Professional Documents
Culture Documents
Chapter 5 - Allocating Resources PDF
Chapter 5 - Allocating Resources PDF
Project
Management
Chapter 6
Allocating
Resources to the
Project
BY : SITI FATMA ABD KARIM
Another References:
Chapter 8:
Scheduling
Resources and
Costs
Chapter 9:
Reducing
Project Duration
This chapter addresses methods available
to project managers for dealing with
resource utilization and availability
through resource leveling and resource-
constrained scheduling. Up to now the
start and sequence of activities has been
based solely on technical or logical
considerations.
Overview of Resources Scheduling Problem
How much
flexibility do we
have in using
resources?
Physical Constraints
Materials
Equipment is
Equipment usually presented
by type, size, and
quantity.
Equipment is often
overlooked as a
constraint.
Example
Equipment
Product – raw
material must enough
to produce the
targeted amount of
product
People / Manpower
Classification of a Scheduling Problem
Yes No
How to determine?
“If the critical path is delayed, will
resources be added to get back on
schedule?”
Resource Allocation Methods
Risk Assumptions
Limiting Assumptions
– Activities with the
– Splitting activities is
most slack pose the
1 not allowed—once
least risk.
an activity is start,
it is carried to – Reduction of
completion. flexibility does not
increase risk.
– Level of resources
used for an activity – The nature of an
cannot be changed. activity (easy,
complex) doesn’t
increase risk.
Resource Allocation Methods
Time-Constrained Projects: 2
Smoothing Resource Demand
The smoothed
resource loading
chart shows the
results of delaying the
fence and walls
activity.
Resource Allocation Methods
Advantages Disadvantages
Resource Demand
Leveling Techniques
for Time-Constrained
Projects
Resource Allocation Methods
Resource-Constrained Projects
3
– Resources are limited in quantity or availability.
– Activities are scheduled using heuristics
(rules-of-thumb) that focus on:
1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
– The parallel method is used to apply heuristics
• An iterative process starting at the first time period
of the project and scheduling period-by-period the start of
any activities using the three priority rules.
Resource-Constrained Schedule through Period 2–3
FIGURE 8.4
Resource-Constrained Schedule through Period 2–3
FIGURE 8.5
Resource-Constrained Schedule through Period 5-6
Condition Impact
Limited Resources Schedule Reduces slack, reduces
flexibility by using slack to
ensure delay is minimized, and
increases the number of
critical and near-critical
activities.
Individual opinion/
answer
Assigning Project Work
There is a natural
Match – Requirements with tendency to assign the
Qualification and Experience best people the most
difficult tasks.
Project Manager
1 2 3 Unforeseen
Time to market Adaptability
delays
• Due to global • Not only on • Reducing project
competition and innovation but also time occurs when
high speed adaptability – unforeseen delays –
technological quickly adapt with (target to complete
advances new challenges early so that when
• For example : • For example : ESSO unforeseen delays
electronics industry become PETRON happen, losses
(6 months delay – (re-branding) occur still
cause loss of market acceptable
share 35%. • For Example : Delay
that occur due to
equipment
breakdown /
adverse weather
Rationale for Reducing Project Duration
4 5
Incentive contracts “Imposed deadlines”
When When
Resources are Resources are
not constrained constrained
1. Adding Resources
3. Scheduling Overtime
The easiest way to add more labour to a project is not to add
more people, but to schedule overtime. If a team works 50 hours
a week instead of 40, it might accomplish 20 percent more.
Advantages Disadvantages
2. Fast-Tracking
For example,
Instead of waiting for the final design to be approved, manufacturing engineers
can begin building the production line as soon as key specifications have been
established.
3. Critical-Chain
For example, the new car will average only 25 mpg instead of 30, or
the software product will have fewer features than originally
planned. While scaling back the scope of the project can lead to big
savings in both time and money, it may come at a cost of reducing
the value of the project.
5. Compromise Quality
2. Find total
1. Find total direct
indirect costs for
costs for selected
selected project
project durations.
durations.
Purpose: The graph is then used to compare additional cost alternatives for benefits.
Determining the Activities to Shorten
What is the
difficult task in What is the How to select
What manager
constructing central the critical
do?
cost-duration concern? activities ?
graph?
Normal Crash
Crash cost
time time
Shortening an
Represents low- activity is called
cost, realistic, crashing. The The direct cost
efficient shortest for completing
methods for possible time an an activity in its
completing the activity can crash time is
activity under realistically be called crash
normal completed in is cost.
conditions. called its crash
time.
Hypothetical Cost–duration Graph For An
Activity
The crash time
for the activity
is five time
units and $800.
The
corresponding
cost is $400.
The normal
time for the
activity is 10
time units
Hypothetical Cost–duration Graph For An
Activity