You are on page 1of 19

Circular 86

STATE OF ILLINOIS
DEPARTMENT OF REGISTRATION AND EDUCATION

by BRIAN BERG, R. W. LANE, AND T. E. LARSON

ILLINOIS STATE WATER SURVEY


URBANA
1963
CONTENTS

Page

Abstract 3
Introduction 3
Acknowledgments 4
Estimation of cooling tower costs 4
Initial cost 5
Fixed costs 7
Power costs 7
Maintenance costs 7
Additional power costs 7
Water treatment 7
Concentrations 9
Make-up water costs 11
Check list 11
Estimation of once-through cooling costs 12
Initial c o s t s , self-supplied water 12
Power costs 13
Derivation of cost relationships 13
Relative rating factor 13
Tower costs 14
Installation 14
Chemical treatment 15
Make-up 16
Power 16
Other considerations 17
Summary 17
References 18
Printed by the authority of the State of Illinois - I.R.S. Ch. 127, P a r . 58.29
Water Use and Related Costs with Cooling Towers

by Brian Berg, R. W. Lane, and T. E. Larson

ABSTRACT

Methods of water use for heat dissipation a r e evaluated, with


emphasis on simplification of annual cooling tower cost e s t i m a t e s .
Tower costs for initial equipment and installation, annual fixed c o s t s ,
and operating costs are considered. Results of the study are presented
in an e a s y - t o - u s e , step-by-step form so that e s t i m a t e s for specific
cases may be made and compared with estimated costs of n o n - c o n s e r -
vation p r a c t i c e s . It is recommended that if costs of once-through and
conservation methods are within about 30 per cent of each other, a
thorough study of cooling water needs is justified.

INTRODUCTION

In studying the water r e s o u r c e s of northeast- use form, so that approximate costs for specific
ern Illinois to determine their ultimate availability cases may be estimated and compared with the
in relation to predicted r e q u i r e m e n t s , considera- costs of non-conservative p r a c t i c e s . If the derived
tions of r e u s e and conservative m e a s u r e s are costs are i n c l o s e range to or l e s s than the p r e s e n t
n e c e s s a r y c o r o l l a r i e s which demand attention. or projected costs of existing water use s y s t e m s ,
Economic factors as well as water availability a complete and thorough study of cooling water
determine whether conservation practices are needs is justified. It is not the purpose of this r e -
adopted. The fact that water conservation m e a s u r e s port to r e p l a c e the specialized competence of the
a r e a common p r a c t i c e , which has led to the devel- consulting e n g i n e e r o r the water t r e a t m e n t
opment of a now sizeable allied industry, testifies consultant.
to a degree that localized needs do exist and that Although this r e p o r t is concerned p r i m a r i l y
such m e a s u r e s can be economical. This study is with n o r t h e a s t e r n Illinois which has suffered from
p r i m a r i l y concerned with an economic evaluation what is probably one of the g r e a t e s t ground-water
of cooling towers for water r e u s e plus comparable r e c e s s i o n s in the world, the r e s u l t s and factors
evaluation of self-supplied or purchased water for considered a r e applicable to m o s t a r e a s where
once-through u s e . p r e l i m i n a r y e s t i m a t e s for relative economic
In judgment on use of cooling towers for con- evaluation a r e d e s i r e d .
servation of w a t e r it should be recognized that the Of p a r t i c u l a r interest from this study was
quantitative need for make-up water for cooling the chemical savings that can be realized by p e r -
towers is low, but such water is largely consumed mitting m i n e r a l concentrations in the cycled water
(evaporated) and the small r e m a i n d e r is degraded in cooling towers to increase 5- to 10-fold r a t h e r
for subsequent r e u s e when r e l e a s e d from the tower than 1.5- to 2.0-fold as c o m m o n l y practiced.
because of the accumulation of m i n e r a l s . For once- Although by percentage the g r e a t e s t water savings
through use of water for cooling the quantitative a r e experienced at 1.5 to 2.0 concentrations of
needs a r e relatively high, but usually l e s s than one m i n e r a l s , significant reduction in water needs can
per cent is consumed and the discharge is generally be obtained when g r e a t e r controlled concentrations
degraded only by a r i s e in t e m p e r a t u r e . of m i n e r a l s a r e permitted in the cycled w a t e r .
This r e p o r t p r e s e n t s the r e s u l t s of an examina- This has g r e a t e r significance f o r t h e l a r g e r
tion of cooling tower costs in a ready and e a s y - t o - installations, and can amount to s e v e r a l million
3
g a l l o n s in a few m o n t h s . Acknowledgments
The specific a r e a s of cooling c o s t s considered This r e p o r t was prepared by Brian Berg,
in this report a r e : s p e c i a l r e s e a r c h a s s i s t a n t , and R u s s e l l W . L a n e ,
1) I n i t i a l c o s t of e q u i p m e n t and i n s t a l l a t i o n c h e m i s t and s u p e r v i s o r o f t h e S t a t e I n s t i t u t i o n
e x c l u s i v e of a l t e r a t i o n s to the existing water t r e a t m e n t s e r v i c e , under the general d i r e c -
system t i o n o f D r . T . E . L a r s o n , a s s i s t a n t chief and h e a d
of t h e c h e m i s t r y s e c t i o n of t h e I l l i n o i s S t a t e W a t e r
2) A n n u a l fixed c o s t s i n c l u d i n g a m o r t i z a t i o n , Survey. J. Raymond C a r r o l l of C a r r o l l , Henneman
depreciation, interest, taxes, insurance, and A s s o c i a t e s p r o v i d e d c o n s u l t a t i o n and r e v i e w e d
rent t h e r e p o r t . D a t a f r o m m a n y v e n d o r s and m a n u -
facturers a r e gratefully acknowledged, as a r e p a r -
3) Annual operating c o s t s including water,
t i c u l a r l y the helpful c o n f e r e n c e s with p e r s o n n e l of
treatment, p o w e r , maintenance, etc.
The Marley Company, Fluor P r o d u c t s Company,
S u g g e s t i o n s for r e l a t i n g t h e s e t o s e l f - p r o d u c e d and Binks M a n u f a c t u r i n g C o m p a n y . M r s . J , L o r e e n a
and p u r c h a s e d w a t e r use on a c o m p a r a b l e basis a r e Ivens e d i t e d the m a n u s c r i p t and John W . B r o t h e r
included. p r e p a r e d the i l l u s t r a t i o n s .

