Weight

platform part 1 = working platform


platform part 2 = outter (edge beam), only for support slab and transverse beam

bottom formwork =
max. 250T (include bottom)

minutes meeting for material list, waiting from wiecon


exclude gantry around 13T

posisi lubang akan sama, tapi lifting di deck hanya di pier table

dsi will revise holes position, notes purpose of each holes


total weight lebih detail sesuai yg direncanakan
step 1 (M1, kicker, launching hanger)

pertama transverse truss dulu,


transverse truss, mungkin bisa ditumpuk lebih dari 4

bisa posisi tidur tapi dikasih bed yg bagus supaya tidak lecet catnya
sediakan plate untuk stopper,

teflon, thickness ?

dsi will give the detail of sequence (duration)

checklist before launching dari dsi will give

stressing tendon PT 8-12 hours


abis stressing survey elevasi

2 coil strand in each span (side and main), 1 coil 3 T

hdpe pipe middle of march in Jakarta, 2 weeks later kendari (estimation)


guide pipe 2nd delivery middle of april in Jakarta

cutting list of strand, additional around 14T


60 coil for all

peter masih ada pertanyaaan ke weilung, gambarnya belum ada