Professional Documents
Culture Documents
Order:
8pcs 10mm x 5m long
1pc 10mm x 6m long
By Unit Block Method
By the Square Meter or Area Method
1. Solve for the area of the fence and total number of CHB:
A=LXW CHB=
A=__
2. For vertical reinforcement spaced at 80cm:
*Refer to the table given
Total length of Rebars= No. of CHB x MF
=
3. Select the most economical length to avoid extra cut
Select:5m
therefore: 4pcs.10mm x 5m long
=20m
4.For Horizontal bars at every after 3 layers
*Refer to the table given
Total length of Rebars= No. of CHB x MF
5. Select the most economical:
4pcs 10mm x 5m long
1pc 10mm x 6m long
Order:
8pcs 10mm x 5m long
1pc 10mm x 6m long
Tie Wires for CHB Reinforcement
Continuing the problem
Vertical Reinforcement Spacing= 80cm
Horizontal Reinforcement spacing at every 3 layers
Area of the wall= 12sqm
1. Determine the no. of CHB
= 12 X 12.5
=
2.Refer to the table given,use 25cm long tie wire
Qty of GI Wire = No. of CHB X MF
2.FOOTINGS REINFORCEMENT
Considerations:
• Wastage
• Dimensions of columns and footings
• Minimum protective covering: 75 mm (underground)
• Hooks and Bends
• Spacing or number of bars in both directions
• G.I. Wire for tying reinforcing bars
From the figure given,determine the number of 12mm steel bars
required if there are 6 footings with a general dimensions of 1.5 x 1.5 m
1. Determine the net length
NL= 1.5 - (0.075+0.075)
=
2.Find the number of cut bars by direct counting and consider the
number of footings
13x2= 26pcs/ footing
Total No.of Pcs = 26 x 6 =156pcs at 1.35m long
3. Select the steel bars whose length is economically cut into 1.35m
long. Consider 6m commercial length
6.00m
4.44 pcs
1.35m
4. Get the total number of 6m commercial length
156
39 pcs of 12mm x 6m long
4.0
Tie Wires foor Footing
1. Determine the number of Intersection
As per ACI CODE, the spacing of the ties shall not exceed:
1.16 x the longitudinal bar diameter
2.48 x lateral tie bar diameter
3.The least dimension of the column
4. Order:
Lateral Ties
Determine the spacing distance of the lateral ties for a tied column as
shown in the following figure
1. Determine the spacing using the three condition
a.16 x the longitudinal bar diameter
b.48 x lateral tie bar diameter
c.The least dimension of the column
Order:
Tie Wires for Column
1. Find the number of main reinforcement i one column multiplied by
the number of lateral ties
Order:
4 pcs of 16mm x 6m long
Stirrups (10mm)
By direct counting
18pcs of stirrups
• By observation
The length of each stirrup is 1m
• Choose the economical length
Try 6m
6/1 = 6pcs
Get the total number of 6m
18/6 = 3pcs of 10mm x 6m long
Order :
6pcs of 16mm x 6m
1pc of 16mm x 9m
3pcs of 10mm x 6m
Slab Reinforcement
• One Way L/S > OR = 2
• Two Way L/S < 2
One Way Slab
Determine the number of steel bars.
For GI Wires
= A x MF
Two way reinforcement bar
Determine the number of steel bars
Spacing of Main reinforcement = 10cm
1. Determine the floor area
A= L x W
2. Using 7.5m long steel bars at 10cm spacing distance. Refer to the
table given.
No. of pcs of 6m = A X MF
For GI Wires
= A x MF