HARGA BAHAN BANGUNAN & UPAH (RAB)

HARGA BAHAN BANGUNAN


NO BAHAN Kode HARGA Satuan
1 Kayu Terentang/Bekisting @ Rp 2,500,000.00 M³
2 Paku USUK RENG @ Rp 22,700.00 Kg
3 Seng GELOMBANG KECIL @ Rp 75,000.00 Lb
4 Batu Kali @ Rp 220,000.00 M³
5 Kapur @ Rp 259,500.00 M³
6 Pasir pasang @ Rp 225,000.00 M³
7 PC @ Rp 1,000.00 Kg
8 Besi Beton @ Rp 15,000.00 Kg
9 Bendrat @ Rp 18,400.00 Kg
10 Batu Split @ Rp 185,000.00 M³
11 Bata Merah @ Rp 600.00 Bj
12 Kayu Meranti @ Rp 4,440,000.00 M³
13 Genteng Beton PALENTONG @ Rp 1,300.00 Bj
14 Bubungan Genteng PELENTONG @ Rp 5,500.00 Bh
15 Paku Genteng Metal @ Rp 15,000.00 Kg
16 PC Warna @ Rp 10,000.00 Kg
17 Kayu Bengkirai Balok @ Rp 12,500,000.00 M³
18 Kayu Kamper Papan @ Rp 10,000,000.00 M³
19 Besi Strip @ Rp 20,000.00 Kg
20 SENG PLAT 3" x 6" BJLS 30 @ Rp 70,000.00 M¹
21 Kayu Bengkirai Papan @ Rp 11,160,000.00 M³
22 Meni Besi @ Rp 24,100.00 Kg
23 Kayu Jati Papan @ Rp 18,500,000.00 M³
24 Kayu Kruing Balok @ Rp 5,260,000.00 M³
25 Asbes Plate 100 ×100×3 @ Rp 12,000.00 Lb
26 Paku Enternit @ Rp 19,303.00 Kg
27 Ubin Keramik 40/40 @ Rp 10,000.00 Bh
28 Ubin Keramik 25/25 @ Rp 3,000.00 Bh
29 Ubin Keramik 20/25 @ Rp 2,500.00 Bh
30 Titik Lampu + Stop Kontak @ Rp 150,000.00
31 Lampu 15 Wat @ Rp 28,000.00 Bh
32 Buis Beton @ Rp 200,000.00 Bh
33 Ijuk @ Rp 18,000.00 Kg
34 Pompa Air @ Rp 1,250,000.00 Bh
35 Pipa PVC 3/4 @ Rp 8,000.00 M¹
36 Lem PVC @ Rp 18,000.00
37 Rangka Baja @ Rp 200,000.00 M²
38 Tandon Air 800 L @ Rp 1,600,000.00 Bh
39 Kran Air 3/4 @ Rp 150,000.00 Bh
40 TBA @ Rp 3,000.00
41 WASTAFEL @ Rp 12,000,000.00 Bh
42 FLOOR DRAIN @ Rp 200,000.00
43 ZINK @ Rp 7,000,000.00 Bh
44 Sock Kombinasi 2.5 = 2 @ Rp 5,500.00
45 Pipa PVC 2´ @ Rp 25,500.00 M¹
46 Pipa PVC 1´ @ Rp 4,500.00 M¹
47 Pipa Vent 2´ @ Rp 25,000.00 M¹
48 Pipa PVC 4´ @ Rp 81,000.00 M¹
49 Keni @ Rp 5,500.00 Bj
50 Testelle 2´ @ Rp 5,500.00 Bj
51 Kloset DUDUK TOTO @ Rp 700,000.00 Bh
52 Pasir Beton @ Rp 98,000.00 M³
53 Plamir Tembok @ Rp 18,200.00 Kg
54 Cat Dasar @ Rp 45,000.00 Kg
55 CAT PENUTUP @ Rp 45,000.00 Kg
56 Politur @ Rp 50,000.00 Ltr
57 Politur Jadi @ Rp 50,000.00 Ltr
58 Amplas @ Rp 3,300.00 Lb
59 Engsel Pintu 5" @ Rp 600,000.00 Bj
60 Kunci Tanam Antik @ Rp 800,000.00 Bh
61 Kunci Tanam Selot @ Rp 500,000.00 Bh
62 Grendel Pintu @ Rp 30,000.00 BJ
63 Door Closerr @ Rp 250,000.00 Bh
64 Engsel Jendela @ Rp 350,000.00 BJ
65 Grendel Jendela @ Rp 30,000.00 BJ
66 Hak Angin @ Rp 60,000.00 Bj
67 Kaca 5mm @ Rp 89,600.00 M²
68 Paku Usuk / Reng @ Rp 30,000.00 Kg
69 Tanah Urug @ Rp 90,000.00 M³
70 Pasir Urug @ Rp 150,000.00 M³
71 Penyambungan PLN PAL 1200 @ Rp 2,500,000.00
72 Lampu 15 Wat @ Rp 15,000.00 Bh
73 Palm Merah @ Rp 350,000.00 Bh
74 Kamboja @ Rp 750,000.00 Bh
75 Beton K225 @ Rp 1,444,810.00 M³
76 Minyak Bekisting @ Rp 8,500.00 Ltr
77 Kayu playwood/multi pleks @ Rp 100,000.00 Lbr
78 Kayu Dolken DIA 8-10 @ Rp 22,000.00 Btg
79 Handle @ Rp 10,000.00 Bh
80 Angkur @ Rp 9,000.00 Bh

