,126.25 113,508.90 154,635.15
HARGA SATUAN PEKERJAAN

LOKASI : KABUPATEN SUKOHARJO


TAHUN : 2013

HARGA SATUAN
NO JENIS PEKERJAAN SATUAN
( Rp )
1 3 4 5
1 Menggali 1 m3 tanah biasa sedalam 1 meter m3 32,780.00
2 Menggali 1 m3 tanah biasa sedalam 2 meter m3 40,194.00
3 Menggali 1 m3 tanah keras sedalam 1 meter m3 43,630.40
4 Menggali 1 m3 tanah cadas sedalam 1 meter m3 66,132.00
5 Mengurug kembali 1 m3 galian m3 1/3 x nilai pek Galian
6 Memadatkan 1 m3 tanah (per 20 cm) m3 23,760.00
7 Mengurug 1 m3 pasir urug m3 148,832.00
8 Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan m3 137,880.00
9 Mengurug 1 m3 dengan tanah urug padat bahan didatangkan m3 115,260.00
10 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP m3 869,695.00
11 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP m3 820,710.00
12 Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP m3 786,768.00
13 Memasang 1 m3 batu kosong (aanstamping) m3 535,243.50
14 1 m2 Plesteran 1 pc : 3 Pp, tebal 15 mm m2 31,663.62
15 1 m2 Plesteran 1 pc : 4 Pp, tebal 15 mm m2 29,686.30
16 1 m² Finishing Siar pas. Batu Kali Adukan, 1 Pc : 2 Pp m2 32,154.80
17 1 m² acian m2 17,285.10
18 Membuat 1m3 Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 728,325.68
19 Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K 125), Slump (12 ± 2) cm, w/c = 0,78 m3 802,479.36
20 Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K 150), Slump (12 ± 2) cm, w/c = 0,72 m3 828,113.77
21 Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, w/c = 0,66 m3 857,948.54
22 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, w/c = 0,61 m3 887,268.51
23 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, w/c = 0,58 m3 908,071.21
24 Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, w/c = 0,56 m3 923,387.36
25 Membuat 1 m3 beton mutu f'c = 24,0 Mpa (K 275), Slump (12 ± 2) cm, w/c = 0,53 m3 949,872.10
26 Membuat 1 m3 beton mutu f'c = 26,4 Mpa (K 300), Slump (12 ± 2) cm, w/c = 0,52 m3 958,073.69
27 Membuat 1 m3 Beton K-175 readymix m3 1,138,429.16
28 Membuat 1 m3 Beton K-350 readymix m3 1,418,068.02
29 Membuat 1 m3 Beton K-500 readymix m3 1,617,345.74
30 Pembongkaran 1 m3 Beton (dengan alat) m3 304,324.70
31 Pembongkaran 1 m3 Pasangan batu (dengan alat) m3 177,153.86
32 Pembongkaran 1 m3 jalan aspal (manual) m3 251,177.56
33 Pembesian 10 kg dengan besi polos 10 kg 199,878.30
29.a Pembesian 1 kg dengan besi polos kg 19,987.83
34 Pembesian 1 kg dengan besi ulir kg 22,087.83
35 Memasang 1 m2 bekisting untuk lantai m2 176,713.60
36 Memasang 1 m2 bekisting untuk dinding m2 165,033.60
37 Memasang 1 m2 bekisting untuk pondasi m2 98,366.20
38 Memasang 1 kg besi profil kg 27,488.60
39 Memasang 1 kg Rangka Baja IWF kg 26,628.60
40 Perakitan (Erection) 1 kg kuda- kuda baja kg 1,252.90
41 Memasang 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm (plesteran beton) m2 38,452.38
42 Memasang 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm m2 31,663.62
43 Memasang 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm m2 29,686.30
44 Memasang 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm m2 28,493.58
45 Memasang 1 m2 plesteran skoning 1 PC : 2 PP, lebar 10 mm m' 30,569.60
46 Memasang 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP m2 32,154.80
47 Memasang 1 m3 Lapis Pondasi Agregat Kelas B (manual) m3 329,143.52
48 Pengadaan dan Pemancangan Kayu Ulin m' #REF!
49 Pemancangan Kayu Ulin m' 19,935.71

