By RPAD /Hand Delivery

REF:GPIPPL/GETCo/O &M /09/Narali/October,November-18 Date: 1/12/2018

To,
The Executive Engineer (TR),
Gujarat Energy Transmission Corporation Limited (GETCO)

Sub: –Operation and maintenance work at 66 KV Sub-station–Calculation of Minimum wages.


Ref:A/T No: CE(TR)/SE(TR)/EE(SS)/DE(L1)/T-12/GPI/1366 Dated 23.05.2018

Dear Sir/Madam,
For Substation: Narali Month: October, November -18
With reference to the above, as per the new Minimum Wages Act revised on 1st April 2018,
following is the calculation for the same:
Wages from 1st April to 31st Oct
Skilled 320.20
Semiskilled 312.20

320.20 + 312.20
= 125067.620 × [ 0.22 + 0.78 × ]
313.60 + 305.60

632.40
= 125067.620 × [ 0.22 + 0.78 ]
619. .20

= 125067.620 x [0.22 + 0.78 x 1.021318]

= 125067.620 x [0.22 + 0.79662]

= 125067.620 x [1.01662]

= 127147.233

 Previously it was different for skilled and semi-skilled workers, which is mention below:

Wages as per time of LOI


Skilled 313.60
Semiskilled 305.60

It is requested to expedite the payment against pending invoices from your end.
Thanking you,
With Regards.

For, GPI Projects Pvt Ltd , Ahmedabad