TEST I.

MULTIPLE CHOICE
1. D 6. A
2. C 7. B
3. A 8. A
4. B 9. C
5. A 10. C

TEST II. ENUMERATION


8 TEMPORARY SERVICES AND FACILITIES
1. Offices
2. Workshops and indoor storage
3. Dry shacks
4. Temporary housing and food service
5. Temporary utilities
6. Sanitary facilities
7. Medical and first aid facilities
8. Access and delivery
REASONS ALLOWED FOR VARIATION OR CHANGE ORDER
1. The owner decide to add and or delete some item to the project
2. Unexpected site conditions discovered during the course of construction
3. Discrepancies may be discovered in the contract documents
4. Codes or regulations may change after the contract is signed, requiring a change in the
contract
5. Products originally specified may not be available
TWO IMPORTANT LEGAL IMPLICATION OF BENEFICIAL OCCUPANCY
1. The issuance of a certificate of completion or substantial completion marks the beginning
of this period
2. The time period for any warranties and guarantees provided by the contractor begins at
that time
FACTORS TO CONSIDER IN DECIDING TO TENDER
1. Project Type
2. Project size
3. The estimated cost of preparing the tender
4. Project location
5. Owner reputation