E S T I M A T I O N O F C O O L I N G TOWER COSTS

Cost d a t a , provided by m a n y cooling tower ings c a n b e u s e d t o b r e a k u p t h e w a t e r s o t h a t i t


m a n u f a c t u r e r s on their respective types of t o w e r s , will h a v e good s u r f a c e c o n t a c t w i t h the a i r . T h e
w e r e a s s e m b l e d and c o m p a r e d o n a c o m m o n b a s i s . t w o m o s t c o m m o n t y p e s a r e t h e film flow p a c k i n g s
Although a n u m b e r of f a c t o r s i n f l u e n c e t h e and t h e s p l a s h p a c k i n g s .
r e l a t i v e c o s t s o f cooling t o w e r s , t h e t y p e o f c o n - C o r r e l a t i n g c o s t s for e q u i p m e n t w i t h t h i s
s t r u c t i o n - - w h e t h e r all w o o d , m e t a l with wood n u m b e r o f v a r i a b l e s i s t h e r e f o r e difficult and
t r i m , galvanized iron, aluminum, stainless steel, h a z a r d o u s and h a s n e c e s s i t a t e d n u m e r o u s a s s u m p -
or other m a t e r i a l -- is a p r i m a r y factor. t i o n s . The r e l a t i v e r a t i n g factor developed by The
T h e r a t i o of a i r to w a t e r flow is a l s o a f a c t o r Marley Company provided a common denominator
b e c a u s e t h e h i g h e r t h i s r a t i o t h e s m a l l e r the t o w e r for t h e c o r r e l a t i o n . A s a p p l i e d i n t h i s r e p o r t , t h e
f r a m e . The s m a l l e r tower frame r e s u l t s in lower d e r i v e d c o s t s s h o u l d b e within a p p r o x i m a t e l y 1 0
initial cost, but at the s a c r i f i c e of higher operating to 30 p e r cent of the actual c o s t s providing the
c o s t s due t o g r e a t e r fan p o w e r r e q u i r e d for i n - proposed installation complies reasonably well
c r e a s e d a i r flow. This o p e r a t i n g cost is further with t h e s e p r i m a r y a s s u m p t i o n s :
r e l a t e d t o t h e t y p e and l o c a t i o n o f t h e f a n . 1) The tower is installed on-grade
Initial c o s t s a r e also r e l a t e d to pump head 2) The tower is in reasonably close proximity
r e q u i r e m e n t s . High p u m p h e a d t o w e r s g e n e r a l l y t o the e q u i p m e n t i t i s t o s e r v e
have a lower initial cost, but again the operating 3) No special provision is m a d e to conceal
p o w e r and m a i n t e n a n c e c o s t s a r e g r e a t e r . T h e the t o w e r ' s e x i s t e n c e ( a e s t h e t i c a p p e a l ) .
efficiency of the packing design is another factor S p e c i a l c o n s i d e r a t i o n s not i n c l u d e d i n t h e s e
in this r e s p e c t , since many different types of pack- assumptions will r e q u i r e additional expenditures,
and a r e n e c e s s a r i l y o m i t t e d f r o m the c o r r e l a t i o n s
ABBREVIATIONS i n t h i s e v a l u a t i o n . A e s t h e t i c a p p e a l , for i n s t a n c e ,
could d i c t a t e s u p p l e m e n t a r y e x p e n d i t u r e s g r e a t e r
R Range (HWT-CWT)* t h a n the c o m b i n e d t o w e r , a c c e s s o r i e s , and i n s t a l -
A Approach (CWT-WBT)* lation c o s t s .
HWT Hot w a t e r t e m p e r a t u r e * To compute individual cooling costs based on
CWT Cold w a t e r t e m p e r a t u r e * t h e m e t h o d s i n t h i s r e p o r t , t h e following i n f o r m a -
WBT Wet b u l b t e m p e r a t u r e * tion (also see list of abbreviations) is r e q u i r e d :
RRF Relative rating factor 1 ) R e q u i r e d c o l d w a t e r t e m p e r a t u r e (CWT)
L Circulation r a t e , gallons per minute (gpm)* 2) E x p e c t e d h o t w a t e r t e m p e r a t u r e (HWT)
MU M a k e - u p w a t e r , g a l l o n s p e r h o u r (gph) 3 ) D e s i g n w e t b u l b t e m p e r a t u r e (WBT); s e e
Q H e a t d i s s i p a t i o n r a t e i n Btu p e r h o u r (Btuh) table 1
C Concentrations 4) C i r c u l a t i o n r a t e of w a t e r in gpm (L), or
t h e h e a t d i s s i p a t i o n r a t e (Q) i n Btu p e r
*From the Cooling Tower Institute Bulletin NCL 1092 h o u r (Btuh)
4
5) M i n e r a l a n a l y s i s of t h e w a t e r s u p p l y graph in figure 2. This cost includes installation
6) C o s t of w a t e r o f t h e t o w e r , and a l l p u m p s , c o n t r o l s , p i p i n g , and
7) C o s t of p o w e r w i r i n g a s s o c i a t e d w i t h the t o w e r .
8) K n o w l e d g e of the v a r i a b l e s i n v o l v e d in the T a b l e 1 . Wet Bulb T e m p e r a t u r e s
fixed c o s t o f o w n e r s h i p ( t a x e s , i n t e r e s t ,
etc.) Summer
With t h i s i n f o r m a t i o n it is t h e n p o s s i b l e to u s e 24-hour 9-hour**
this report to e s t i m a t e initial cost, the costs of City average* average
power, maintenance, water treatment, make-up
w a t e r , and b a s i c fixed c o s t s for c o o l i n g t o w e r i n - Chicago 63 65.1
s t a l l a t i o n s and o p e r a t i o n . C e r t a i n d e s c r i p t i v e Joliet 62.8 ----
m a t t e r i s i n c l u d e d for c l a r i f i c a t i o n , and s u p p l e - Peoria 63.9 68
m e n t a r y explanations of derivations a r e discussed. Springfield 65.3 68.3
St. L o u i s 66.6 68.8
Annual
Initial Cost Design***
24-hour 9-hour** wet
average average bulb
The r e l a t i v e r a t i n g f a c t o r (RRF) i s a m e a s u r e
of t h e d e g r e e of difficulty to o b t a i n t h e r e q u i r e d Chicago 45.2 47.3 74.8
p e r f o r m a n c e . A r e l a t i v e r a t i n g f a c t o r of 1.0 h a s Joliet ---- ---- 75.3
b e e n assigned to the a r b i t r a r y s t a n d a r d conditions Peoria ---- ---- 75.6
of r a n g e (R) = 1 0 F , a p p r o a c h (A) = 1 0 F , and d e s i g n Springfield ---- ---- 76.8
w e t bulb t e m p e r a t u r e (WBT) = 7 0 F . T h e r a n g e and St. L o u i s 49.7 51.6 76.8
t h e a p p r o a c h p a r a m e t e r s define the r e l a t i v e r a t i n g (Data tabulated by meteorology 'section, Illinois State Water Survey,
f a c t o r for s p e c i f i c d e s i g n c o n d i t i o n s . D e s i g n wet from U.S. Weather Bureau airport records 1949-56 and from Fluor
bulb values m a y be obtained from table 1. The Products Company 3)
* Median values are about 1.5F higher
r e l a t i v e r a t i n g f a c t o r u s e d for s e l e c t i o n of t o w e r ** 8:00 AM to 5:00 PM
s i z e can be o b t a i n e d f r o m f i g u r e 1, and the t o t a l *** Design wet bulbs are those which will be exceeded only 5 per
i n i t i a l c o s t m a y t h e n b e d e r i v e d f r o m the n o m o - cent of the hours in the period June 1 through September 30.

