CHB Computations

The document provides specifications for concrete hollow blocks (CHB), including quantities of cement and sand needed for different block sizes, reinforcing bar lengths for vertical and horizontal reinforcement, and quantities of wire mesh needed per square meter for different spacing configurations. It includes tables with dimensions, materials, and spacing parameters for hollow blocks of varying sizes in a greenfield park construction project.

Uploaded by

Mario Trinidad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as ODS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
336 views129 pages

CHB Computations

The document provides specifications for concrete hollow blocks (CHB), including quantities of cement and sand needed for different block sizes, reinforcing bar lengths for vertical and horizontal reinforcement, and quantities of wire mesh needed per square meter for different spacing configurations. It includes tables with dimensions, materials, and spacing parameters for hollow blocks of varying sizes in a greenfield park construction project.

Uploaded by

Mario Trinidad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as ODS, PDF, TXT or read online on Scribd

QUANTITY OF CEMENT AND SAND FOR C

DIMENSION

QUANTITY OF Length (m.) Width (m.)


Size of CHB CHB (pcs.)
35 1.4 2

10cm x 20 cm x 40cm

TOTAL 35

17.5 1.4 1

15cm x 20cm x 40cm

TOTAL 17.5

52.5 3 1.4

20cm x 20cm x 40cm

TOTAL 52.5

PROJECT TITLE: greenfield park at novaliches q


NOTE: FILL ONLY ON THE SHADED RED COLU
"QUITTERS
OF CEMENT AND SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C”
AREA (sq.m.)
Cement Cement Cement
Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag)

2.8 2.2176 0.1218 1.4616 0.1218 1.1032

2.8 2.2176 0.1218 1.4616 0.1218 1.1032

1.4 2.1364 0.11816 1.4252 0.11816 1.0682

1.4 2.1364 0.11816 1.4252 0.11816 1.0682

4.2 9.492 0.525 6.3 0.525 4.725

4.2 9.492 0.525 6.3 0.525 4.725

park at novaliches qc
ON THE SHADED RED COLUMN FOR THE DIMENSION OF THE WALL.
"QUITTERS NEVER WIN
"
ER LENGTH OF REINFORCING BAR
D AND CEMENT
Vertical Reinforcement
Class “C” Class “D”

Cement
Sand (cu.m.) Sand (cu.m.) Length of Bars in Meters
(40kg/bag)
SPACING
0.1218 0.9184 0.1218 8.204

0.40 m.

0.1218 0.9184 0.1218 TOTAL LENGTH 4

0.11816 0.8862 0.11816 4.102

0.40 m.

0.11816 0.8862 0.11816 TOTAL LENGTH 4.102

0.525 3.9396 0.525 12.306

0.40 m.

0.525 3.9396 0.525 TOTAL LENGTH 12.306

F THE WALL.
F REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters Length in Meters SPACING


Length in Meters
Three-Layer Four-Layer
Two-Layer Spacing
Spacing Spacing
9.24 6.02 4.816

0.60 m.

9.24 6.02 4.816

13.86 3.01 2.408

0.60 m.

13.86 3.01 2.408

13.86 9.03 7.224

0.60 m.

13.86 9.03 7.224


LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters
Length of Bars in Length in Meters
Three-Layer
Meters Two-Layer Spacing
Spacing
5.964 9.24 6.02

5.964 9.24 6.02

2.982 4.62 3.01

2.982 4.62 3.01

8.946 13.86 9.03

8.946 13.86 9.03


HB IN METER LENGTH OF REINFORCING BARS FOR CHB I

nforcement Vertical Reinforcement Horizontal Reinfor


SPACING Length in Meters
Length in Meters Length of Bars in
Two-Layer
Four-Layer Spacing Meters
Spacing
4.816 4.48 9.24

0.80 m.

4.816 4.48 9.24

2.408 2.24 4.62

0.80 m.

2.408 2.24 4.62

7.224 6.72 13.86

0.80 m.

7.224 6.72 13.86


NG BARS FOR CHB IN METER NO.16 G.I. WIRE FOR CHB RE

Horizontal Reinforcement TWO-LAYER Horizontal Spacing

Length in Meters
Length in Meters
Three-Layer VERTICAL 25 cm. 30 cm.
Four-Layer Spacing
Spacing SPACING
6.02 4.816 0.1512 0.182

0.40 m

Engr. Marcon M. Orosco


6.02 4.816 0.1512 0.182

3.01 2.408 0.0756 0.091

0.40 m

3.01 2.408 0.0756 0.091

9.03 7.224 0.2268 0.273

0.40 m

9.03 7.224 0.2268 0.273


RE FOR CHB REINFORCEMENT PER SQUARE METER

Horizontal Spacing TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal S

40 cm VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm.


