1 SWT- SOLENOID OPERATED GAS STOP VALVE FLAME PROOF COIL 4 nil
230V/50HZ.
SOL.VALVE
2 SWT- 3 1
Date: 11/9/2018
AGM (S&M)
POL-House, Morgah,
Rawalpindi
Sir,
We would like to inform you that listed spare parts are required for
The maintenance of Elixir LPG filling machines at POL gas filling plant Karachi
Plant superintendent
POL Gasplant,
Karachi
POL GAS PLANT KARACHI
Maintenance Schedule for the month of November 2018