UPAH PEKERJA
NO PEKERJA KODE UPAH SATUAN
1 Pekerja @ Rp 72,000.00 OH
2 Tukang Batu @ Rp 84,000.00 OH
3 Tukang Besi @ Rp 85,000.00 OH
4 Tukang Kayu @ Rp 90,000.00 OH
5 Tukang Cat @ Rp 85,000.00 OH
6 Tukang Pipa @ Rp 90,000.00 OH
7 Kepala Tukang @ OH
8 Mandor @ Rp 96,000.00 OH
PAKU 2"-5" Rp 24,000.00 Kg

SIRTU Rp 160,000.00 M³
PASIR URUG Rp 144,100.00 M³
PASIR PASANG Rp 225,000.00 M³
PC GRESIK /HOLCIM Rp 1,000.00 KG
BESI BETON ULIR SNI Rp 15,000.00 KG
BESI BETON POLOS SNI Rp 15,000.00 KG

PORSELEN 11X11 Rp 3,000.00


SEMEN NAT Rp 5,500.00

BM PER METER Rp 39,500.00

Kayu Bengkirai PAPAN Rp 10,000,000.00 M³

KAYU JATI BALOK Rp 17,500,000.00


KAYU PROFIL Rp 6,000.00

50/50 Rp 15,000.00

PERLENGKAPAN Rp 8,000.00
PERLENGKAPAN Rp 100,000.00

PERLENGKAPAN Rp 100,000.00

PERLENGKAPAN Rp 25,000.00

PERMETER SALAHHHH Rp 38,500.00 PERLENGKAPAN Rp 38,500.00

PERLENGKAPAN Rp 100,000.00

BATHUP Rp 5,500,000.00
PERLENGKAPAN Rp 100,000.00

PAS BATU TEMPEL EKS Rp 450,000.00

1 SET RAILING GARASI Rp 10,000,000.00

PAKU 2-5 Rp 30,000.00


PAKU SENG Rp 30,000.00

BESI BETON POLOS Rp 17,216.80 M3 KAYU MERANTI 5/7


BEKESTING FOOTPLAT Rp 99,953.00 M2
BEKESTING PLAT Rp 385,144.00 M2
MYK BEKESTING Rp 8,500.00 LTR

MUR BAUT Rp 10,000.00


BEGEL KALUNG Rp 15,000.00

TUKANG GALI Rp 115,000.00

KEP T. BATU Rp 90,000.00


KEP T. BESI Rp 90,000.00
KEP T. KAYU Rp 96,000.00
KEP T. CAT Rp 90,000.00
KEP T. PIPA Rp 96,000.00
ROOSTER Rp 5,800.00 Bh
Rp 2,200,000.00 M3
PERHITUNGAN VOLUME PEKE
NO JENIS PEKERJAAN
I PEKERJAAN PERSIAPAN
1. MEMBERSIHKAN LAHAN & MERATAKAN TANAH

2. PAGAR PENGAMAN SENG

3. PASANG BOUWPLANK

II PEKERJAAN TANAH DAN GALIAN


1. PEKERJAAN GALIAN TANAH
2. PEK. URUG KEMBALI GALIAN TANAH
III PEKERJAAN PONDASI
PONDASI BATU KALI
1. VOLUME PONDASI BK 1 PC : 3 KP : 10 PS