SPACING SPACING
0.2408 0.1092 0.1316 0.1764 0.0672

0.40 m 0.40 m

0.2408 0.1092 0.1316 0.1764 0.0672

0.1204 0.0546 0.0658 0.0882 0.0336

0.40 m 0.40 m

0.1204 0.0546 0.0658 0.0882 0.0336

0.3612 0.1638 0.1974 0.2646 0.1008

0.40 m 0.40 m

0.3612 0.1638 0.1974 0.2646 0.1008


NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE M

OUR-LAYER Horizontal Spacing TWO-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL


SPACING SPACING
0.0812 0.1092 0.1008 0.1232 0.1596

0.60 m 0.60 m

0.0812 0.1092 0.1008 0.1232 0.1596

0.0406 0.0546 0.0504 0.0616 0.0798

0.60 m 0.60 m

0.0406 0.0546 0.0504 0.0616 0.0798

0.1218 0.1638 0.1512 0.1848 0.2394

0.60 m 0.60 m

0.1218 0.1638 0.1512 0.1848 0.2394


T PER SQUARE METER NO.16

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

25 cm. 30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.0728 0.0896 0.1176 0.056 0.0672 0.0896

0.60 m

0.0728 0.0896 0.1176 0.056 0.0672 0.0896

0.0364 0.0448 0.0588 0.028 0.0336 0.0448

0.60 m

0.0364 0.0448 0.0588 0.028 0.0336 0.0448

0.1092 0.1344 0.1764 0.084 0.1008 0.1344

0.60 m

0.1092 0.1344 0.1764 0.084 0.1008 0.1344


NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.0756 0.0924 0.1232 0.056 0.0672

0.80 m. 0.80 m.

0.0756 0.0924 0.1232 0.056 0.0672

0.0378 0.0462 0.0616 0.028 0.0336

0.80 m. 0.80 m.

0.0378 0.0462 0.0616 0.028 0.0336

0.1134 0.1386 0.1848 0.084 0.1008

0.80 m. 0.80 m.

0.1134 0.1386 0.1848 0.084 0.1008


SQUARE METER

RHorizontal Spacing FOUR-LAYER Horizontal Spacing

40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.0896 0.042 0.0504 0.0672

0.80 m.

0.0896 0.042 0.0504 0.0672

0.0448 0.021 0.0252 0.0336

0.80 m.

0.0448 0.021 0.0252 0.0336

0.1344 0.063 0.0756 0.1008

0.80 m.

0.1344 0.063 0.0756 0.1008


QUANTITY OF CEMENT AND SAND FOR CH

DIMENSION
AREA (sq.m.)
QUANTITY OF Length (m.) Width (m.)
Size of CHB CHB (pcs.)
150 4 3 12

10cm x 20 cm x 40cm

TOTAL 150 12

15cm x 20cm x 40cm

TOTAL

20cm x 20cm x 40cm

TOTAL

NOTE: FILL ONLY ON THE SHADED RED COLU


"QUITTERS
SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C” Class “D”

Cement Cement Cement Cement


Sand (cu.m.) Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag) (40kg/bag)

9.504 0.522 6.264 0.522 4.728 0.522 3.936

9.504 0.522 6.264 0.522 4.728 0.522 3.936

D RED COLUMN FOR THE DIMENSION OF THE WALL.


QUITTERS NEVER WIN
"
LENGTH OF REINFORCING BARS FOR CHB IN ME

Vertical Reinforcement Horizontal Reinforcem


Class “D”

Length in Meters
Sand (cu.m.) Length of Bars in Meters
Two-Layer Spacing
SPACING
0.522 35.16 39.6

0.40 m.

0.522 TOTAL LENGTH 4 39.6

0.40 m.

TOTAL LENGTH

0.40 m.

TOTAL LENGTH
ARS FOR CHB IN METER LENGTH OF REINFORCING BA

Horizontal Reinforcement Vertical Reinforcement

Length in Meters Length in Meters SPACING


Length of Bars in
Three-Layer Four-Layer
Meters
Spacing Spacing
25.8 20.64 25.56

0.60 m.

25.8 20.64 25.56

0.60 m.

0.60 m.
H OF REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters SPACING


Length in Meters Length in Meters
Three-Layer
Two-Layer Spacing Four-Layer Spacing
Spacing
39.6 25.8 20.64

0.80 m.

39.6 25.8 20.64

0.80 m.

0.80 m.
LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters Length in Meters


Length of Bars in
Two-Layer Three-Layer
Meters
Spacing Spacing
19.2 39.6 25.8

19.2 39.6 25.8


HB IN METER NO.16 G.I. WIRE FOR CHB REINFORCEMENT

inforcement TWO-LAYER Horizontal Spacing

Length in Meters
VERTICAL 25 cm. 30 cm. 40 cm
Four-Layer Spacing
SPACING
20.64 0.648 0.78 1.032

0.40 m
Engr. Marcon M. Orosco

20.64 0.648 0.78 1.032

0.40 m

0.40 m
CHB REINFORCEMENT PER SQUARE METER NO.16 G

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.40 m 0.40 m
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

R Horizontal Spacing TWO-LAYER Horizontal Spacing TREE-LAYER Horizontal

40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL 25 cm.