Figure 1. Relative rating factor chart


5
To determine total initial cost, first calculate If the cooling water circulation rate is not
the range (R) and approach (A), then enter figure 1 known, it can be determined (ingallons per minute),
with these values to select a relative rating factor from the heat dissipation r a t e (Q) in Btuh and the
(RRF). With this relative rating factor, the water t e m p e r a t u r e s (HWT and CWT) by using the equa-
flow r a t e (L), and the design wet bulb t e m p e r a t u r e tion
(WBT), enter figure 2 to obtain the total initial cost
as in the illustrative example below.

Figure 2. Derivation of total initial cost of cooling tower


6
Example problem: Maintenance Costs

Estimate the total initial cost required to F o r lack of a specific application, m a i n -


cool 200 gpm from 94.8F to 84.8F when the tenance costs may be assumed equal to the power
wet bulb t e m p e r a t u r e is 78F: c o s t s . This assumption is recommended 4 as a good
preliminary estimate.
R = 94.8 - 84.8 = 10F
A = 84.8 - 78 = 6.8F
From figure 1, RRF = 1.5
Additional Power Costs
Enter figure 2 and place a straightedge
between the 78F WBT point and the RR F = 1.5 The pump power for existing heat t r a n s f e r
point. Place a straightedge between the i n t e r - equipment (heat exchangers, etc., exclusive of
section point on the pivot line and the 200 gpm connecting piping) in remodeled s y s t e m s can be
point on the L s c a l e . The cost scale thus reads estimated by the following elementary p r o c e d u r e .
$3,600. This is the approximate initial cost of E s t i m a t e the new head loss as
a complete cooling tower installation (includes
tower, pumps, piping, controls, and, electrical
wiring) to cool 200 gpm from 94.8F to 84.8F Additional head loss for connecting piping m u s t be
when the wet bulb t e m p e r a t u r e is 78F. added to this head l o s s . With the combined new
head l o s s , and an assumed per cent efficiency of
40 to 70, the pump power in kilowatts per hour may
be calculated from the following equation
Fixed Costs

The fixed cost of ownership can now be d e t e r - F o r new heat t r a n s f e r equipment, it will be
mined according to individual accounting p r o c e - n e c e s s a r y to refer to m a n u f a c t u r e r s ' data for the
d u r e . This cost should include such i t e m s as taxes, prediction of head l o s s . The ASHRAE Guide 5 p r o -
depreciation, i n s u r a n c e , and i n t e r e s t . vides g r e a t e r detail on head loss calculations for
an e n t i r e s y s t e m .

Power Costs
Water Treatment
Figure 3 is a nomograph for the determination
of the power r e q u i r e m e n t in kilowatts per hour. The role of water treatment in cooling tower
This r e q u i r e m e n t includes the fan power and pump- operations is an important economic consideration,
ing power attributed to the tower only. The p r e - since equipment maintenance and operation effi-
vailing power costs must be used with these values ciency as well as water savings are dependent upon
to determine a per hour cost-of-operation figure. it. Scale and corrosion problems, which can be
A straightedge is used with this figure following serious in once-through cooling s y s t e m s , are
the same procedure outlined for figure 2. usually accentuated when water is r e c i r c u l a t e d in
The power consumption will not be constant cooling t o w e r s y s t e m s . However, with proper
over a whole year or season. This is due to capa- water t r e a t m e n t , water savings of n e a r l y 99 per
city modulation which is dependent upon the type of cent a r e possible.
control s y s t e m , the type of service, and the weather The cooling tower is designed to evaporate
conditions. For this r e a s o n , it is n e c e s s a r y to water as it is circulated through the t o w e r . This
either c o r r e c t the full load operating hours as evaporation lowers the t e m p e r a t u r e of the r e m a i n -
calculated or given in table 2, p. 11, or to adjust ing circulated water. As the evaporation takes
the power requirement. place, the m i n e r a l salts (present in all water
For estimation p u r p o s e s , the power r e q u i r e - s o u r c e s ) remain in the circulated w a t e r and
ments can be corrected for a particular CWT and i n c r e a s e in concentration. As water is evaporated,
R by using an average wet bulb t e m p e r a t u r e for m a k e - u p water is added to maintain the volume of
the period of operation instead of the design wet circulated water.
bulb t e m p e r a t u r e . With these values the RRF chart The concentration (C) refers to the number of
(figure 1) can be used with the average approach t i m e s that the original minerals in the circulated
(CWT-WBT), and the s a m e procedure can be fol- water a r e concentrated or increased by continuous
lowed in figure 3 as that outlined for figure 2. evaporation. The circulated water volume may
Table 1 l i s t s the average wet bulb t e m p e r a t u r e t h e r e f o r e develop 2, 3, 10, or 20 concentrations of
for some locations in and near Illinois, as well as m i n e r a l s a l t s , depending on the chemical t r e a t -
the n o r m a l design wet bulb t e m p e r a t u r e s . ment design and corresponding operation c r i t e r i a .
7
The first n e c e s s i t y for avoiding excessive down r a t e s a r e wasteful, and efficient operation
concentration of m i n e r a l s in the water is to with- dictates that minimum blowdown be practiced and
draw periodically, or continuously, a portion of the that maximum m i n e r a l s be retained as consistent
circulated water and to dilute the remainder with with e c o n o m y and freedom from s c a l e and
fresh w a t e r . This withdrawal is similar to that corrosion.
p r a c t i c e d in the operation of boilers for steam Chemical t r e a t m e n t is therefore p r i m a r i l y
generation and is called blowdown. Excessive blow- designed to prevent the problems which r e s u l t from

