EOT DELAYS ANALYSIS
Presented by :
Hany Ismail, MSc, PMP
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
LESSON 7
TIME IMPACT WINDOW DELAY ANALYSIS
TECHNIQUE
TIME IMPACT – WINDOW ANALYSIS
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Agenda
• Introduction.
• Why is TIA preferred technique ?
• Window Analysis Technique
• Window Analysis Technique Steps
• Smart Windows Time Periods
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Introduction
Time Impact Analysis Technique is Actual Based Approach
the responsibility for delay prior to the impact of the delaying event
is not material to the calculation of the effect of the delaying event
itself.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
- Analysis steps
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
CASE STUDY
BANK XYZ PROJECT
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Appr.
22,April,
P0 Baseline
2013
A.01
P0+Delay
W0 31 P1 Events
13,May,
2013
P1+Progress
14,May,
P2 update on
2013
DD
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Approved
P3 P2 14,May,
2013
P3+Delay
W1 264 P4 Events
25,May,
2013
P4+Progress
3,Jun
P5 update on
, 2013
DD
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Approved
P6 P5 3,Jun
, 2013
P6+Delay
W2 264 P7 Events
9,July,
2013
P7+Progress
21,July,
P8 update on
2013
DD
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Approved
P9 P8 21,July,
2013
P9+Delay
W3 79 P10 Events
15,Aug,
2013
P10+Progres
15,Sep.,
P11 s update on
2013
DD
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Total Entitlement
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Total Entitlement
146 Calendar Day
Excusable Non-Excusable
93 Day 53 Day
Non-
Compensable
Compensable
WWW.PLANNINGENGINEER.NET
Thank You …