2. VOLUME BATU KOSONG


PONDASI FOOTPLAT
1. VOLUME PONDASI FOOTPLAT

IV PEKERJAAN BETON BERTULANG


A. PEKERJAAN BETON BERTULANG
1. PEKERJAAN SLOOF 15/25

2. PEKERJAAN KOLOM
2.1 PEKERJAAN KOLOM K1 DIA 50 CM

2.2 PEKERJAAN KOLOM K2 40/40

3. PEKERJAAN BALOK LANTAI


3.1 PEKERJAAN BALOK B1 30/60

3.2 PEKERJAAN BALOK B2 25/45

4. PEKERJAAN BALOK DAG 25/45

5. PEKERJAAN RINGBALK 15/20 (KUBAH)

6. PEKERJAAN BETON PADA TANGGA

7. PEKERJAAN PLAT LANTAI T = 12 CM

8. PEKERJAAN BETON MULDING


9. PEKERJAAN BALOK MENARA 15/25

8. PEKERJAAN BETON KUBAH & MENARA

V PEKERJAAN DINDING PASANGAN BATA MERAH ½ BT


1. PASANGAN BATA MERAH TRASRAAM 1 PC : 3 PS

2.       PAS. BATA MERAH , 1 PC : 3 KP : 10 PS

VI PEKERJAAN PLESTERAN
1. PEKERJAAN PLESTERAN DINDING TEBAL 15 MM,
CAMP. 1PC : 4PS

2. LIST SUDUT PLESTERAN

VII PEKERJAAN CAT


1. PEKERJAAN CAT EKSTERIOR INTERIOR

2.PEKERJAAN PLAT LANTAI

3. PEKERJAAN POLITUR KUSEN PINTU DAN JENDELA


4. PEKERJAAN POLITUR PANIL PINTU DAN JENDELA

VIII PEKERJAAN KUSEN PINTU & JENDELA


1. PEKERJAAN KUSEN

2. PEKERJAAN DAUN PINTU JENDELA


IX PEKERJAAN INSTALASI LISTRIK

X PEKERJAAN LANTAI
1. LANTAI KERAMIK 50x50

2. LANTAI KERAMIK 40x40

XI PEKERJAAN ALAT GANTUNG & KACA


1. BESI ANGKUR

3. ALAT GANTUNG PINTU & JENDELA


3.1 PINTU
3.2 JENDELA
PERHITUNGAN VOLUME PEKERJAAN
PEHITUNGAN VOLUME

> LUAS LAHAN KAPLING = 16 M × 16 M


256

> PANJANG = 110 M , TINGGI = 1.8 M


110

2 (P + L) = 2 (16 M + 16 M)
64

PONDASI BATU KALI


> VOLUME GALIAN TANAH
L. TAMPANG GALIAN PONDASI TENGAH
((1.3 + 1.58) : 2) × 0.7
1.008

L. TAMPANG GALIAN PONDASI TEPI


((0.73 + 0.87) : 2) × 0.7
0.56

> PANJANG PONDASI


PONDASI TENGAH
67

PONDASI TEPI
56

> P. KESELURUHAN = P. TENGAH + P. TEPI


67 + 56
123

> VOLUME GALIAN PONDASI


PONDASI TENGAH
L. PENAMPANG × P. PONDASI
67.536

PONDASI TEPI
L. PENAMPANG × P. PONDASI
31.36
> VOLUME GALIAN PONDASI BK TOTAL
98.896

PONDASI FOOTPLAT
JUMLAH FOOTPLAT = 38 Bh
> LUAS PENAMPANG GALIAN
1.4 x 1.3
1.82

> VOLUME GALIAN PONDASI


L. PENAMPANG x PANJANG
1.82 x 1.4
2.548

> VOLUME GALIAN PONDASI FOOTPLAT TOTAL


38 x 2.548
96.824

> VOLUME GALIAN PONDASI KESELURUHAN (BK + FOOTPLAT)


195.720

VOLUME URUG TANAH PONDASI


Ø  URUG TANAH GALIAN PONDASI BK
1/4 × V. GALIAN PONDASI
24.724

Ø  URUG TANAH GALIAN PONDASI FOOTPLAT


1.296 x 38
49.248

Ø  VOLUME TOTAL URUG TANAH PONDASI


73.97

VOLUME URUG TANAH BAWAH LANTAI


TEBAL URUG TANAH × LUAS LANTAI
0.98 x 200
196

TOTAL URUG TANAH BAWAH LANTAI


196
VOLUME URUG SIRTU
Ø  URUG SIRTU BAWAH PONDASI FOOTPLAT
6.338

VOLUME URUG PASIR


Ø  URUG PASIR BAWAH PONDASI BK
PONDASI TENGAH
0.066 x 67
4.39

PONDASI TEPI
0.014 x 56
0.76

Ø  URUG PASIR BAWAH LANTAI


LANTAI 1
40

LANTAI 2
10.50

URUG PASIR KESELURUHAN


55.65

> V. PONDASI TENGAH + V. PONDASI TEPI


0.87 × 67 + 0.56 × 56
89.650

> V. PONDASI TRAP TANGGA SAMPING


6.4

> VOLUME PONDASI BK KESELURUHAN


96.05

> PONDASI TENGAH


PENAMPANG x PANJANG
0.272 x 67
18.224

> PONDASI TEPI


PENAMPANG x PANJANG
0.151 x 56
8.456

> VOLUME KESELURUHAN


26.68

JUMLAH FOOTPLAT UTUH = 38 Bh


> VOLUME PONDASI FOOTPLAT
0.59

> VOLUME KESELURUHAN (38 Bh)