Figure 3. Total power requirement for tower


8
high m i n e r a l concentrations. Either internal or
external t r e a t m e n t or both may be applied. Internal
type t r e a t m e n t s , involving addition of chemicals
including scale and corrosion inhibitors, often
prove to be l e s s expensive than external p r e t r e a t -
ment since the equipment costs are low (less than
$600) and the chemical costs are reasonable.
During evaporation, carbon dioxide (carbonic
acid) is lost to the atmosphere and thereby causes
the circulated water to become more alkaline. In
the presence of calcium h a r d n e s s this causes scale
deposits. To avoid this, the water may be treated
with acid, and because of cost, sulfuric acid is
usually specified.
Other methods of t r e a t m e n t are designed to
reduce or remove the h a r d n e s s in the make-up
water. The two most generally used are external
softening methods, the cold lime softening p r o c e s s
and the sodium zeolite softening p r o c e s s . These
a r e discussed in the third section, p. 15. Others
may be competitive in effectiveness and in cost.
The d i r e c t acid application (along with scale
and corrosion inhibitors) as an internal treatment
preferably requires proportioning equipment for
controlled application of the chemicals to the m a k e -
up water. The cost of t r e a t m e n t in cents per 1000
gallons of make-up water (MU) may be calculated
from the following formula, where A is the alka-
linity (as CaCO 3 ) of the m a k e - u p water:

Concentrations
Figure 4. Decrease of operating cost with increasing
Assuming proper scale and corrosion p r e - mineral concentration for circulation rates of 200 gpm
vention t r e a t m e n t , the maximum cooling tower con- (A) and 1000 gpm (B)
centration (C) is usually limited bythe calcium and
sulfate contents in the circulated water. These Example 1:
limits a r e dictated by the solubility of calcium
sulfate. Since hardness (H) is related to the calcium In figure 4a, a 10F range with a 94.8F
concentration and is also a reasonable empirical hot water t e m p e r a t u r e , a 200 gpm circulation
m e a s u r e of the "effective" sulfate concentration in r a t e , and a cost of 15 cents per 1000 gallons
a c i d - t r e a t e d make-up w a t e r s , this readily avail- were a s s u m e d . Using the derived make-up
able p a r a m e t e r can be employed in the following r e q u i r e m e n t s , the water cost per hour is indi-
equation for estimating the maximum p e r m i s s i b l e cated by the dashed line. With internal acid
concentration ratio (C) for m i n e r a l s in the c i r c u - t r e a t m e n t and an assumed alkalinity of 300
lating water to the m i n e r a l s in the make-up water. ppm in the make-up water, the estimated cost
The equation is of chemicals per hour from the t r e a t m e n t
cost equation is indicated by the solid line.
The combined cost is 4.3 cents per hour at
C = 10.
In o r d e r to demonstrate savings in water and By way of comparison for the same heat
chemical costs by maintaining high concentration load and hot water t e m p e r a t u r e , and a water
ratios in the circulating water, graphical examples supply t e m p e r a t u r e of 60F at a cost of 15
are provided in figures 4a and 4b. The make-up in cents per 1000 gallons , the once-through water
gallons per hour for selected concentration ratios cost would be $1.80 per hour without water
can be obtained from figure 5, p. 10. treatment.
9
Figure 5. Make-up water requirements for varying mineral concentrations
10
Example 2: ing hours accordingly. This can be accomplished
by converting to an equivalent full load b a s i s . For
In figure 4b, a 10F range with a 94.8F hot example, if it is expected that the heat load to the
water t e m p e r a t u r e , a 1000 gpm circulation tower will be a certain percentage of full load c a -
r a t e , and a water cost of 5 cents per 1000 pacity for a predetermined period, the number of
gallons were assumed. For the derived m a k e - equivalent full load hours is the ratio of the expect-
up r e q u i r e m e n t s , the water costs a r e shown ed load to the full load capacity times the number
by the dashed line. For a m a k e - u p water with of hours in the reduced load period. That is
50 ppm alkalinity, the estimate of cost of
internal acid treatment is shown by the solid equivalent full _ no, of full
line. The combined cost is 9.5 cents per hour load hours load hours
at C = 10.
For the same heat load and hot water
t e m p e r a t u r e , and a water supply t e m p e r a t u r e
of 60F at a cost of 5 cents per 1000 gallons,
the once-through cost would be $3.00 per hour Table 2 lists some equivalent full load operating
without t r e a t m e n t . hours recommended for some typical air condi-
tioning applications. To determine t h e annual
In normal practice where treatment control
m a k e - u p w a t e r costs and chemical t r e a t m e n t
with minimum supervision is not rigid, maintenance
c o s t s , multiply the total number of gallons t i m e s
of 1.5 to 2 concentrations is not uncommon for
the cost per 1000 gallons, thus
s m a l l e r t o w e r s . This practice provides a factor of
m a k e - u p cost =[(gal/hr) (cost/1000 gal)]x hours
safety where costly shut-downs due to failure in
application is a n e c e s s a r y consideration. With
g r e a t e r a s s u r a n c e of proper chemical applications,
Table 2. Typical Equivalent Full Load
3 to 5 concentrations may well be practiced. For
Operating Hours for Air Conditioning *
l a r g e r t o w e r s , concentration of 3 to 4 may be
common for s i m i l a r r e a s o n s , but may well be
increased to obtain the efficiencies indicated in Hours **
figures 4a and 4b by g r e a t e r attention to properly open for
controlled chemical application and blowdown. Application business Chicago St. Louis
For conversion of costs per hour for c h e m i - Barber shops 1280 720 890
cal t r e a t m e n t and for water to an annual b a s i s ,
adjustment must be made in the make-up r e q u i r e - Department s t o r e s 940 610 750
ments for hours of operation and for reduced load
operation. Drug stores 2100 1060 1420