15
HARGA SATUAN
NO JENIS PEKERJAAN SATUAN
( Rp )
1 3 4 5
PEKERJAAN PERPIPAAN
I PENGADAAN DAN PEMASANGAN PIPA
1 Pengadaan dan Pemasangan Pipa PVC ND 50 mm (SCJ), S-10 (PN 10) per m' m' 27,901.00
2 Pengadaan dan Pemasangan Pipa PVC ND 75 mm (RRJ), (S-10 - 12,5 bar) per m' m' 61,893.25
3 Pengadaan dan Pemasangan Pipa PVC ND 100 mm (RRJ), (S-10 - 12,5 bar) per m' m' 139,136.40
4 Pengadaan dan Pemasangan Pipa PVC ND 150 mm (RRJ), (S-10 - 12,5 bar) per m' m' 276,503.90
5 Pengadaan dan Pemasangan Pipa PVC ND 200 mm (RRJ), (S-10 - 12,5 bar) per m' m' 440,128.40
6 Pengadaan dan Pemasangan Pipa PVC ND 250 mm (RRJ), (S-10 - 12,5 bar) per m' m' 671,600.90
7 Pengadaan dan Pemasangan Pipa PVC ND 300 mm (RRJ), (S-10 - 12,5 bar) per m' m' 1,049,819.40
8 Pengadaan dan Pemasangan Pipa PVC ND 400 mm (RRJ), (S-10 - 12,5 bar) per m' m' 1,704,924.40
9 Pengadaan dan Pemasangan Pipa GI ND 75 mm per m' m' 261,072.87
10 Pengadaan dan Pemasangan Pipa GI ND 100 mm per m' m' 356,673.28
11 Pengadaan dan Pemasangan Pipa GI ND 150 mm per m' m' 544,827.52
12 Pengadaan dan Pemasangan Pipa GI ND 200 mm per m' m' 965,427.52
13 Pengadaan dan Pemasangan Pipa GI ND 250 mm per m' m' 1,186,422.08
14 Pengadaan dan Pemasangan Pipa GI ND 300 mm per m' m' 1,301,438.92
15 Pengadaan dan Pemasangan Pipa GI ND 400 mm per m' m' 1,654,438.92

II PENCUCIAN DAN PENGETESAN PIPA


1 Pencucian Pipa ND 50 mm per m' m' 1,733.18
2 Pencucian Pipa ND 75 mm per m' m' 2,131.70
3 Pencucian Pipa ND 100 mm per m' m' 2,556.07
4 Pencucian Pipa ND 150 mm per m' m' 2,814.46
5 Pencucian Pipa ND 200 mm per m' m' 3,176.22
6 Pencucian Pipa ND 250 mm per m' m' 4,889.45
7 Pencucian Pipa ND 300 mm per m' m' 5,721.65
8 Pencucian Pipa ND 400 mm per m' m' 7,782.47
9 Pengetesan Pipa ND 50 mm per m' m' 1,699.94
10 Pengetesan Pipa ND 75 mm per m' m' 2,081.66
11 Pengetesan Pipa ND 100 mm per m' m' 2,467.10
12 Pengetesan Pipa ND 150 mm per m' m' 2,614.29
13 Pengetesan Pipa ND 200 mm per m' m' 3,256.91
14 Pengetesan Pipa ND 250 mm per m' m' 4,333.41
15 Pengetesan Pipa ND 300 mm per m' m' 5,093.79
16 Pengetesan Pipa ND 400 mm per m' m' 6,354.60

III PENGADAAN DAN PEMASANGAN BEND (termasuk mur baut dan packing)
1 Bend All Flange CI F 75 mm x 90° bh 272,751.60
2 Bend All Flange CI F 100 mm x 90° bh 344,751.60
3 Bend All Flange CI F 250 mm x 90° bh 610,076.00
4 Bend All Flange CI F 300 mm x 90° bh 1,960,051.00
5 Bend All Flange CI F 100 mm x 45° bh 344,751.60
6 Bend All Flange CI F 150 mm x 45° bh 551,641.60
7 Bend All Flange CI F 200 mm x 45° bh 603,633.10
8 Bend All Flange CI F 250 mm x 45° bh 600,394.20
9 Bend All Flange CI F 300 mm x 45° bh 4,458,160.20
10 Bend all socket PVC 75 mm x 90° bh 132,949.40
11 Bend all socket PVC 100 mm x 90° bh 326,644.60
12 Bend all socket PVC 150 mm x 90° bh 873,245.65
13 Bend all socket PVC 200 mm x 90° bh 1,346,509.65
14 Bend all socket PVC 250 mm x 90° bh 1,937,009.00
15 Bend all socket PVC 300 mm x 90° bh 3,201,514.00
16 Bend all socket PVC 400 mm x 90° bh 14,371,849.00
17 Bend all socket PVC 100 mm x 45° bh 299,375.60
18 Bend all socket PVC 150 mm x 45° bh 549,141.60
19 Bend all socket PVC 200 mm x 45° bh 666,786.60
20 Bend all socket PVC 250 mm x 45° bh 585,076.00
21 Bend all socket PVC 300 mm x 45° bh 1,427,566.00
22 Bend PVC F 100 mm x 22.5° bh 296,558.20
23 Bend PVC F 250 mm x 22.5° bh 1,533,695.20
24 Bend all socket PVC RRJ 11,25° SNI DN 100 mm bh 280,762.20
25 Bend all socket PVC RRJ 11,25° SNI DN 75 mm bh 124,859.20
26 Bend all socket PVC RRJ 11,25° SNI DN 150 mm bh 498,529.20
27 Bend all socket PVC RRJ 11,25° SNI DN 200 mm bh 798,213.20
28 Bend all socket PVC RRJ 11,25° SNI DN 250 mm bh 1,356,353.20
29 Bend all socket PVC RRJ 11,25° SNI DN 300 mm bh 2,132,469.20
30 Bend PVC F 250 mm x 11.25° bh 1,356,353.20