22.42

PANJANG SLOOF
123

n. TITIK KOLOM × TINGGI KOLOM


(14 x 10.3) + (4 x 11.1) + (2 x 11.7)
212

n. TITIK KOLOM × TINGGI KOLOM


(12 x 10.3) + (6 x 11.7)
193.8

16

140

186

35.67

BETON BAWAH ANAK TANGGA + BETON BORDES


0.14

0.12 x LUAS PLAT LANTAI


34.66

LUAS PENAMPANG x PANJANG


0.03 x 166.6
4.998
63.5 + 85.5
149

29.87

> LANTAI 1
> PAS. TRASRAAM
110.3

> LANTAI 2
> PAS. TRASRAAM
100.68

TOTAL PAS TRASRAAM


210.98

> LANTAI 1
40.77

> LANTAI 2
30.23

TOTAL PAS BATA MERAH


71.00

2 × LUAS PAS. BM & TRASRAAM


2 × 271.05
542.1

LIST SUDUT PLESTERAN KESELURUHAN


500.98

> LUAS TOTAL PENGECATAN TEMBOK, KOLOM, DAN BALOK


1105.46

352.2

PJ KUSEN TEPI × PENAMPANG


283.12 × 0.24
68
SAMA DENGAN LUAS TOTAL PANIL
39.46

JADI JUMLAH CAT POLITUR KESELURUHAN


107.46

JADI V. KUSEN
0.08 × 0.12 × 283.12
2.72

INVENTARISASI ALAT GANTUNG

ENGSEL : BESAR (PINTU) : 3 x 9 = 27 Bh


KECIL (JENDELA) :-

GRENDEL : BESAR (PINTU) :2x9 = 18 Bh


KECIL (JENDELA) :-

SLOOT PINTU : 1 x 9 = 9 Bh

BESI DOOK : 2 x 9 = 18 Bh

ANGKUR : PINTU : 54 Bh
JENDELA : 246 Bh

1. BIAYA PENYAMBUNGAN PAL PLN 1200 KWh


2. TITIK LAMPU = 38
3. STOP KONTAK = 10 BUAH (SUDAH TERMASUK BIAYA TITIK LAMPU)
4. LAMPU SL = 12 WATT = 29 BUAH
10 WATT = 5 BUAH
8 WATT = 4 BUAH

L. BIDANG KERAMIK 50x50


322.07

L. BIDANG KERAMIK 40x40


45.6

1. ANGKUR KUSEN = 300 Bh


60

1. ENGSEL PINTU (BESAR)


JUMLAH PINTU × 3
9×3
27

2. SELOT PINTU
JUMLAH PINTU x 1
9x1
9

KUNCI TANAM ANTIK = 3


SELOT BIASA = 6
3. GRENDEL PINTU (BESAR)
JUMLAH PINTU × 2
2x9
18

1. KACA JENDELA
41.33




11.2
M¹ 27.75
39.65
58
136.6



TOTAL
JENIS JMLH SATUAN K. TENGAH K.TEPI
TENGAH
P1 1 M¹ ˉ 7.02 ˉ
P2 2 M¹ ˉ 7.02 ˉ
P3 4 M¹ ˉ 5.02 ˉ
P4 2 M¹ ˉ 4.92 ˉ
J1 4 M¹ ˉ 8.44 ˉ
J2 8 M¹ ˉ 5.32 ˉ
J3 36 M¹ ˉ 3.32 ˉ
J4 15 M¹ ˉ 2.42 ˉ
TOTAL ˉ

JENIS JMLH SATUAN PANIL KACA KREPYAK

M³ P1 1 M² 6.57 ˉ ˉ
P2 2 M² 1.27 4.9 ˉ
P3 4 M² 1.72 ˉ ˉ
P4 2 M² 1.51 ˉ ˉ
J1 4 M² 1.17 4.4 ˉ
J2 8 M² 0.4 0.5 ˉ
J3 36 M² 0.27 0.23 ˉ
J4 15 M² 0.19 0.11 ˉ
TOTAL ˉ

Kg

Bh

Bh

Bh
Bh
Bh


TOTAL
TOTAL
TEPI
7.02 7.02
14.04 14.04
20.08 20.08
9.84 9.84
33.76 33.76
42.56 42.56
119.52 119.52
36.3 36.3
252.1 283.12

TOTAL
PANIL KACA
6.57 ˉ
2.54 9.8
6.88 ˉ
3.02 ˉ
4.68 17.6
3.2 4
9.72 8.28
2.85 1.65
39.46 41.33
SCHDULE PERENCANAA

NAMA PROYEK : PENGADAAN RUMAH TINGGAL KLASIK 2 LANTAI TYPE 155/380


LOKASI : MANDUNGAN, SRIMARTANI, PIYUNGAN, BANTUL, YK
TAHUN : 2018

MARET APRIL
NO NAMA PEKERJAAN BOBOT %
0 1 2 3 4
I PEKERJAAN PERSIAPAN 0.000 0.00 0.00 0.00

II PEKERJAAN TANAH DAN GALIAN 0.000 0.00 0.00 0.00

III PEKERJAAN PASANGAN PONDASI BK 0.000 0.00 0.00

IV PEKERJAAN BETON BERTULANG 0.000

V PEKERJAAN DINDING PASANGAN 0.000 0.00

VI PEKERJAAN PLESTERAN 0.000

VII PEKERJAAN CAT DAN POLITUR 0.000

VIII PEKERJAAN KUSEN & DAUN PINTU JENDELA 0.000 0.00 0.00 0.00 0.00 0.00

IX PEKERJAAN ATAP DAN RANGKA ATAP 0.000

X PEKERJAAN PLAFOND / LANGIT LANGIT 0.000

XI PEKERJAAN INSTALASI LISTRIK 0.000


XII PEKERJAAN KERAMIK LANTAI 0.000

XIII PEKERJAAN INSTALASI AIR 0.000

XIV PEKERJAAN ALAT GANTUNG & KACA 0.000

XV PEKERJAAN TAMAN DAN HALAMAN 0.000

XVI JASA PERENC, PENGWS DAN PENGELOLAAN 0.000 0.00 0.00 0.00 0.00

TOTAL

0.000
RENCANA KENAIKAN PRESTASI DALAM 1 MINGGU 0.00 0.00 0.00 0.00 0.00

TOTAL PRESTASI AKHIR MINGGU 0.00 0.00 0.00 0.00 0.00


LAPORAN PELAKSANAA

NAMA PROYEK : PENGADAAN RUMAH TINGGAL KLASIK 2 LANTAI TYPE 155/380


LOKASI : MANDUNGAN, SRIMARTANI, PIYUNGAN, BANTUL, YK
TAHUN : 2018

MARET APRIL
NO NAMA PEKERJAAN BOBOT %
0 1 2 3 4
I PEKERJAAN PERSIAPAN 0.000 0.00 0.00

II PEKERJAAN TANAH DAN GALIAN 0.000 0.00 0.00 0.00

III PEKERJAAN PASANGAN PONDASI BATU KALI 0.000 0.00 0.00

IV PEKERJAAN BETON BERTULANG 0.000 0.00

V PEKERJAAN DINDING PASANGAN 0.000 0.00 0.00

VI PEKERJAAN PLESTERAN 0.000

VII PEKERJAAN CAT DAN POLITUR 0.000

VIII PEKERJAAN KUSEN & DAUN PINTU JENDELA 0.000

IX PEKERJAAN ATAP DAN RANGKA ATAP 0.000


X PEKERJAAN PLAFOND / LANGIT LANGIT 0.000

XI PEKERJAAN INSTALASI LISTRIK 0.000

XII PEKERJAAN KERAMIK LANTAI 0.000

XIII PEKERJAAN INSTALASI AIR 0.000

XIV PEKERJAAN ALAT GANTUNG & KACA 0.000

XV PEKERJAAN TAMAN DAN HALAMAN 0.000

XVI JASA PERENC, PENGWS DAN PENGELOLAAN 0.000 0.00 0.00 0.00 0.00

TOTAL

0.000
RENCANA KENAIKAN PRESTASI DALAM 1 MINGGU 0.00 0.00 0.00 0.00 0.00

TOTAL PRESTASI AKHIR MINGGU 0.00 0.00 0.00 0.00 0.00

SCHEDULE RENCANA DAN PELA

NAMA PROYEK : PENGADAAN RUMAH TINGGAL KLASIK 2 LANTAI TYPE 155/380


LOKASI : MANDUNGAN, SRIMARTANI, PIYUNGAN, BANTUL, YK
TAHUN : 2018
MARET APRIL
NO NAMA PEKERJAAN BOBOT %
0 1 2 3 4
I PEKERJAAN PERSIAPAN 0.000 0.00 0.00 0.00