SPACING SPACING
0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.60 m 0.60 m
UARE METER NO.16 G.I. WIR

REE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm VERTICAL


SPACING SPACING
0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.60 m 0.80 m.
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.80 m.
E METER

FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.18 0.216 0.288

0.80 m.

0.18 0.216 0.288

0.80 m.

0.80 m.
QUANTITY OF CEMENT AND SAND FOR CH

DIMENSION
AREA (sq.m.)
QUANTITY OF Length (m.) Width (m.)
Size of CHB CHB (pcs.)
150 4 3 12

10cm x 20 cm x 40cm

TOTAL 150 12

15cm x 20cm x 40cm

TOTAL

20cm x 20cm x 40cm

TOTAL

NOTE: FILL ONLY ON THE SHADED RED COLU


"QUITTERS
SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C” Class “D”

Cement Cement Cement Cement


Sand (cu.m.) Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag) (40kg/bag)

9.504 0.522 6.264 0.522 4.728 0.522 3.936

9.504 0.522 6.264 0.522 4.728 0.522 3.936

D RED COLUMN FOR THE DIMENSION OF THE WALL.


QUITTERS NEVER WIN
"
LENGTH OF REINFORCING BARS FOR CHB IN ME

Vertical Reinforcement Horizontal Reinforcem


Class “D”

Length in Meters
Sand (cu.m.) Length of Bars in Meters
Two-Layer Spacing
SPACING
0.522 35.16 39.6

0.40 m.

0.522 TOTAL LENGTH 4 39.6

0.40 m.

TOTAL LENGTH

0.40 m.

TOTAL LENGTH
ARS FOR CHB IN METER LENGTH OF REINFORCING BA

Horizontal Reinforcement Vertical Reinforcement

Length in Meters Length in Meters SPACING


Length of Bars in
Three-Layer Four-Layer
Meters
Spacing Spacing
25.8 20.64 25.56

0.60 m.

25.8 20.64 25.56

0.60 m.

0.60 m.
H OF REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters SPACING


Length in Meters Length in Meters
Three-Layer
Two-Layer Spacing Four-Layer Spacing
Spacing
39.6 25.8 20.64

0.80 m.

39.6 25.8 20.64

0.80 m.

0.80 m.
LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters Length in Meters


Length of Bars in
Two-Layer Three-Layer
Meters
Spacing Spacing
19.2 39.6 25.8

19.2 39.6 25.8


HB IN METER NO.16 G.I. WIRE FOR CHB REINFORCEMENT

inforcement TWO-LAYER Horizontal Spacing

Length in Meters
VERTICAL 25 cm. 30 cm. 40 cm
Four-Layer Spacing
SPACING
20.64 0.648 0.78 1.032

0.40 m
Engr. Marcon M. Orosco

20.64 0.648 0.78 1.032

0.40 m

0.40 m
CHB REINFORCEMENT PER SQUARE METER NO.16 G

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.40 m 0.40 m
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

R Horizontal Spacing TWO-LAYER Horizontal Spacing TREE-LAYER Horizontal

40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL 25 cm.


SPACING SPACING
0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.60 m 0.60 m
UARE METER NO.16 G.I. WIR

REE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm VERTICAL


SPACING SPACING
0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.60 m 0.80 m.
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.80 m.
E METER

FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.18 0.216 0.288

0.80 m.

0.18 0.216 0.288

0.80 m.

0.80 m.
QUANTITY OF CEMENT AND SAND FOR CH

DIMENSION
AREA (sq.m.)
QUANTITY OF Length (m.) Width (m.)
Size of CHB CHB (pcs.)
150 4 3 12

10cm x 20 cm x 40cm

TOTAL 150 12

15cm x 20cm x 40cm

TOTAL

20cm x 20cm x 40cm

TOTAL

NOTE: FILL ONLY ON THE SHADED RED COLU


"QUITTERS
SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C” Class “D”

Cement Cement Cement Cement


Sand (cu.m.) Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag) (40kg/bag)

9.504 0.522 6.264 0.522 4.728 0.522 3.936

9.504 0.522 6.264 0.522 4.728 0.522 3.936

D RED COLUMN FOR THE DIMENSION OF THE WALL.


QUITTERS NEVER WIN
"
LENGTH OF REINFORCING BARS FOR CHB IN ME

Vertical Reinforcement Horizontal Reinforcem


Class “D”

Length in Meters
Sand (cu.m.) Length of Bars in Meters
Two-Layer Spacing
SPACING
0.522 35.16 39.6

0.40 m.

0.522 TOTAL LENGTH 4 39.6

0.40 m.

TOTAL LENGTH

0.40 m.

