Obiectiv: Consolidare si refacere drum local 0.

100 KM, satul Podu Cheii, GRAFIC DE EXECUTIE INITIAL


Comuna Brebu, Judetul Prahova

ID Task Task Name Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4
Mode W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19
1 ORDIN INCEPERE LUCRARI 0 days Mon 01.04.19 Mon 01.04.19 01.04
2 MOBILIZARE 7 days Mon 01.04.19 Tue 09.04.19 1
3 Lucrari de consolidare si refacere drum 75 days Wed 10.04.19 Wed 24.07.19 2
4 Pozitia 1 - Micropiloti 51 days Wed 10.04.19 Thu 20.06.19 2
5 Foraj rotativ 20 days Wed 10.04.19 Wed 08.05.19 2
6 Turnare beton C30/37 23 days Thu 02.05.19 Mon 03.06.19 5FS-5 days
7 Strat de balast 2 days Tue 04.06.19 Wed 05.06.19 6
8 Strat de piatra sparta 2 days Wed 12.06.19 Thu 13.06.19 10
9 Hidroizolatie 5 days Tue 04.06.19 Mon 10.06.19 6
10 Protectia hidroizolatiei cu BA8 1 day Tue 11.06.19 Tue 11.06.19 9
11 Strat de beton asfaltic BA16 1 day Fri 14.06.19 Fri 14.06.19 10;8
12 Parapet metelic directional 4 days Mon 17.06.19 Thu 20.06.19 11
13 Pozitia 2 - Micropiloti 50 days Thu 09.05.19 Wed 17.07.19 5
14 Foraj rotativ 20 days Thu 09.05.19 Wed 05.06.19 5
15 Turnare beton C30/37 22 days Thu 30.05.19 Fri 28.06.19 14FS-5 days
16 Strat de balast 2 days Mon 01.07.19 Tue 02.07.19 15
17 Strat de piatra sparta 2 days Tue 09.07.19 Wed 10.07.19 19
18 Hidroizolatie 5 days Mon 01.07.19 Fri 05.07.19 15
19 Protectia hidroizolatiei cu BA8 1 day Mon 08.07.19 Mon 08.07.19 18
20 Strat de beton asfaltic BA16 1 day Thu 11.07.19 Thu 11.07.19 19;17
21 Parapet metelic directional 4 days Fri 12.07.19 Wed 17.07.19 20
22 Protectia mediului 5 days Thu 18.07.19 Wed 24.07.19 21
23 Protectia mediului 5 days Thu 18.07.19 Wed 24.07.19 21
24 DEMOBILIZARE 5 days Thu 25.07.19 Wed 31.07.19 23

Project: Grafic de executie Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Tue 26.02.19 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress