You are on page 1of 11

IADC/SPE

IADC/SPE 17256

A Shallow Gas Research Program


by M. Grin rod,* 0. Haaland,* and B. Ellingsen, Statoil AJS
* SPE Members

Copyright 1988, IADC/SPE Drilling Conference

This paper was prepared for presentation at the 1988 IADC/SPE Drilling Conference held in Dallas, Texas, February 28-March 2, 1988.

This paper was selected for presentation by an IADC/SPE Program <?ommittee following review of information contained in an abstract submitted by
the author(s). Contents of the paper, as presented, have not been rev1ewed by the Society of Petroleum Engineers or International Association of Drill-
ing C~ntrac.tors and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the IADC or
SPE, 1ts officers, or members. Papers presented at IADC/SPE meetings are subject to publication review by Editorial Committees of the IADC and
SPE. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicu-
ous acknowledgment of where and by whom the paper is presented. Write Publications Manager, SPE, P .0. Box 833836, Richardson, TX 75083-3836.
Telex, 730989 SPEDAL.

Introduction
A SHALLOW GAS RESEARCH PROGRAM
Up to the present (nov. 19&7) shallow gas
has been reported in 155 of the 567
Abstract exploration and appraisal wells drilled on
the Norwegian Continental Shelf.
Operational problems associated with the Seven blowouts and a number of kicks caused
occurence of shallow gas in offshore by shallow gas have been recorded.
drilling led Statoil to initiate a massive On the night of October 6th, 1985, a gas
research program. The program consisted of blowout occured on the semi-submersible
the following subprojects: Revised drilling "West Vanguard", during exploration
procedures, shallow gas drainage, drilling in block 6407/6, Haltenbanken,
multistage cementing, gas tight cement, Norwegian sector.
diverter systems, rig ventilation systems The well blew out from a shallow gas sand
and emergency anchor release. while drilling ·the 311mm (12 1/4") pilot
Emphasis in this paper is placed on the hole at 523m RKB, with the marine riser
experience from the West Vanguard blowout, installed. The diverter system and riser
and results from the subprojects on failed as a result of the extremely large
diverter systems, drilling procedures, flow of gas and solids.
quick anchor release and ventilation The eroded flow diverter system and slip
systems. joint packing leak allowed gas to flow into
Other papers (reference 1, 2) give the drilling platform where the gas
information on development of gas tight subsequently ignited.
cement, stage cementing and additional The resulting explosion and fire caused
background on shallow gas drainage. considerable damage. The platform was
quickly evacuated. One person was lost.
Damage to the rig amounted to several
hundred million Norwegian kroner.

629
2 A SiiALI!M GAS RESEARCH PROGRAM S~£17256

The investigation after the West Vanguard


blowout disclosed that significant Erosive wear test of Diverter System
improvements were needed in diverter Compo]1ents
systems. It was further evident that
riser-less drilling would be the best The West Vanguard blowout clearly
option under certain conditions. Air demonstrated the weakness of diverter
ventilation systems had an influence on gas systems. Holes were worn in the diverter
distribution, and the fire and explosion bends in a period of less than 20 minutes.
pattern. The drilling procedures needed to The largest hole was located in the first
be updated, and rig crews educated on the bend where the diverter line was tied to
dangers of shallow gas. the flowline.
At this point the sand had cut its way
through other piping and into the shale
Shallow Gas shaker room. The second bend in the
diverter line was also eroded.
Gas sands at shallow depths have frequently Based on these facts an experimental
been penetrated. These sands have been investigation has been performed to
encountered as shallow as lOOm below the determine the most suitable geometry for
seabed. Predicting the exact presence of diverter components, and the relative
shallow gas sands from seismic or sparker erosion and abrasion resistance
investigations is still unreliable, and characteristics of selected materials.

their existence is often exclusively The test philosophy was based on comparing

disclosed by MWD and/or wire line logs. the various coatings as well as piping

Shallow gas is primarily localized in sand geometry. Identical components with

lenses surrounded by shale in the upper different coating were placed in a test
tertiary sediments. loop to obtain comparable test conditions.
Common mild steel was used as a reference
The gas pressure in these pockets is
material. In the appendix the mathematical
normally at or slightly above the normal
water gradient. Since the thickness of the theory behind these tests is discussed.

sand pockets are normally limited to a In summary the test results were:

maximum·of lOrn, the actual over-pressure in


excess of a hydrostatic water gradient, is Particle velocity is the most

small. significant factor on erosive wear.


Particle size has very little influence
Because of the low pressure regime,
spontaneous kicks with the riser installed on the value of specific erosion.
seldom occur. The risks of losing primary Increase of bending diameter reduces

control lies mainly in swabbing or when the value of specific erosion.


lost circulation occurs. Hardfacing extends the lifetime of

The West Vanguard blowout is assumed to be bends.


a consequence of loss of hydrostatic head Efforts should be made to design

caused by gas expansion in the riser. diverter systems as straight as


possible, avoiding bends.

630
sP6 17256 M. GRINR(£?D A.(Z). HALAND B. ELLINGSEN 3

Components and Bend Coating significantly longer life than the short
radius bend. The long radius bend with a
The test programme included some 53 bending diameter of 0.83m had almost a 50%
components. This comprised of 37 bends, 10 improvement in life span compared with the
hoses and 6 valves. In addition to the short radius bend with a bending diameter
reference steel bends tested, a total of of 0.26m.
five different bend surface coatings were
examined for erosive wear resistance. Bend Angle

Test Rig It is difficult to isolate the influence of


the bend angle since the tested bends had
The erosive wear test was carried out in a different diameters. It would appear,
closed test loop ~here high abrasive silica however, that the 60° bend tested with a
sand was recirculated. One mobile diesel diameter similar to the short radius 90°
3
compressor capable of delivering 0.7lm /s bend, will last about 80 % longer than the
of free air at a pressure of 10 bar was equivalent 90° bends.
used to accelerate the sand to a maximum
velocity of lOOm/s. Diverter Design

Comparison of surface coatings During the erosive wear testing it became


evident that the reinforcement of diverter
One of the hardfacing materials showed components will not provide an acceptable
significantly better restistance to erosive level of lifetime within economical or
wear than the other materials. This practical limits. The hardfacing material
hardfacing material contained 60 percent by that performed best extended the life by
weight tungsten carbide bonding in an about three and a half times compared with
erosive-corosive resistant alloyd matrix. mild steel.
The amount of tungsten carbide is of great Consequently every effort should be made in
importance. Tests also were performed with designing a more satisfactory diverter
65 percent by weight tungsten carbide and system. Geometry being the most important
these showed even better results. However factor.
cracking was more extensive than for the Discontinuties in the diverter line must be
other materials. This is due to the avoided; such as bends or changes in pipe
thermal strain during the hardfacing diameter.
process, and can be improved by reducing Where bends are unavoidable, these should
the hardness in the matrix. be hardfaced. The tests have proved the
importance of material selection.
The other hardfacing materials tested were
not significantly better than plain steel. In addition the straight section following
a discountinuity should be hardfaced at a
Bend Diameter length of approx. 1,5 mas this section
will be exposed to heavy turbulent flow and
Since two 90° bends with different erosive wear.
diameters were tested, the analysis Diverter valves should be located before,
provided a direct comparison of the or at a sufficient distance from any
influence of bend diameter. The results discontinuty.
showed that the long radius bend had a

631
4 A SHALLOW GAS RESEARCH PROORAM SPe 17256

Where flanges are used, these should be The potential fire hazard from an
machined and matched to ensure that the
underwater release of shallow gas was
inside surface is perfectly smooth and free
investigated.
from steps and ridges.
The testing proved that the most important
At the West Vanguard blowout the fire on
parameter effecting erosive wear is the
the ocean surface had a diameter of
particle velocity, and this parameter can
approximately 60 meters. The waterdepth was
be controlled by mounting a choke at the
220 meters giving a central gas zone of
ends of the diverter lines. On jackups and
some 35% of the water depth.
fixed platforms where the diverter system
Based on the experience from the actual
in most cases is the only protection if gas
blowout, theoretical simulations were
flow occurs, it is of great importance to
performed to investigate gas concentrations
reduce the flow rate.
on the ocean surface and above.

Figure 1 is a projection of the gas cloud


Development of drilling procedures
resulting from the gas flow from the 762mm
(30") wellhead after the marine riser was
The top hole drilling procedures for
disconnected on the West Vanguard accident.
floaters were reviewed. This changes can
This projection indicates the height of the
be summarised as follows:
flame up to 1 meter above sea level, which
seems to be a fair assumption of what was
setting depth of the 762mm casing (30")
actually seen at the location. Figures 2
based on
and 3 show two different projections with
expected leak off
wind velocity reduced to 3m/s. Here it
20 inch setting depth
clearly shows how the shape, height and
site survey results
concentration of gas is highly dependent
increased mudweight in pilot hole to
upon the effect of wind, and that in this
min. 1.10 SG when drilling with marine
instance the concentration is within the
riser
limits of flameability up to a height of
MWD tool run on slick bottom hole 25 meters. However these figures support
assembly the fact that upgrading in design and
max. 30 m/hour rate of penetration layout of the ventilation system is
important, since in certain instances
Later the authorities' requirements led to dangerous concentrations of gas can be
an amendment in the maritime certificates present at 15-25 meters above sea level.
of all Norwegian flagged drilling vessels. Reducing the amount of gas by 50% and
Stating that surface diverter systems waterdepth to BOrn, dangerous concentrations
should only be used in the short period, of gas up to 20m above sea level can arise,
until the riser is disconnected. This in (ref. fig. 4).
addition to the fact that several problems
were experienced in the disconnection of
the marine riser led to a philosophy where
riserless drilling is accepted by Statoil
as a safe and co9t effective top hole
drilling procedure under certain
conditions.

632
M. GRINRQ)D B. ELLINGSEN 5

The fact that dangerous concentrations of Special arrangements and modifications· in


gas on a rig are not solved by drilling the use of a shallow gas stack:
riserless, led to extra precautions when
drilling through seismic anomalies without It will be necessary to be able to
the marine riser installed. These can be drift an existing specific profile on a
summarised; by displacing the hole to 4 76rnrn · (18 3 I 4 ") wellhead housing
sufficient mud weight, and combining the through the 7621nrn (30") ID of the SGS.
design of the hole size and bottom hole
assembly so that dynamic kill is possible. Flushing arrangement in the 762rnrn (30")
wellhead connector will keep the
When shallow gas is encountered the pilot wellhead area clear during cementing of
hole will be plugged back and 20" c~sing the 508mrn (20") casing.
set immediately above. The conventional
476rnrn (18 3/4") BOP stack is then installed Original minimum disconnecting
allowing the gas zone to be drilled with requirements on 762mrn (30") connector
BOP control. In this case setting of a in the upper section were:
406mrn (16") liner may be necessary. To
avoid this time consuming operation Statoil 69 bar pressure trapped under
a)
is now in the process of incorporating a 6
shear ram equal to 3.1 x 10 N
subsea shallow gas stack (SGS), which will
tension.
allow setting of the 508rnrn (20") through
shallow gas zones with BOP control. 2.7 x 10 5N tension caused by riser
b)
tensioners.

The SGS consists of an upper section and a 3.4 x 10 5Nm bending caused by the
c)
lower section (fig. 5). The lower section
flexible joint.
has a 762mrn (30") wellhead connector with
flushing ports, a spool with kill valve and 0-10° angle on flexible joint.
d)
a "dump" valve, 30" annular BOP,
accumrnulator bottles, adaptor and The selected connector is capable of
framework. The lower section has a minimum
disconnecting under combined loads.
inner diameter of 762mrn (30").
The upper section consists of a 762nun (30")
The shear ram is designed to cut 127mrn
connector capable of disconnection under
(5") DP if emergency disconnection of
extreme conditions, a shear ram, flex
the upper section is necessary.
joint, choke/kill line, riser adaptor and
framework. Minimum inner diameter of the
A control system and a flexible kill
upper section is 476mrn (18 3/4").
line are connected to the lower section
of the SGS. This arrangement makes it
If gas cannot be controlled, or if
possible to operate the lower section
formation breaks down, the upper section of
while the upper section and riser are
the SGS will be released by means of the
pulled.
specially selected connector/disconnector
system.