Funeral p a r l o r s 600 330 400


Make-up Water Costs
Offices 1100 720 910
Figure 5 is a nomograph of make-up water
requirements based on a v a r i a b l e dissolved solids Restaurants 2100 930 1300
concentration r a t i o . Make-up is equivalent to blow-
down, windage l o s s , and evaporation l o s s e s . Place Specialty shops 1090 590 720
a straightedge on figure 5 between the appropriate
L and R and m a r k the intersection on the pivot Theaters,
line. Place a straightedge between this point on the neighborhood 900 450 .550
pivot line and the appropriate concentration. Where
the straight line intersects the make-up s c a l e , * From ASHRAE Guide 5 ** Hours between May 15 and October 15
read the r e q u i r e d make-up water in gallons per
hour.
To determine the number of hours of operation Check List
per year, multiply the number of calendar days by
the number of operation hours per day. This n u m - Table 3 m a y be used as a check list for the
ber is applicable only for constant heat dissipation costs involved in the comparison calculations. No
as would be found in some p r o c e s s applications. attempt is made h e r e t o list power, water, interest,
If the heat dissipation r a t e is not expected to be and tax rates as these are variables which each
constant during this period, as in air conditioning user must include in order that the estimate may
applications, it is n e c e s s a r y to modify the o p e r a t - apply specifically to the particular c i r c u m s t a n c e s .

11
Table 3. Cost Sheet
Initial Investment
1. Cost of total installation
2. Other costs (alterations or additions required
to complete the conservation system)
Total Initial Investment (T)
Annual Fixed Costs
1. Amortization and depreciation period (Y y e a r s )
2. Interest r a t e (i)
3. Amortization and depreciation (T/Y)
4. Interest x i x T
5. Taxes
6. Insurance
7. Rent
Total Fixed Costs, 3-7 (Tf)
Annual Operating Costs
1. Power (pump and fan of tower)
2. Maintenance
3. Power (other)
4. Water t r e a t m e n t
5. Make-up water
6. Sewer c h a r g e s
7. Miscellaneous
Total Operating Cost, 1-7 (To)
Annual Fixed and Operating Cost, Tf + To

ESTIMATION OF ONCE-THROUGH
COOLING COSTS

The cost of once-through water cooling may


be obtained by using the estimated initial cost of
the water supply (source and facilities) and d e t e r -
mining the fixed and operating c o s t s according to
the check l i s t in table 3. If purchased water is
used, the applicable c o s t s , both fixed and o p e r a t -
ing, should also be determined.
The quantity of once-through water is depen-
dent upon the heat to be dissipated, the maximum
allowable t e m p e r a t u r e (HWT), and the t e m p e r a -
ture of available water (CWT). The available water
t e m p e r a t u r e can be as low as 50F from shallow
wells or as high as 90F for some surface w a t e r s .
The two limiting t e m p e r a t u r e s indicate the allow-
able t e m p e r a t u r e difference (Range) for once-
through water. The once-through flow rate is t h e r e -
fore equal to 60Q/500(HWT-CWT) in gallons per
hour. This quantity multiplied by the unit cost of
the water, whether purchased or self-supplied,
gives the cost per hour. It is then n e c e s s a r y to
multiply this number by the expected full load
operating hours to determine the total annual op-
erating cost.

Initial Costs, Self-supplied Water


To approximate the cost of a well installation, Figure 6. Total cost of well pump assembly
s t a r t with the flow r a t e determined above which and installation
12
These values are rules-of-thumb for rock wells
Table 4. Well Size Requirements and do not include the cost of pumping equipment.
The well pump assembly and installation cost
Pumping Minimum casing m a y b e estimated from generalized data assembled
r a t e , gpm sizes , inches in figure 6. The pumping head is taken to be the
pump setting from ground surface to the top of the
120 6-8 bowls. These estimates were obtained from a single
300 8-10 vendor. Competitive estimates may be significantly
600 10-12 g r e a t e r or l e s s e r depending on circumstances and
1200 12-14 specifications.
2000 14-16 For surface water supplies, no attempt has
3000 16-18 been made to indicate estimates on costs for s u r -
face water inlets with attendant maintenance p r o -
blems or the cost of pumps for this type of installa-
tion, as these are beyond the scope of this r e p o r t .
will designate the minimum hole and casing size
as indicated in table 4.
Drilling costs for rock wells with casings may Power Costs
then be estimated at $1.50 to $2.00 per inch dia-
m e t e r per foot of depth to 600 feet (including c e - In general, power costs may be estimated
mented casing), and $1.50 to $3.00 per inch d i a m e - from an approximate 0.525 kilowatt r e q u i r e m e n t
t e r per foot at g r e a t e r depths (including l i n e r s ) . per 100 feet of head per 1000 gallons pumped.