TOTAL LENGTH
ARS FOR CHB IN METER LENGTH OF REINFORCING BA

Horizontal Reinforcement Vertical Reinforcement

Length in Meters Length in Meters SPACING


Length of Bars in
Three-Layer Four-Layer
Meters
Spacing Spacing
25.8 20.64 25.56

0.60 m.

25.8 20.64 25.56

0.60 m.

0.60 m.
H OF REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters SPACING


Length in Meters Length in Meters
Three-Layer
Two-Layer Spacing Four-Layer Spacing
Spacing
39.6 25.8 20.64

0.80 m.

39.6 25.8 20.64

0.80 m.

0.80 m.
LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters Length in Meters


Length of Bars in
Two-Layer Three-Layer
Meters
Spacing Spacing
19.2 39.6 25.8

19.2 39.6 25.8


HB IN METER NO.16 G.I. WIRE FOR CHB REINFORCEMENT

inforcement TWO-LAYER Horizontal Spacing

Length in Meters
VERTICAL 25 cm. 30 cm. 40 cm
Four-Layer Spacing
SPACING
20.64 0.648 0.78 1.032

0.40 m
Engr. Marcon M. Orosco

20.64 0.648 0.78 1.032

0.40 m

0.40 m
CHB REINFORCEMENT PER SQUARE METER NO.16 G

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.40 m 0.40 m
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

R Horizontal Spacing TWO-LAYER Horizontal Spacing TREE-LAYER Horizontal

40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL 25 cm.


SPACING SPACING
0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.60 m 0.60 m
UARE METER NO.16 G.I. WIR

REE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm VERTICAL


SPACING SPACING
0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.60 m 0.80 m.
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.80 m.
E METER

FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.18 0.216 0.288

0.80 m.

0.18 0.216 0.288

0.80 m.

0.80 m.
QUANTITY OF CEMENT AND SAND FOR CH

DIMENSION
AREA (sq.m.)
QUANTITY OF Length (m.) Width (m.)
Size of CHB CHB (pcs.)
150 4 3 12

10cm x 20 cm x 40cm

TOTAL 150 12

15cm x 20cm x 40cm

TOTAL

20cm x 20cm x 40cm

TOTAL

NOTE: FILL ONLY ON THE SHADED RED COLU


"QUITTERS
SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C” Class “D”

Cement Cement Cement Cement


Sand (cu.m.) Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag) (40kg/bag)

9.504 0.522 6.264 0.522 4.728 0.522 3.936

9.504 0.522 6.264 0.522 4.728 0.522 3.936

D RED COLUMN FOR THE DIMENSION OF THE WALL.


QUITTERS NEVER WIN
"
LENGTH OF REINFORCING BARS FOR CHB IN ME

Vertical Reinforcement Horizontal Reinforcem


Class “D”

Length in Meters
Sand (cu.m.) Length of Bars in Meters
Two-Layer Spacing
SPACING
0.522 35.16 39.6

0.40 m.

0.522 TOTAL LENGTH 4 39.6

0.40 m.

TOTAL LENGTH

0.40 m.

TOTAL LENGTH
ARS FOR CHB IN METER LENGTH OF REINFORCING BA

Horizontal Reinforcement Vertical Reinforcement

Length in Meters Length in Meters SPACING


Length of Bars in
Three-Layer Four-Layer
Meters
Spacing Spacing
25.8 20.64 25.56

0.60 m.

25.8 20.64 25.56

0.60 m.

0.60 m.
H OF REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters SPACING


Length in Meters Length in Meters
Three-Layer
Two-Layer Spacing Four-Layer Spacing
Spacing
39.6 25.8 20.64

0.80 m.

39.6 25.8 20.64

0.80 m.

0.80 m.
LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters Length in Meters


Length of Bars in
Two-Layer Three-Layer
Meters
Spacing Spacing
19.2 39.6 25.8

19.2 39.6 25.8


HB IN METER NO.16 G.I. WIRE FOR CHB REINFORCEMENT

inforcement TWO-LAYER Horizontal Spacing

Length in Meters
VERTICAL 25 cm. 30 cm. 40 cm
Four-Layer Spacing
SPACING
20.64 0.648 0.78 1.032

0.40 m
Engr. Marcon M. Orosco

20.64 0.648 0.78 1.032

0.40 m

0.40 m
CHB REINFORCEMENT PER SQUARE METER NO.16 G

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.40 m 0.40 m
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

R Horizontal Spacing TWO-LAYER Horizontal Spacing TREE-LAYER Horizontal

40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL 25 cm.


SPACING SPACING
0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.60 m 0.60 m
UARE METER NO.16 G.I. WIR

REE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm VERTICAL


SPACING SPACING
0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.60 m 0.80 m.
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.80 m.
E METER

FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.18 0.216 0.288

0.80 m.

0.18 0.216 0.288

0.80 m.

