METHODE OF IMPLEMENTATION OF DEWATERING CLOSING WORK

1. PREPARATION
A. PROTECTION OF WELL AREA
• Protecting the well area for dewatering work does not interfere with other work.

• Provide marks and safety tapes for warnings of nearby workers.

B. MATERIAL WORK
• SIKA GROUT 215
C. ALAT KERJA
• Hammer

• Chisel
• Injection Machine
• Mixer Machine
• Bucket
• Cement spoon
• Machine cutter

2. WORK IMPLEMENTATION
A. Implementation of Dewatering Closure Works

 Make concrete balls ± 5 pieces with diameter size adjusted with pipe dewatering.
 Put all the concrete balls into the dewatering hole.
 Every 1 meter in the content of coral material.
 If the coral has reached the working floor (-25cm), it will be implemented closure using
grouting material sika grout 215.
 Grouting can be done 2 stages, if the source of water from ex well big enough.