Oct 01,2018 Nov 01,2018 Dec 01,2018 Jan 01,2019 Feb 01,2019 Mar 01,2019 Apr 01,2019 May

1,2019 Apr 01,2019 May 01,2019 Jun 01,2019 Jul 01,2019


ID Task Duration Progress
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15

1 Document Review & Revision 12 d 100%

2 Bids & Contracts 10.5 d 100%

3 Grading & Building Permits 4d 100%

4 Install Construction Entrance 2d 100%

5 Install Sediment Controls 2d 100%

6 Site Work 7d 100%

7 Foundation 10 d 100%

8 Layout Footings 1d 100%

9 Install Reinforcing 2d 100%

10 Build Block Foundation 3d 100%

11 Materials Delivery 3d 100%

12 Waterproofing 1d 100%

13 Rough Carpentry 8.5 d 100%

14 Set Steel 1d 100%

15 Framing 7d 100%

16 Install Windows & Doors 1.5 d 100%

17 Concrete Slabs 7d 100%

18 H.V.A.C. 14 d 100%

19 Facilities Rough-in 25 d 33%

20 Roofing 41 d 66%

21 Finish Exterior Work 36 d 44%

22 Insulation 4d 0%

23 Drywall 21.5 d 0%

24 Finish Floor 52 d 0%

25 Paint 42 d 0%

26 Exterior Landscaping 25 d 0%

27 Install Hardware 8d 0%

28 Final Punch-out 5.5 d 0%

29 Construction Close-out 1d 0%