633
6 A SHALLOW GAS RESEAHCH PROGRAM sJ?e 112s6

Anchor emergency guick release: Rig Ventilation system

During the shallow gas blowout/explosion on The air ventilation system on West Vanguard
board the "West Vanguard", the emergency was divided into several separate systems
quick release on four anchor lines was with air intake fans and air outlet fans.
activated. on·e of the winches failed to Air ventilation had manual shut-down in
release. case of a gas alarm. The air intake fans
were stopped manually when the well started
Considering off-shore blowouts it has been to flow; however air outlet fans remained
obvious that: running.
This is considered to have contributed to
Technical damages and weak points in gas explosions in some rig areas.
the anchor system on several occasions The explosion potential, when gas enters
have rendered. an emergency quick the ventilation system, was proven during
release impossible. the blowout, i.e the generator room
Emergency quick release has not been exploded. Consequently measures to reduce
activated due to risk of ignition of this risk were investigated.
the blowout gases.
The anchor system is vulnerable to Following are the results which have been
explosions at deck level. implemented:
Most existing anchor systems lack
sufficient redundancy. Gas detectors installed in all air
intakes.
Information concerning the following was Automatic stop of all ventilation fans
collected and analyzed: when gas alarms are activated.
Remote control ~f valves on critical
Anchor systems and emergency quick air intakes.
release systems on existing platforms
Procedures related to operations of Shallow gas drainage
these systems
Accidents related to blowouts Drainage of shallow gas could be an option
Alternative release systems in the following circumstances:

Based on the results the following items


Before commencement of development
have been implemented on Statoil operated
drilling where the fixed installations
platforms during 1986/87:
cannot be located outside the shallow
gas area.
1. Manual release of the anchor winches.
In exploration drilling where gas
2. Quick release panel installed on the
layers have a large areal extent and
bridge.
several wells are to penetrate the gas
3. Improvement of electric/electronic
layers.
components.
4. Increased sprinkler capacity.

634
rofJts 17256 a. GRINR0D 7

During exploration drilling in block 34/10 Increasing the lifetime of surface


- i.e. Gullfaks field, in ca. 60% of the diverters can be achieved by reducing
wells shallow gas has been penetrated. In velocity of particles. Reduction of
1983 it was decided to drill the first velocity can be obtained by end mounted
shallow gas investigation well near the chokes.
Gullfaks "A" platform location. This well
was drilled to 550m MSL and shallow gas was -Increase of bend diameter and
revealed. A number of similar wells have hardfacing of diverterpiping, and an
been drilled since to improve the mapping increase in pipe diameter will increase
of shallow gas in general. lifetime of diverter systems.
Well 34/10-30 was drilled and completed
with the intent to attempt depletion of the A theoretical model for gas
gas sand before the Gullfaks "A" platform concentrations above sea level has been
was placed on its location. developed taking into account rate,
The sand, 312-314,5m MSL, produced during waterdepth and wind velocity.
35 days. The production rate was
approximately 60.000 SCM/day~ the maximum Riserless top hole drilling when
rate was 115.000 SCM/day (short period). checking out anomalies should in all
cases be done with hole size and
The reservoir pressure, in the shallow mudweight designed to allow dynamic
sand, was 33.5 bar, i.e. 1 bar in kill.
excess of normal hydrostatic pressure.
This indicates a gas column height of Shallow gas stacks will promote control
6m. of top hole drilling and protect
The gas was 99% methane. against gas flow to the rig.
Sand was produced into the well. A
gravel pack was done. Rig ventilation system should be
Permeability of the reservoir: between designed for full automatic shut down
200 and 350mD. in case of a gas alarm.

Due to circumstances and platform placement


the test was abandoned and the well References:
plugged. In total 2.800.000 SCM had been
produced. (Ref. 1.) The desired pressure 1. Grinr¢d. M, Tomren. P.H, Justad. T:
and gas depletion was not obtained. "Development of the Gullfaks field"
Paper IADC/SPE 17220, presented at
IADC/SPE Drilling Conference, March
Conclusion 1988.

Changing drilling procedures seem to be 2. Dings¢yr. E, Vass¢y. B and Grinr¢d. M:


the most important contribution to an "Development and Use of a Gas Tight
increased level of safety for floating Cement" Paper IADC/SPE 17258, presented
drilling. Drilling programs and at IADC/SPE Drilling Conference, March
procedures for top hole drilling should 1988.
be designed to enhance safety at each
location based on existing information.

635
8 A SHALI.CM GAS RESEARCH PR:X;RAM S'PE. 17256

3. D. Mills and J.S. Mason: "Conveying


Velocity Effects in Bend Erosion. Proc.
Int Symp. on Freight Pipeline.
Washington D.C. 1976".

Subsequently published in the Jnl. of


Pipelines, Vo. 1, No. 1, pp 69-81,
1981.

4. D. Mills and J.S. Mason: "Particle


Concentration Effects in bend Erosion
Powder Techno!. Vol. 17, No. 1, pp
37-53, 1977".

5. D. Mills and J.S. Mason: Evaluating the


Conveying Capacity and Service Life of
Pipe Bends in Pneumatic Conveying
Systems. Proc. Powder Europa '78. PAC
Conf. Wiesbaden. Jan. 1978"~

Jnl. of Powder and Bulk Solids Tech.