II PEKERJAAN TANAH DAN GALIAN 0.000 0.00 0.00 0.00

III PEKERJAAN PASANGAN PONDASI BATU KALI 0.000 0.00 0.00

IV PEKERJAAN BETON BERTULANG 0.000

V PEKERJAAN DINDING PASANGAN 0.000 0.00

VI PEKERJAAN PLESTERAN 0.000

VII PEKERJAAN CAT DAN POLITUR 0.000

VIII PEKERJAAN KUSEN & DAUN PINTU JENDELA 0.000 0.00 0.00 0.00 0.00 0.00

IX PEKERJAAN ATAP DAN RANGKA ATAP 0.000

X PEKERJAAN PLAFOND / LANGIT LANGIT 0.000

XI PEKERJAAN INSTALASI LISTRIK 0.000

XII PEKERJAAN KERAMIK LANTAI 0.000

XIII PEKERJAAN INSTALASI AIR 0.000

XIV PEKERJAAN ALAT GANTUNG & KACA 0.000

XV PEKERJAAN TAMAN DAN HALAMAN 0.000


XVI JASA PERENC, PENGWS DAN PENGELOLAAN 0.000 0.00 0.00 0.00 0.00

RENCANA KENAIKAN
TOTAL BOBOT

RENCANA KENAIKAN PRESTASI DALAM 1 MINGGU 0.00 0.00 0.00 0.00 0.00

TOTAL PRESTASI AKHIR MINGGU 0.000 0.00 0.00 0.00 0.00 0.00
KENAIKAN DALAM PELAKSANAAN
TOTAL BOBOT

RENCANA KENAIKAN PRESTASI DALAM 1 MINGGU 0.00 0.00 0.00 0.00 0.00

TOTAL PRESTASI AKHIR MINGGU 0.00 0.00 0.00 0.00 0.00


PERENCANAAN

APRIL MEI JUNI


KETERANGAN
5 6 7 8 9 10 11 12 13 14 15

100%
0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


75%
0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00


50%
0.00 0.00 0.00

0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


25%
0.00 0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PELAKSANAAN

APRIL MEI JUNI


KETERANGAN
5 6 7 8 9 10 11 12 13 14 15

100%
0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00


75%
0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


50%
0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


25%
0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

NA DAN PELAKSANAAN
APRIL MEI JUNI
KETERANGAN
5 6 7 8 9 10 11 12 13 14 15

100%
0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


75%
0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00


50%
0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00


25%
0.00 0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0%

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
HARGA BAHAN BANGUNAN & UPAH (RAB)
HARGA BAHAN BANGUNAN
NO BAHAN SPESIFIKASI HARGA SATUAN
1 Kayu Terentang / Bekisting Lokal Rp 2,500,000.00 M³
2 Paku Seng Lokal Rp 30,000.00 Kg
3 Seng Bergelombang SNI Rp 75,000.00 Lb
4 Kayu Meranti 5/7 Lokal Rp 2,200,000.00 M³
5 Paku Usuk Reng Lokal Rp 30,000.00 Kg
6 Tanah Urug Lokal Rp 90,000.00 M³
7 Pasir Urug Lokal Rp 150,000.00 M³
8 Urug Sirtu Lokal Rp 160,000.00 M³
9 Batu Kali SNI Rp 220,000.00 M³
10 Kapur Pasang SNI Rp 259,500.00 M³
11 PC Holchim Rp 1,000.00 Kg
12 Batu Split 1/2 SNI Rp 185,000.00 M³
13 Pasir Pasang Lokal Rp 225,000.00 M³
14 Besi Beton SNI Rp 15,000.00 Kg
15 Bendrat SNI Rp 18,400.00 Kg
16 Paku 2" - 5" Lokal Rp 24,000.00 Kg
17 Minyak Bekisting Lokal Rp 8,500.00 Ltr
18 Plywood T=9mm Lokal Rp 100,000.00 Lbr
19 Kayu Dolken dia 8-10 /4M Lokal Rp 22,000.00 Btg
20 Bata Merah Lokal Rp 600.00 Bh
21 Plamir Tembok Sanyo / setara Rp 18,200.00 Kg
22 Cat Dasar Nippon paint Rp 45,000.00 Kg
23 Cat Penutup Nippon paint Rp 45,000.00 Kg
24 Politur Jago SNI Rp 50,000.00 Ltr
25 Politur Jadi Mowilex Pinguin/setara Rp 50,000.00 Ltr
26 Amplas SNI Rp 3,300.00 Bh
27 Kayu Bengkirai Balok Lokal Rp 12,500,000.00 M³
28 Kayu Bengkirai Papan Lokal Rp 10,000,000.00 M³
29 Penyambungan PAL PLN 1200 KWh SNI Rp 2,500,000.00 Set
30 Titik Lampu / Stop kontak Philips / Broco Rp 150,000.00 Set
31 Keramik 50x50 (Motif) KIA / Setara Rp 15,000.00 Bh
32 PC Warna Lokal Rp 10,000.00 Kg
33 Keramik 40x40 (Motif) KIA / Setara Rp 10,000.00 Bh
34 Angkur SNI Rp 9,000.00 Kg
35 Engsel Pintu Solid Rp 600,000.00 Bh
36 Kunci Tanam Antik Solid Rp 800,000.00 Bh
37 Kunci Tanam Biasa Solid Rp 500,000.00 Bh
38 Grendel Pintu Lokal Rp 30,000.00 Bh
39 Kaca Tebal 5mm SNI Rp 89,600.00 M²
Harga Upah Pekerja
NO PEKERJA KODE HARGA SATUAN
1 Pekerja / Tenaga @ Rp 72,000.00 OH / Hari
2 Tukang Batu @ Rp 84,000.00 OH / Hari
3 Kepala Tukang Batu @ Rp 90,000.00 OH / Hari
4 Tukang Besi @ Rp 85,000.00 OH / Hari
5 Kepala Tukang Besi @ Rp 90,000.00 OH / Hari
6 Tukang Kayu @ Rp 90,000.00 OH / Hari
7 Kepala Tukang Kayu @ Rp 96,000.00 OH / Hari
8 Tukang Cat @ Rp 85,000.00 OH / Hari
9 Kepala Tukang Cat @ Rp 90,000.00 OH / Hari
10 Tukang Pipa @ Rp 90,000.00 OH / Hari
11 Kepala Tukang Pipa @ Rp 96,000.00 OH / Hari
12 Tukang Gali @ Rp 115,000.00 OH / Hari
13 Mandor @ Rp 96,000.00 OH / Hari
)
PERHITUNGAN VOLUME PEKERJAAN
NO JENIS PEKERJAAN
I PEKERJAAN PERSIAPAN
1. MEMBERSIHKAN LAHAN & MERATAKAN TANAH

