SCHEDULE PLAN

No. : 00231/RFQ/DIP-IPPS/III/2019
NAMA PEKERJAAN : PEKERJAAN PENGECORAN KANTOR BARU IPPS
LOKASI : Sepinggan, PT. Intraco Penta Prima Servis

RENCANA WAKTU PELAKSANAAN


BOBOT MINGGU KE #1 MINGGU KE #2 MINGGU KE #3
NO URAIAN PEKERJAAN VOLUME SAT DUR KET.
% D#1 D#2 D#3 D#4 D#5 D#6 D#7 D#8 D#9 D#10 D#11 D#12 D#13 D#14 D#15 D#16 D#17 D#18 D#19 D#20
1 PEKERJAAN PERSIAPAN
100%
Mobilisasi dan Demobilisasi 1.00 LS 0.71% 20 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Pekerjaan bouwplank, marking dan levelling
Procurement, Purchasing 90%

2 PEKERJAAN GALIAN/ BONGKARAN 358.15 M2 5.42% 5 1.08% 1.08% 1.08% 1.08% 1.08% 80%
Pekerjaan Bongkar/ Galian
Pembuangan sisa bongkaran 70%

3 PEKERJAAN PENGECORAN JEMBATAN 60%


SPESIFIKASI MATERIAL :
Ready Mix K300, Tebal 350 mm 26.30 M3 19.36% 2 9.68% 9.68% 50%
Besi Beton D-14mm Double Layer (pembesian lantai) 2,479.50 KG 9.45% 5 1.89% 1.89% 1.89% 1.89% 1.89%
Besi Beton 16mm (pembesian cakar ayam dan coloum) 1,254.00 KG 4.78% 5 0.96% 0.96% 0.96% 0.96% 0.96% 40%

4 PEKERJAAN PENGECORAN HALAMAN 30%


SPESIFIKASI MATERIAL
Ready Mix K250, tebal 200 mm 71.63 M3 51.29% 5 10.26% 10.26% 10.26% 10.26% 10.26% 20%
Besi Beton M12 (pembesian lantai) 2,224.50 KG 8.48% 4 2.12% 2.12% 2.12% 2.12%
10%
5 PEKERJAAN PEMBERSIHAN
Pekerjaan Pembersihan area 1.00 LS 0.50% 2 0.25% 0.25%
0%
6 % RENCANA MINGGUAN 100.00% 48 0.04% 0.04% 3.97% 3.97% 3.97% 3.97% 3.97% 9.72% 9.72% 2.16% 2.16% 2.16% 2.16% 10.29% 10.29% 10.29% 10.29% 10.29% 0.29% 0.29%
7 % KUMULATIF RENCANA MINGGUAN 0.04% 0.07% 4.04% 8.00% 11.97% 15.93% 19.90% 29.62% 39.33% 41.49% 43.64% 45.80% 47.96% 58.25% 68.54% 78.84% 89.13% 99.43% 99.71% 100.00%