0.80 m.
QUANTITY OF CEMENT AND SAND FOR CH

DIMENSION
AREA (sq.m.)
QUANTITY OF Length (m.) Width (m.)
Size of CHB CHB (pcs.)
150 4 3 12

10cm x 20 cm x 40cm

TOTAL 150 12

15cm x 20cm x 40cm

TOTAL

20cm x 20cm x 40cm

TOTAL

NOTE: FILL ONLY ON THE SHADED RED COLU


"QUITTERS
SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C” Class “D”

Cement Cement Cement Cement


Sand (cu.m.) Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag) (40kg/bag)

9.504 0.522 6.264 0.522 4.728 0.522 3.936

9.504 0.522 6.264 0.522 4.728 0.522 3.936

D RED COLUMN FOR THE DIMENSION OF THE WALL.


QUITTERS NEVER WIN
"
LENGTH OF REINFORCING BARS FOR CHB IN ME

Vertical Reinforcement Horizontal Reinforcem


Class “D”

Length in Meters
Sand (cu.m.) Length of Bars in Meters
Two-Layer Spacing
SPACING
0.522 35.16 39.6

0.40 m.

0.522 TOTAL LENGTH 4 39.6

0.40 m.

TOTAL LENGTH

0.40 m.

TOTAL LENGTH
ARS FOR CHB IN METER LENGTH OF REINFORCING BA

Horizontal Reinforcement Vertical Reinforcement

Length in Meters Length in Meters SPACING


Length of Bars in
Three-Layer Four-Layer
Meters
Spacing Spacing
25.8 20.64 25.56

0.60 m.

25.8 20.64 25.56

0.60 m.

0.60 m.
H OF REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters SPACING


Length in Meters Length in Meters
Three-Layer
Two-Layer Spacing Four-Layer Spacing
Spacing
39.6 25.8 20.64

0.80 m.

39.6 25.8 20.64

0.80 m.

0.80 m.
LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters Length in Meters


Length of Bars in
Two-Layer Three-Layer
Meters
Spacing Spacing
19.2 39.6 25.8

19.2 39.6 25.8


HB IN METER NO.16 G.I. WIRE FOR CHB REINFORCEMENT

inforcement TWO-LAYER Horizontal Spacing

Length in Meters
VERTICAL 25 cm. 30 cm. 40 cm
Four-Layer Spacing
SPACING
20.64 0.648 0.78 1.032

0.40 m
Engr. Marcon M. Orosco

20.64 0.648 0.78 1.032

0.40 m

0.40 m
CHB REINFORCEMENT PER SQUARE METER NO.16 G

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.40 m 0.40 m
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

R Horizontal Spacing TWO-LAYER Horizontal Spacing TREE-LAYER Horizontal

40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL 25 cm.


SPACING SPACING
0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.60 m 0.60 m
UARE METER NO.16 G.I. WIR

REE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm VERTICAL


SPACING SPACING
0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.60 m 0.80 m.
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.80 m.
E METER

FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.18 0.216 0.288

0.80 m.

0.18 0.216 0.288

0.80 m.

0.80 m.
QUANTITY OF CEMENT AND SAND FOR CH

DIMENSION
AREA (sq.m.)
QUANTITY OF Length (m.) Width (m.)
Size of CHB CHB (pcs.)
150 4 3 12

10cm x 20 cm x 40cm

TOTAL 150 12

15cm x 20cm x 40cm

TOTAL

20cm x 20cm x 40cm

TOTAL

NOTE: FILL ONLY ON THE SHADED RED COLU


"QUITTERS
SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C” Class “D”

Cement Cement Cement Cement


Sand (cu.m.) Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag) (40kg/bag)

9.504 0.522 6.264 0.522 4.728 0.522 3.936

9.504 0.522 6.264 0.522 4.728 0.522 3.936

D RED COLUMN FOR THE DIMENSION OF THE WALL.


QUITTERS NEVER WIN
"
LENGTH OF REINFORCING BARS FOR CHB IN ME

Vertical Reinforcement Horizontal Reinforcem


Class “D”

Length in Meters
Sand (cu.m.) Length of Bars in Meters
Two-Layer Spacing
SPACING
0.522 35.16 39.6

0.40 m.

0.522 TOTAL LENGTH 4 39.6

0.40 m.

TOTAL LENGTH

0.40 m.

TOTAL LENGTH
ARS FOR CHB IN METER LENGTH OF REINFORCING BA

Horizontal Reinforcement Vertical Reinforcement

Length in Meters Length in Meters SPACING


Length of Bars in
Three-Layer Four-Layer
Meters
Spacing Spacing
25.8 20.64 25.56

0.60 m.

25.8 20.64 25.56

0.60 m.

0.60 m.
H OF REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters SPACING


Length in Meters Length in Meters
Three-Layer
Two-Layer Spacing Four-Layer Spacing
Spacing
39.6 25.8 20.64

0.80 m.