2. PAGAR PENGAMAN SENG

3. PASANG BOUWPLANK

II PEKERJAAN TANAH DAN GALIAN


1. PEKERJAAN GALIAN TANAH
2. PEK. URUG KEMBALI GALIAN TANAH

III PEKERJAAN PONDASI


PONDASI BATU KALI
1. VOLUME PONDASI BK 1 PC : 3 KP : 10 PS
2. VOLUME BATU KOSONG

PONDASI FOOTPLAT
1. VOLUME PONDASI FOOTPLAT

IV PEKERJAAN BETON BERTULANG


A. PEKERJAAN BETON BERTULANG
1. PEKERJAAN SLOOF 15/25

2. PEKERJAAN KOLOM
2.1 PEKERJAAN KOLOM K1 dia 50 CM

2.2 PEKERJAAN KOLOM K2 40/40

3. PEKERJAAN BALOK LANTAI


3.1 PEKERJAAN BALOK B1 30/60
3.2 PEKERJAAN BALOK B2 25/45

4. PEKERJAAN BALOK DAG 25/45

5. PEKERJAAN RINGBALK 15/20 (KUBAH)

6. PEKERJAAN BETON TANGGA

7. PEKERJAAN PLAT LANTAI T = 12 CM

8. PEKERJAAN BETON MULDING

9. PEKERJAAN BALOK MENARA 15/25

10. PEKERJAAN BETON KUBAH & MENARA

V PEKERJAAN DINDING PASANGAN


1. PASANGAN BATA MERAH TRASRAAM 1 PC : 3 PS

2.       PAS. BATA MERAH , 1 PC : 3 KP : 10 PS


VI PEKERJAAN PLESTERAN
1. PEKERJAAN PLESTERAN DINDING TEBAL 15 MM,
CAMP. 1PC : 4PS

2. LIST SUDUT PLESTERAN

VII PEKERJAAN CAT


1. PEKERJAAN CAT DINDING INTERIOR EKSTERIOR

2.PEKERJAAN CAT PLAFOND & PLAT LANTAI

3. PEKERJAAN POLITUR KUSEN PINTU DAN JENDELA

4. PEKERJAAN POLITUR PANIL PINTU DAN JENDELA

VIII PEKERJAAN KUSEN PINTU & JENDELA


1. PEKERJAAN KUSEN

2. PEKERJAAN DAUN PINTU JENDELA


IX PEKERJAAN INSTALASI LISTRIK

X PEKERJAAN LANTAI
1. LANTAI KERAMIK 50x50

2. LANTAI KERAMIK 40x40

XI PEKERJAAN ALAT GANTUNG & KACA


1. BESI ANGKUR

2. ALAT GANTUNG PINTU & JENDELA


3.1 PINTU

3.2 JENDELA
TUNGAN VOLUME PEKERJAAN
PEHITUNGAN VOLUME

> LUAS LAHAN KAPLING = 16 M × 16 M


256 M²

> PANJANG = 110 M , TINGGI = 1.8 M


110 M¹

> 2 (P + L) = 2 (16 M + 16 M)
64 M¹

PONDASI BATU KALI


> VOLUME GALIAN TANAH
L. TAMPANG GALIAN PONDASI TENGAH
((1.3 + 1.58) : 2) × 0.7
1.008 M³

L. TAMPANG GALIAN PONDASI TEPI


((0.73 + 0.87) : 2) × 0.7
0.56 M³

> PANJANG PONDASI


PONDASI TENGAH
67 M¹

PONDASI TEPI
56 M¹

> P. KESELURUHAN = P. TENGAH + P. TEPI


123 M¹

> VOLUME GALIAN PONDASI


PONDASI TENGAH
L. PENAMPANG × P. PONDASI
67.536 M³

PONDASI TEPI
L. PENAMPANG × P. PONDASI
31.36 M³

> VOLUME GALIAN PONDASI BK TOTAL


98.896 M³

PONDASI FOOTPLAT
JUMLAH FOOTPLAT = 38 Bh
> LUAS PENAMPANG GALIAN
1.4 x 1.3
1.82 M²

> VOLUME GALIAN PONDASI


L. PENAMPANG x PANJANG
1.82 x 1.4
2.548 M³

> VOLUME GALIAN PONDASI FOOTPLAT TOTAL


38 x 2.548
96.824 M³

> VOLUME GALIAN PONDASI KESELURUHAN (BK + FOOTPLAT)