DERIVATION OF COST RELATIONSHIPS

Relative Rating Factor approach curves when conditions greatly different


from R R F = 1.0 a r e chosen. The system, t h e r e -
Rating charts for cooling towers are generally fore, is acceptable for conditions close to a RRF
developed from experimental data. The relative of 1.0, but l a r g e r e r r o r s are expected as m o r e
rating factor (figure l ) i s obtained from an average adverse conditions p r e v a i l .
of a number of cross flow and counter flow rating
charts developed for a constant air flow r a t e .
Figure 1 was developed l by superimposing the
various rating charts for different towers upon
one another so that the a r b i t r a r y standard condi-
tions of 10F r a n g e , 10F approach to a 70F wet bulb
t e m p e r a t u r e coincided, and this point was a r b i -
t r a r i l y assigned a rating factor of 1.0. Other con-
ditions of range and approach were then assigned
relative values (RRF) w h i c h are fractions or
multiples of t h i s . These rating factors have the
dimensions of square feet per gallons per minute
(sq ft/gpm). In this instance the relative rating Figure 7. Deviation of approach curves for varying
factor has no relationship to the physical size of a tower types
tower; it is a number for comparison only. To use F o r simplification, o n l y the 70F wet bulb
this number with the dimensions of sq ft/gpm to t e m p e r a t u r e chart is used, and for other wet bulb
determine the plan size would yield a tower (de- conditions, standard wet bulb correction factors
pending on the packing) from 2 to 5 times too l a r g e . have been incorporated in the nomographs. Wet
Figure 7 i l l u s t r a t e s the general trend of two bulb correction factors have been used frequently
10F approach curves when compared with the curve to simplify cooling tower rating p r o c e d u r e s and
plotted from figure 1. All the 10F approach curves preliminary estimates.
p a s s through the point R R F = l.0 and R = 10F. For The possible net e r r o r which is introduced by
each different tower, the 10F approach curve will both the relative rating factor and the wet bulb
rotate about this point as shown. The inherent e r r o r correction factors does not exceed 9 per cent in
within this method of reducing all towers to one set the range of 70 to 80F WBT and an RRF between
of performance curves l i e s in the deviation of the 0.6 and 1.7.
13
Tower Costs e s t i m a t e s and should not be used for other m o r e
refined p u r p o s e s . For a generalized p r e l i m i n a r y
Because equipment pricing is not standard, e s t i m a t e , however, this can b e c o n s i d e r e d
and reflects business judgment, deviations from acceptable.
the values obtained from these charts m u s t be
anticipated. The tower cost is r e p r e s e n t e d by a
faired curve through the scatter of points shown
in figure 8. This scatter indicates a possible e r r o r Installation
of - 24 per cent. If an additional 9 per cent i n a c -
curacy for the method of reduction is considered, The complete tower installation costs w e r e
a total e r r o r of approximately 33 per cent in the a r r i v e d at by using the customary " r u l e s - o f - t h u m b "
tower cost is possible. The inherent e r r o r s of which are recommended for estimates by m a n u -
" r u l e s - o f - t h u m b " for the total installation costs f a c t u r e r s . Two types of towers are involved. The
will add to, or compensate for, some of this s m a l l e r towers (10-400 gpm) are generally fully
inaccuracy. packaged for delivery and priced fob factory and
This evaluation of dependability clearly indi- the l a r g e r (400-10,000 gpm) are assembled on
cates that the derived costs must be used only as site and priced as site as sembled. This is indicated

Figure 8. Point scatter of tower cost curve


14
b y the d i s c o n t i n u i t y i n t h e t o w e r c o s t c u r v e (figure p e r 1000 g a l l o n s , is 4 x ( A / 1 2 0 ) , or 0 . 0 3 3 A .
8 ) . T h e i n s t a l l a t i o n c o s t s ( f i g u r e s 2 and 8) h a v e The scale inhibitor cost is based on an example
t h e r e f o r e been e s t i m a t e d as a r u l e - o f - t h u m b to be w h e r e s o d i u m p o l y p h o s p h a t e is m a i n t a i n e d at 6
2 - 1 / 2 t i m e s the c o s t o f the s m a l l e r ( 1 0 - 4 0 0 g p m ) p p m a n d s o d i u m l i g n o s u l f o n a t e at 18 p p m in the
t o w e r s and 1-1/2 t i m e s t h e c o s t o f t h e l a r g e r (400- c i r c u l a t i n g w a t e r . T h i s r e q u i r e s 0.05 pound o f
10,000 g p m ) t o w e r s , w h e r e c i r c u l a t i o n r a t e s (L) a r e s o d i u m t r i p o l y p h o s p h a t e ( 1 3 ¢ / l b ) and 0.15 pound
a t 9 0 F H W T , 8 0 F C W T , and 7 0 F W B T . o f s o d i u m l i g n o s u l f o n a t e ( 1 5 . 6 ¢ / l b ) p e r 1000 g a l -
lons of c i r c u l a t i n g w a t e r . T h e c o s t of t h e m a k e - u p
w a t e r r e q u i r e m e n t s i n c e n t s p e r 1000 g a l l o n s i s
therefore
Chemical Treatment