39.6 25.8 20.64

0.80 m.

0.80 m.
LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters Length in Meters


Length of Bars in
Two-Layer Three-Layer
Meters
Spacing Spacing
19.2 39.6 25.8

19.2 39.6 25.8


HB IN METER NO.16 G.I. WIRE FOR CHB REINFORCEMENT

inforcement TWO-LAYER Horizontal Spacing

Length in Meters
VERTICAL 25 cm. 30 cm. 40 cm
Four-Layer Spacing
SPACING
20.64 0.648 0.78 1.032

0.40 m
Engr. Marcon M. Orosco

20.64 0.648 0.78 1.032

0.40 m

0.40 m
CHB REINFORCEMENT PER SQUARE METER NO.16 G

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.468 0.564 0.756 0.288 0.348

0.40 m 0.40 m

0.40 m 0.40 m
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

R Horizontal Spacing TWO-LAYER Horizontal Spacing TREE-LAYER Horizontal

40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL 25 cm.


SPACING SPACING
0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.468 0.432 0.528 0.684 0.312

0.60 m 0.60 m

0.60 m 0.60 m
UARE METER NO.16 G.I. WIR

REE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm VERTICAL


SPACING SPACING
0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.384 0.504 0.24 0.288 0.384

0.60 m 0.80 m.

0.60 m 0.80 m.
NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.324 0.396 0.528 0.24 0.288 0.384

0.80 m.

0.80 m.
E METER

FOUR-LAYER Horizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.18 0.216 0.288

0.80 m.

0.18 0.216 0.288

0.80 m.

0.80 m.
QUANTITY OF CEMENT AND SAND FOR C

DIMENSION

QUANTITY OF Length (m.) Width (m.)


Size of CHB CHB (pcs.)
150 4 3

10cm x 20 cm x 40cm

TOTAL 150

12.5 1 1

15cm x 20cm x 40cm

TOTAL 12.5

12.5 1 1

20cm x 20cm x 40cm

TOTAL 12.5

PROJECT TITLE: ENGR. MARCON M. OROSCO


NOTE: FILL ONLY ON THE SHADED RED COLU
"QUITTERS
OF CEMENT AND SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C”
AREA (sq.m.)
Cement Cement Cement
Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag)

12 9.504 0.522 6.264 0.522 4.728

12 9.504 0.522 6.264 0.522 4.728

1 1.526 0.0844 1.018 0.0844 0.763

1 1.526 0.0844 1.018 0.0844 0.763

1 2.26 0.125 1.5 0.125 1.125

1 2.26 0.125 1.5 0.125 1.125

ARCON M. OROSCO
ON THE SHADED RED COLUMN FOR THE DIMENSION OF THE WALL.
"QUITTERS NEVER WIN
"
ER LENGTH OF REINFORCING BAR
D AND CEMENT
Vertical Reinforcement
Class “C” Class “D”

Cement
Sand (cu.m.) Sand (cu.m.) Length of Bars in Meters
(40kg/bag)
SPACING
0.522 3.936 0.522 35.16

0.40 m.

0.522 3.936 0.522 TOTAL LENGTH 4

0.0844 0.633 0.0844 2.93

0.40 m.

0.0844 0.633 0.0844 TOTAL LENGTH 2.93

0.125 0.938 0.125 2.93

0.40 m.

0.125 0.938 0.125 TOTAL LENGTH 2.93

F THE WALL.
F REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters Length in Meters SPACING


Length in Meters
Three-Layer Four-Layer
Two-Layer Spacing
Spacing Spacing
39.6 25.8 20.64

0.60 m.

39.6 25.8 20.64

3.3 2.15 1.72

0.60 m.

3.3 2.15 1.72

3.3 2.15 1.72

0.60 m.

3.3 2.15 1.72


LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters
Length of Bars in Length in Meters
Three-Layer
Meters Two-Layer Spacing
Spacing
25.56 39.6 25.8

25.56 39.6 25.8

2.13 3.3 2.15

2.13 3.3 2.15

2.13 3.3 2.15

2.13 3.3 2.15


HB IN METER LENGTH OF REINFORCING BARS FOR CHB I

nforcement Vertical Reinforcement Horizontal Reinfor


SPACING Length in Meters
Length in Meters Length of Bars in
Two-Layer
Four-Layer Spacing Meters
Spacing
20.64 19.2 39.6

0.80 m.

20.64 19.2 39.6

1.72 1.6 3.3

0.80 m.

1.72 1.6 3.3

1.72 1.6 3.3

0.80 m.

1.72 1.6 3.3


NG BARS FOR CHB IN METER NO.16 G.I. WIRE FOR CHB RE

Horizontal Reinforcement TWO-LAYER Horizontal Spacing

Length in Meters
Length in Meters
Three-Layer VERTICAL 25 cm. 30 cm.
Four-Layer Spacing
Spacing SPACING
25.8 20.64 0.648 0.78

0.40 m

Engr. Marcon M. Orosco


25.8 20.64 0.648 0.78

2.15 1.72 0.054 0.065

0.40 m

2.15 1.72 0.054 0.065

2.15 1.72 0.054 0.065

0.40 m

2.15 1.72 0.054 0.065


RE FOR CHB REINFORCEMENT PER SQUARE METER

Horizontal Spacing TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal S

40 cm VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm.


SPACING SPACING
1.032 0.468 0.564 0.756 0.288

0.40 m 0.40 m

1.032 0.468 0.564 0.756 0.288

0.086 0.039 0.047 0.063 0.024

0.40 m 0.40 m

0.086 0.039 0.047 0.063 0.024

0.086 0.039 0.047 0.063 0.024

0.40 m 0.40 m

0.086 0.039 0.047 0.063 0.024


NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE M

OUR-LAYER Horizontal Spacing TWO-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL


SPACING SPACING
0.348 0.468 0.432 0.528 0.684

0.60 m 0.60 m

0.348 0.468 0.432 0.528 0.684

0.029 0.039 0.036 0.044 0.057

0.60 m 0.60 m

0.029 0.039 0.036 0.044 0.057

0.029 0.039 0.036 0.044 0.057

0.60 m 0.60 m

0.029 0.039 0.036 0.044 0.057


T PER SQUARE METER NO.16

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

25 cm. 30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.312 0.384 0.504 0.24 0.288 0.384

0.60 m

0.312 0.384 0.504 0.24 0.288 0.384

0.026 0.032 0.042 0.02 0.024 0.032

0.60 m

0.026 0.032 0.042 0.02 0.024 0.032

0.026 0.032 0.042 0.02 0.024 0.032

0.60 m

0.026 0.032 0.042 0.02 0.024 0.032


NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.324 0.396 0.528 0.24 0.288

0.80 m. 0.80 m.

0.324 0.396 0.528 0.24 0.288

0.027 0.033 0.044 0.02 0.024

0.80 m. 0.80 m.

0.027 0.033 0.044 0.02 0.024

0.027 0.033 0.044 0.02 0.024

0.80 m. 0.80 m.

0.027 0.033 0.044 0.02 0.024


SQUARE METER

RHorizontal Spacing FOUR-LAYER Horizontal Spacing

40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.384 0.18 0.216 0.288

0.80 m.

0.384 0.18 0.216 0.288

0.032 0.015 0.018 0.024

0.80 m.

0.032 0.015 0.018 0.024

0.032 0.015 0.018 0.024

0.80 m.

0.032 0.015 0.018 0.024


QUANTITY OF CEMENT AND SAND FOR C

DIMENSION

QUANTITY OF Length (m.) Width (m.)


Size of CHB CHB (pcs.)
150 4 3

10cm x 20 cm x 40cm

TOTAL 150

12.5 1 1

15cm x 20cm x 40cm

TOTAL 12.5

52.5 1.4 3

20cm x 20cm x 40cm

TOTAL 52.5

PROJECT TITLE: ENGR. MARCON M. OROSCO


NOTE: FILL ONLY ON THE SHADED RED COLU
"QUITTERS
OF CEMENT AND SAND FOR CHB MORTAR PER SQUARE METER
QUANTITY OF SAND AND CEMENT
Class “A” Class “B” Class “C”
AREA (sq.m.)
Cement Cement Cement
Sand (cu.m.) Sand (cu.m.)
(40kg/bag) (40kg/bag) (40kg/bag)

12 9.504 0.522 6.264 0.522 4.728

12 9.504 0.522 6.264 0.522 4.728

1 1.526 0.0844 1.018 0.0844 0.763

1 1.526 0.0844 1.018 0.0844 0.763

4.2 9.492 0.525 6.3 0.525 4.725

4.2 9.492 0.525 6.3 0.525 4.725

ARCON M. OROSCO
ON THE SHADED RED COLUMN FOR THE DIMENSION OF THE WALL.
"QUITTERS NEVER WIN
"
ER LENGTH OF REINFORCING BAR
D AND CEMENT
Vertical Reinforcement
Class “C” Class “D”

Cement
Sand (cu.m.) Sand (cu.m.) Length of Bars in Meters
(40kg/bag)
SPACING
0.522 3.936 0.522 35.16

0.40 m.

0.522 3.936 0.522 TOTAL LENGTH 4

0.0844 0.633 0.0844 2.93

0.40 m.

0.0844 0.633 0.0844 TOTAL LENGTH 2.93

0.525 3.9396 0.525 12.306

0.40 m.

0.525 3.9396 0.525 TOTAL LENGTH 12.306

F THE WALL.
F REINFORCING BARS FOR CHB IN METER LENGTH OF

Horizontal Reinforcement

Length in Meters Length in Meters SPACING


Length in Meters
Three-Layer Four-Layer
Two-Layer Spacing
Spacing Spacing
39.6 25.8 20.64

0.60 m.