Vol. 3, No. 2, pp 13-20 1979.

6. D. Mills and J.S. Mason: "Analysis of


Factors Influencing the Premature
Failure of Pipe Bends in Pneumatic
Conveying Systems. Proc. 2nd Conf. on
Pneumatic Conveying, pp 93-103. ISBN
963 8091 64 7. HUngarian Sci. Soc.
Mech. Engrs. Pees. Hungary, March
1978".

7. D. Mills and J.S. Mason: "The Effect of


Particle Size on the Erosion of Pipe
Bends in Pneumatic Conveying Systems.
Proc. POWTECH '70. pp H 50-96. !ChernE
Conf. Birmingham. March 1979".

636
SPE 17256
A P P E N D I X

BEND LIFE CALCULATIONS (ref. D. Mills and J.S. Mason)

Specific Erosion mass eroded from component g/tonne


mass conveyed through component

Msf Mbf
tonne
E

where Msf Conveyed mass of sand before


component fails (g)

and Mbf Eroded mass from component


before failure g

and E Specific erosion

The Time to Failure For a Component

Tbf = Msf x 60 min


ms

Where Tbf time before failure


and ms flowrate of sand tonne/h

In the test the sand was conveyed at a phase density (0) of 1.0
and the mass flow rate of the sand was the same as that of the
air.

The Influence of Conveying Air Velocity

Specific erosion increases with the increase in velocity


according to

E~ C 2.65

for sand conveyed through 90 degr. bends.

Where C = Conveying air velocity m/s

The Influence of Phase Density

Specific erosion decreases with increase in phase density


according to

EOc:' 0 -0.16

for sand conveyed through 90 degr. bends.

The Influence of Particle Size

Particle size has little influence on the value of specific


erosion, however, the influence o£ turbulence increases
significantly with a decrease in the mean particle size. The
influence of turbulence is additionally effected by phase density
(0) and so for a 70 ~m sand, for example, the time quoted at 0=1
will vary by a factor of about +/- 2 compared with a 230 ~m sand.

637
SPE 1725b
%BY VOLUME GAS IN AIR % BY VOLUME GAS IN AIR

- · - · - · - · - 30.0
- - - - - - - - 15.0
===~ 5.0
2.0
1.3
i i
)( )(

120
Z(M) Z(M)
Y(M): O.OOOE + 00 Y(M): O.OOOE + 00

RATE : 120 KG/S UF RATE : 120 KG/S U


WIND: 15M/S ' L: 15%, LFL: 5% WIND: 3M/S ' FL: 15%, LFL: 5%
WATER ' T-AIR: 10C ' T-AIR• 10C
DEPTH•• 2 20M, DIAMETER GAS ZONE· 60 ATER DEPTH• • ' T-GAS: 10C
W • 220M, DIAMETER GAS
Fig. 1-Gaa oloud alter Weal Van guard accident.
• M Fig. 2-Weat V ZONE: &OM
anguard gaa cloud with reduced wind velocity.

% BY VOLUME GAS IN AIR %BY VOLUME GAS IN AIR

40

- · - · - · - · - 30 0
---·
................ 5.0
2.0
- - - - - - - - 15:0
.•... ::::::::: 5.0
1.3 2.0
1.3
·····································
i
)(

10

40 70
Y(M) Z(M)
z (M): 1.000E + 02 Y(M): O.OOOE + 00

RATE : 120 KG/S RATE : 60 KG/S


WIND: 3M/S T' UFL: 15%, LFL: 5% WIND: 3M/S T ' UFL: 15%, LFL: 5%
• -AIR· 10C WATER DEPT'H· -AIR: 10C, T-GAS: 10C
WATER DEPTH: 220M. ' T-GAS: 10C
. ' DIAMETER GAS ZONE· • 80M, DIAMETER GAS ZONE: 19M
Fig. 3-Weat V • &OM
anguard gaa cloud with reduced wind velocity. Fig. 4-Gaa cloud with water depth and
' rate reduced.

638
SP£ 17256

SHALLOW GAS BOP

RISER
ADAPTOR

FLEXIBLE
KILL LINE
CHOKE
LINE

ANNULAR
BOP
DUMP

0VALVE
FLUSHING W.H.
LINE
CONNECTOR

Fig. 5-Shallow gas valve stack.

639

You might also like