C o s t s for o n l y t h r e e c o m m o n m e t h o d s o f w a t e r
t r e a t m e n t were considered. These include costs
The corrosion inhibitor* cost is similarly
o f t r e a t m e n t for m a k e - u p w a t e r and s u p p l e m e n t a r y
b a s e d o n m a i n t a i n i n g 300 p p m C r O 4 i n the c i r c u -
t r e a t m e n t of circulating water. Cost derivations
l a t i n g w a t e r , and i s a p p l i e d a s N a 2 C r 2 O 7 • 2 H 2 O
w e r e m a d e in a m a n n e r p e r m i t t i n g all to be ex-
(22¢/lb), or
p r e s s e d in t e r m s of c e n t s p e r 1000 g a l l o n s of
make-up water.
As shown in the t a b l e of n o m e n c l a t u r e for
water analysis, concentration of all ingredients
used is e x p r e s s e d in equivalents of calcium c a r - T h e c o m b i n e d s c a l e and c o r r o s i o n i n h i b i t o r
b o n a t e e x c e p t t h a t for c a r b o n d i o x i d e . T h e c o s t o f cost is then (3/C) + (71/C) or 7 4 / C , in cents per
c h e m i c a l s m a y vary depending on the source of 1000 g a l l o n s m a k e - u p , and t h e t o t a l t r e a t m e n t
s u p p l y and the q u a n t i t y p u r c h a s e d . U s u a l l y t h e s e c o s t b y t h i s m e t h o d i s t h e r e f o r e 0.033A + ( 7 4 / C ) .
c o s t s w i l l b e i n the r a n g e i n d i c a t e d i n t a b l e 5 , With acid t r e a t m e n t , a s i m p l i f i e d r e l a t i o n s h i p
which gives the costs of c h e m i c a l s used in the for e s t i m a t i n g m a x i m u m c o n c e n t r a t i o n o f m i n e r a l s
in cooling w a t e r to avoid calcium sulfate s c a l e is
f o r m u l a s i n the o p p o s i t e c o l u m n .
C = 2 4 0 0 / H . Using D e n m a n ' s data7 the m a x i m u m
c o n c e n t r a t i o n w a s c a l c u l a t e d for a n u m b e r o f r e p -
T a b l e 5. C o s t of C h e m i c a l s r e s e n t a t i v e Illinois w a t e r s t r e a t e d with sulfuric
a c i d , and the a b o v e e q u a t i o n p r o v i d e d c o m p a r a b l e
Cost used Range* r e s u l t s for the 1 0 4 F d a t a .
The choice of i n t e r n a l v e r s u s e x t e r n a l t r e a t -
Sulfuric acid, 66° B a u m e ' 4¢/lb 3 to 5¢/lb m e n t d e p e n d s o n the m a n y f a c t o r s w h i c h s h o u l d b e
Scale and c o r r o s i o n 15¢/lb 15 to 25¢/lb studied by competent e x p e r t s before r e a c h i n g a
inhibitors decision based largely on economics. These factors
Salt $2/100 lb are:
Hydrated lime $1.10/100 lb
1) The w a t e r a n a l y s i s , p a r t i c u l a r l y the h a r d -
n e s s and a l k a l i n i t y
* Under circumstances where chemical costs include services in
the form of periodic analyses or consultations, these may be as 2) T h e a v a i l a b i l i t y and c o s t o f w a t e r
much as twice the range indicated. 3) T h e s i z e of t h e s y s t e m
4) The r e l a t i v e c l e a n l i n e s s of the s y s t e m
NOMENCLATURE, WATER ANALYSIS desired
5) The availability of s p a c e , capable o p e r a t -
A A l k a l i n i t y (as C a C O 3 ) , r a w w a t e r ing p e r s o n n e l , and t e c h n i c a l a s s i s t a n c e .
A' A l k a l i n i t y (as C a C O 3 ) , a f t e r l i m e t r e a t m e n t *
E x t e r n a l c o l d p r o c e s s softening b y l i m e t r e a t -
CO2 C a r b o n D i o x i d e (as C O 2 )
m e n t g e n e r a l l y r e d u c e s the h a r d n e s s to about 80-
Ca C a l c i u m (as C a C O 3 ) , r a w w a t e r
100 p p m , and i n c l u d e s a s u b s e q u e n t a c i d a p p l i c a t i o n
Mg M a g n e s i u m (as C a C O 3 ) , r a w w a t e r
for s t a b i l i z a t i o n and a c o r r o s i o n i n h i b i t o r .
H H a r d n e s s (as C a C O 3 ) , r a w w a t e r
H' H a r d n e s s (as C a C O 3 ) , a f t e r l i m e t r e a t m e n t *
*Since chemicals of possible or definite toxicity are often used for
* Estimates from equipment manufacturer corrosion inhibition in the water treatments, definite preventative
measures shouldbe taken to insure that the cooling tower water can
not be permitted to possibly mix with or be siphoned into the drink-
ing water system. Make-up water should be introduced only at the
F o r the i n t e r n a l t r e a t m e n t b y a p p l i c a t i o n o f tower basin and should be applied at least twice the effective pipe
opening above the maximum possible water level or the overflow
a c i d , the a c i d c o s t is b a s e d on 1 pound 66° B a u m e ' pipe in order to prevent back siphonage6. Disposal of wastes or
a c i d ( 4 ¢ / l b ) p e r 1000 g a l l o n s m a k e - u p r e q u i r e d t o blowdown should be in accordance with regulations of local health
n e u t r a l i z e 120 p p m a l k a l i n i t y . T h i s c o s t , i n c e n t s agencies and the State Public Health Department.

15
F o r the external lime t r e a t m e n t p r o c e s s for
the m a k e - u p water, the usual r e q u i r e m e n t s are
based onhydrated lime (1.1¢/lb) and on the formu-
la, 0.007 (A + 50) + 0.015(CO 2 ) in pounds per 1000
gallons. Therefore the lime t r e a t m e n t cost is equal
to