39.6 25.8 20.64

13.86 2.15 1.72

0.60 m.

13.86 2.15 1.72

13.86 9.03 7.224

0.60 m.

13.86 9.03 7.224


LENGTH OF REINFORCING BARS FOR CHB IN METER

Vertical Reinforcement Horizontal Reinforcement

Length in Meters
Length of Bars in Length in Meters
Three-Layer
Meters Two-Layer Spacing
Spacing
25.56 39.6 25.8

25.56 39.6 25.8

2.13 3.3 2.15

2.13 3.3 2.15

8.946 13.86 9.03

8.946 13.86 9.03


HB IN METER LENGTH OF REINFORCING BARS FOR CHB I

nforcement Vertical Reinforcement Horizontal Reinfor


SPACING Length in Meters
Length in Meters Length of Bars in
Two-Layer
Four-Layer Spacing Meters
Spacing
20.64 19.2 39.6

0.80 m.

20.64 19.2 39.6

1.72 1.6 3.3

0.80 m.

1.72 1.6 3.3

7.224 6.72 13.86

0.80 m.

7.224 6.72 13.86


NG BARS FOR CHB IN METER NO.16 G.I. WIRE FOR CHB RE

Horizontal Reinforcement TWO-LAYER Horizontal Spacing

Length in Meters
Length in Meters
Three-Layer VERTICAL 25 cm. 30 cm.
Four-Layer Spacing
Spacing SPACING
25.8 20.64 0.648 0.78

0.40 m

Engr. Marcon M. Orosco


25.8 20.64 0.648 0.78

2.15 1.72 0.054 0.065

0.40 m

2.15 1.72 0.054 0.065

9.03 7.224 0.2268 0.273

0.40 m

9.03 7.224 0.2268 0.273


RE FOR CHB REINFORCEMENT PER SQUARE METER

Horizontal Spacing TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal S

40 cm VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm.


SPACING SPACING
1.032 0.468 0.564 0.756 0.288

0.40 m 0.40 m

1.032 0.468 0.564 0.756 0.288

0.086 0.039 0.047 0.063 0.024

0.40 m 0.40 m

0.086 0.039 0.047 0.063 0.024

0.3612 0.1638 0.1974 0.2646 0.1008

0.40 m 0.40 m

0.3612 0.1638 0.1974 0.2646 0.1008


NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE M

OUR-LAYER Horizontal Spacing TWO-LAYER Horizontal Spacing

30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm. VERTICAL


SPACING SPACING
0.348 0.468 0.432 0.528 0.684

0.60 m 0.60 m

0.348 0.468 0.432 0.528 0.684

0.029 0.039 0.036 0.044 0.057

0.60 m 0.60 m

0.029 0.039 0.036 0.044 0.057

0.1218 0.1638 0.1512 0.1848 0.2394

0.60 m 0.60 m

0.1218 0.1638 0.1512 0.1848 0.2394


T PER SQUARE METER NO.16

TREE-LAYER Horizontal Spacing FOUR-LAYER Horizontal Spacing

25 cm. 30 cm. 40 cm. VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.312 0.384 0.504 0.24 0.288 0.384

0.60 m

0.312 0.384 0.504 0.24 0.288 0.384

0.026 0.032 0.042 0.02 0.024 0.032

0.60 m

0.026 0.032 0.042 0.02 0.024 0.032

0.1092 0.1344 0.1764 0.084 0.1008 0.1344

0.60 m

0.1092 0.1344 0.1764 0.084 0.1008 0.1344


NO.16 G.I. WIRE FOR CHB REINFORCEMENT PER SQUARE METER

TWO-LAYER Horizontal Spacing TREE-LAYERHorizontal Spacing

VERTICAL 25 cm. 30 cm. 40 cm VERTICAL 25 cm. 30 cm.


SPACING SPACING
0.324 0.396 0.528 0.24 0.288

0.80 m. 0.80 m.

0.324 0.396 0.528 0.24 0.288

0.027 0.033 0.044 0.02 0.024

0.80 m. 0.80 m.

0.027 0.033 0.044 0.02 0.024

0.1134 0.1386 0.1848 0.084 0.1008

0.80 m. 0.80 m.

0.1134 0.1386 0.1848 0.084 0.1008


SQUARE METER

RHorizontal Spacing FOUR-LAYER Horizontal Spacing

40 cm VERTICAL 25 cm. 30 cm. 40 cm


SPACING
0.384 0.18 0.216 0.288

0.80 m.

0.384 0.18 0.216 0.288

0.032 0.015 0.018 0.024

0.80 m.

0.032 0.015 0.018 0.024

0.1344 0.063 0.0756 0.1008

0.80 m.

0.1344 0.063 0.0756 0.1008