Project: Jakarta Tank

Daily Activity QAQC Terminal Phase 2

Date/Day: 27-03-2019
PT. Jakarta Tank Terminal Document No: INA-VTJ-MTCF-PRJ014
Hours: 08.00-17.00
Project: Jakarta Tank
Daily Activity QAQC Terminal Phase 2

Date/Day: 27-03-2019
PT. Jakarta Tank Terminal Document No: INA-VTJ-MTCF-PRJ014
Hours: 08.00-17.00

Subject : Daily Activity


Discipline : Civil
EPC : TPEC

Area of Concern:

- Pile No 123 of manifold Pit broken.


- Pile broken 5 pcs at manifold pit, info from TPEC damage hit by HSPD.
- Some Pile at pipe sleeper 2008 the mis location is out of tolerance.
Today:

- Witness tensile test of anchor bolt A-307B dia 1’’, 7/8’’, ¾’’, ½’’ & 5/8’’ result pass.
- Monitoring excavating, LC & Install formwork of Pit Manifold.
- Monitoring Finishing Foundation of Tank.
- Monitoring foundation work of PSL 2008.
- Monitoring install formwork at bund wall.
- Monitoring install sheet pile bund wall.

Tomorrow:

- Monitoring excavating Pit Manifold.


- Monitoring Finishing Foundation work.
- Monitoring install formwork at bund wall.

Photograph
Project: Jakarta Tank
Daily Activity QAQC Terminal Phase 2

Date/Day: 27-03-2019
PT. Jakarta Tank Terminal Document No: INA-VTJ-MTCF-PRJ014
Hours: 08.00-17.00