Unusual waters with excessive non-carbonate hard-


ness (H g r e a t e r than A), r e q u i r e supplementary
treatment.
To prevent the development of causticity in the
circulating water, the acid r e q u i r e m e n t s (4¢/lb) for
the m a k e - u p following lime t r e a t m e n t are 0.033A'.
The total treatment cost by this method, including
the need for scale and c o r r o s i o n inhibitors in the Figure 9. Water treatment equipment costs
circulating water, will then be
The blowdown in gallons per hour required to s a -
tisfy a given concentration ratio m a y b e estimated
F o r estimating the maximum concentration as a fraction of the evaporation l o s s . In equation
of m i n e r a l s when this t r e a t m e n t is used, the hard- form,
ness of the treated water m u s t be used in the p e r -
m i s s i b l e concentratton equation, p. 9, as follows:
C = 2400/H' Summing both the evaporation loss and the blow-
Although external h a r d n e s s removal by sodium down, the make-up in gallons per hour is equal to
zeolite softening m a y b e employed without applica-
tion of a corrosion inhibitor, m o r e complete inhi-
bition is usually considered n e c e s s a r y . F i g u r e 5 is a nomograph of this equation. Drift or
F o r the external zeolite softening p r o c e s s the windage loss was assumed to be part of the blow-
salt r e q u i r e m e n t s (2¢/lb) a r e based on 1 pound down and consequently does not appear in the equa-
salt required per 2000 grains h a r d n e s s (H), where tion. The general limit on drift loss is usually
1 g r a i n - p e r - g a l l o n hardness is 17 ppm. The salt given as 0.1 per cent of the circulation r a t e with a
cost then is equal to maximum allowable of 0.2 per cent, but these limits
a r e exceeded in some tower designs.
The m a k e - u p given in figure 5 is based on a
Therefore the total cost of zeolite t r e a t m e n t constant heat load to the tower. This is generally
in cents per 1000 gallons m a k e - u p is the salt cost not the case in air conditioning, as well as in
plus the inhibitor cost, or some p r o c e s s work, and hence the m a k e - u p for a
full season derived in the foregoing manner will
be in e r r o r unless c o r r e c t e d by the equivalent full
load method described in the first section.
In the case of zeolite softening, the maximum
The initial fill of water has been neglected in
concentration is limited by the alkalinity of the
this calculation as it is generally a minor fraction
circulating water. An a r b i t r a r y maximum limit
of the operating cost if the system is drained and
of 1200 ppm is suggested; however lower values
refilled only once a y e a r .
may be required to provide longer tower life by
avoiding disintegration of wood by high alkalinity.
The maximum concentration (C) is therefore
1200/A. Power
F i g u r e 9 i l l u s t r a t e s typical equipment costs
for external t r e a t m e n t . The zeolite equipment The power r e q u i r e m e n t s (figure 3) were d e -
cost is based on water h a r d n e s s of 340 ppm and rived from the fan and pump power values cited by
daily r e g e n e r a t i o n . Pfeiffer. 8 These were assumed to be applicable at
the conditions of 90F HWT, 80F CWT, and 70F
WBT. Other conditions of approach, r a n g e , and wet
bulb t e m p e r a t u r e s consequently require a different
Make-up amount of power, which has been derived in the
nomograph through incorporation of the wet bulb
Make-up (MU) water r e q u i r e m e n t s (figure 5) c o r r e c t i o n factor and the relative rating factor.
were derived by assuming an evaporation loss in The power r e q u i r e m e n t s indicated by figure 3 a r e
gallons per hour of 1 per cent per 10F r a n g e , or comparable (within 35 per cent) to those indicated
60 x 0.001 x R x L by o t h e r s . 4 , 9 , 1 0
16
OTHER CONSIDERATIONS

Other cooling methods may be desirable for tent water for use as m a k e - u p for cooling t o w e r s .
relatively small heat dissipation r a t e s (less than This method not only limits the cost of water to
1,000,000 Btuh). For these r a t e s refrigeration cost of storage, but also reduces the cost of water
s e r v i c e or other similar condensing s e r v i c e , a i r - treatment.
cooled condensers or evaporative condensers, can Multiple r e u s e either within an industry or
s o m e t i m e s provide competitive cost advantages to between industries is not an uncommon p r a c t i c e .
cooling t o w e r s . The scope of this r e p o r t has not Side-channel or flood-water collection basins
permitted consideration of this type of equipment. a r e also used for storage of n e c e s s a r y m a k e - u p
Information is available from the ASHRAE Guide. 5 water.
Where land is available at reasonable cost, Sewage t r e a t m e n t plant effluents are available
pond cooling can also be used for air conditioning sources of low quality cooling water where potable
as well as some p r o c e s s cooling p u r p o s e s . water is at a p r e m i u m .
Other conservation methods may be considered These few examples suggest that the methods
a l s o . Water used for cooling can be conserved by and p r a c t i c e s of water conservation canbe adapted
many different methods, either with or without the and expanded by positive efforts through evaluation
use of a cooling tower. The collection and storage and design. In each c a s e , an element of " f r e e "
of precipitation from roofs and parking areas can water is p r e s e n t which limits costs to storage and
often provide an ample supply of low m i n e r a l con- transportation.

SUMMARY

This r e p o r t has been an evaluation of costs of is d e s i r e d for the equipment to be cooled and the
water used for heat dissipation with particular heat dissipation equipment. For this reason, s p e c i -
emphasis on simplification of cooling tower e s t i - fic cooling needs should be subjected to c o m p r e -
m a t e s . Because of the complex nature of evapora- hensive study by a competent engineer.
tive cooling methods, these simplifications should If the costs of both once-through and c o n s e r -
be used only for p r e l i m i n a r y comparison of p o s - vation equipment a r e within about 30 per cent of
sible economic advantages in water conservation. each other, a thorough investigation should be ad-
In the refrigeration industry, evaporative or visable. The future availability of water is also a
air-cooled condensers a r e often economically consideration that should not be overlooked.
competitive to cooling towers in the smaller sizes Economical justification f o r conservation
(10-100 tons). m e a s u r e s stimulates wise use of the water r e -
For maximum economy, optimum size match source and avoids regulation and r e s t r i c t i o n .

17
REFERENCES

1 The Marley Company. Test your tower. Technical Bulletin No.


R - 6 1 - P - 8 , Kansas City, Missouri, 1961.

2 Cooling Tower Institute. Nomenclature for industrial water-cooling


t o w e r s . CTI Bulletin NCL-109, January 16, 1958.

3 Fluor Products Company. Evaluated weather data for cooling equip-


ment design, 1958.

4 K. K. McKelvey and Maxey Brooke. The industrial cooling tower.


Elsevier Publishing Company, A m s t e r d a m , 1959.

5 American Society of Heating, Refrigeration and Air Conditioning


E n g i n e e r s . Guide. p. 719, 1960.

6 Illinois state plumbing code. Department of Public Health, 1959.

7 W. L. Denman. Maximum r e - u s e of cooling water. Industrial Engi-


neering and Chemistry, v. 53, p. 817, 1961.

8 E. L. Pfeiffer. What size cooling t o w e r s ? Chemical Engineering,


v. 56(4), p. 98, April 1949.

9 G. M. Anderson. Cooling tower specifications and design. ASME Paper


No. 5 9 - P E T - 6 , June 1959.

10 F. J. Lockhart, J. M. Whitesell, and A. C. Catland, J r . Cooling towers


for the power industry. Paper presented at 17th annual meeting,
American Power Conference, March 30, 1955.

18

You might also like