16
HARGA SATUAN
NO JENIS PEKERJAAN SATUAN
( Rp )
1 3 4 5

IV PENGADAAN DAN PEMASANGAN VALVE


1 Gate Valve All Flange F 100 mm unit 1,248,218.61
2 Gate Valve All Flange F 250 mm unit 5,291,046.53
3 Gate Valve All Flange F 300 mm unit 7,667,464.53

V PENGADAAN DAN PEMASANGAN WATER METER


1 Water Meter All Flange F 100 mm unit 2,898,218.61
2 Water Meter All Flange F 250 mm unit 12,166,046.53

VI PENGADAAN DAN PEMASANGAN FLANGE


1 Las Flange F 100 mm bh 194,621.00
1 Las Flange F 150 mm bh 290,981.00
2 Las Flange F 200 mm bh 332,561.00
3 Las Flange F 250 mm bh 585,326.15
4 Las Flange F 300 mm bh 620,856.15

VII PENGADAAN DAN PEMASANGAN TEE DAN REDUSER


1 Tee All Flange CI F 100 x 75 mm bh 461,313.55
2 Tee All Flange CI F 250 x 100 mm bh 1,428,043.55
3 Tee All Flange CI F 300 x 200 mm bh 1,893,123.55
4 Tee all socket. PVC RRJ SNI DN 400 x 300 mm bh 7,248,143.55
5 Tee all socket. PVC RRJ SNI DN 300 x 100 mm bh 3,144,923.55
6 Tee all socket. PVC RRJ SNI DN 200 x 150 mm bh 1,711,293.55
7 Tee all socket. PVC RRJ SNI DN 200 x 100 mm bh 1,423,643.55
8 Tee all socket. PVC RRJ SNI DN 100 x 100 mm bh 468,887.55
9 Tee all socket. PVC RRJ SNI DN 200 x 75 mm bh 1,476,388.55
10 Tee all socket. PVC RRJ SNI DN 100 x 75 mm bh 515,780.55
11 Tee all socket. PVC RRJ SNI DN 150 x 150 mm bh 843,019.55
12 Tee all socket. PVC RRJ SNI DN 150 x 100 mm bh 735,736.55
13 Reducer PVC SNI DN 400 x 100 mm bh 1,765,193.55
14 Reducer PVC SNI DN 200 x 150 mm bh 762,950.55
15 Reducer PVC SNI DN 200 x 100 mm bh 1,088,693.55
16 Reducer PVC SNI DN 150 x 100 mm bh 433,720.55

VIII PENGADAAN DAN PEMASANGAN ACCESSORIES LAIN


1 Flange Socket PVC F 100 mm bh 567,853.43
2 Flange Socket PVC F 250 mm bh 2,045,428.43
3 Flange Socket CI F 100 mm bh 655,163.43
4 Flange Socket CI F 250 mm bh 3,454,863.43
5 Flange Spigot CI F 300 mm bh 4,194,003.43
6 Flange Spigot CI F 100 mm bh 610,731.43
7 End Cap/Dop PVC SNI ND 100 mm bh 62,540.80
8 End Cap/Dop PVC SNI ND 200 mm bh 341,654.80
9 End Cap/Dop PVC SNI ND 250 mm bh 639,919.80
10 Air Valve Ø 25 mm bh 369,811.05
11 Thrust Block K-225 -ND 100 mm bh 79,173.20
12 Thrust Block K-225 -ND 250 mm bh 154,635.15

17

You might also like