195.720 M³
VOLUME URUG TANAH PONDASI
> URUG TANAH GALIAN PONDASI BK
1/4 × V. GALIAN PONDASI BK
24.724 M³

> URUG TANAH GALIAN PONDASI FOOTPLAT


1.296 x 38
49.248 M³

> VOLUME TOTAL URUG TANAH GALIAN PONDASI


73.97 M³

VOLUME URUG TANAH BAWAH LANTAI


TEBAL URUG TANAH × LUAS LANTAI
0.98 x 200
196 M³

VOLUME URUG SIRTU


> URUG SIRTU BAWAH PONDASI FOOTPLAT
6.338 M³

VOLUME URUG PASIR


> URUG PASIR BAWAH PONDASI BK
PONDASI TENGAH
0.066 x 67
4.39 M³

PONDASI TEPI
0.014 x 56
0.76 M³

> URUG PASIR BAWAH LANTAI


LANTAI 1
40 M³

LANTAI 2
10.5 M³

> URUG PASIR KESELURUHAN


55.65 M³

> V. PONDASI TENGAH + V. PONDASI TEPI


0.87 × 67 + 0.56 × 56
89.65 M³

> V. PONDASI TRAP TANGGA SAMPING


6.4 M³

> VOLUME PONDASI BK KESELURUHAN


96.05 M³

> PONDASI TENGAH


PENAMPANG x PANJANG
0.272 x 67
18.224 M³

> PONDASI TEPI


PENAMPANG x PANJANG
0.151 x 56
8.456 M³

> VOLUME KESELURUHAN


26.68 M³

JUMLAH FOOTPLAT = 38 Bh
> VOLUME PONDASI FOOTPLAT UTUH (1)
0.59 M³

> VOLUME KESELURUHAN (38)


22.42 M³

> PANJANG SLOOF


123 M¹

n. TITIK KOLOM × TINGGI KOLOM


(14 x 10.3) + (4 x 11.1) + (2 x 11.7)
212 M¹

n. TITIK KOLOM × TINGGI KOLOM


(12 x 10.3) + (6 x 11.7)
193.8 M¹

16 M¹
140 M¹

186 M¹

35.67 M¹

0.14 M³

0.12 x LUAS PLAT LANTAI


34.66 M³

LUAS PENAMPANG x PANJANG


0.03 x 166.6
4.998 M³

149 M¹

29.87 M³

> LANTAI 1
> PAS. TRASRAAM
110.3 M²

> LANTAI 2
> PAS. TRASRAAM
100.68 M²

TOTAL PAS TRASRAAM


210.98 M²

> LANTAI 1
40.77 M²

> LANTAI 2
30.23 M²

TOTAL PAS BATA MERAH


71 M²
2 × LUAS PAS. BM & TRASRAAM
2 × 271.05
542.1 M²

LIST SUDUT
500.98 M¹

> LUAS TOTAL


1105.46 M²

352.2 M²

PJ KUSEN TEPI × PENAMPANG


283.12 × 0.24
68 M²

SAMA DENGAN LUAS TOTAL PANIL


39.46 M²

JADI JUMLAH CAT POLITUR KESELURUHAN


107.46 M²

JADI V. KUSEN
0.08 × 0.12 × 283.12
2.72 M³
INVENTARISASI ALAT GANTUNG

ENGSEL : BESAR (PINTU) : 3 x 9 = 27 Bh


KECIL (JENDELA) :-

GRENDEL : BESAR (PINTU) :2x9 = 18 Bh


KECIL (JENDELA) :-

SLOOT PINTU : 1 x 9 = 9 Bh

BESI DOOK : 2 x 9 = 18 Bh

ANGKUR : PINTU : 54 Bh
JENDELA : 246 Bh

1. BIAYA PENYAMBUNGAN PAL PLN 1200 KWh


2. TITIK LAMPU = 38
3. STOP KONTAK = 10 BUAH (SUDAH TERMASUK BIAYA TITIK LAMPU)
4. LAMPU SL = 12 WATT = 29 BUAH
10 WATT = 5 BUAH
8 WATT = 4 BUAH

L. BIDANG KERAMIK 50x50


322.07 M²

L. BIDANG KERAMIK 40x40


45.6 M²

1. ANGKUR KUSEN = 300 Bh = 60Kg


1. ENGSEL PINTU (BESAR)
JUMLAH PINTU × 3
9×3
27 Bh

2. SELOT PINTU
JUMLAH PINTU x 1
9x1
9 Bh

KUNCI TANAM ANTIK = 3 Bh


SELOT BIASA = 6 Bh

3. GRENDEL PINTU (BESAR)


JUMLAH PINTU × 2
9x2
18 Bh

1. KACA JENDELA
41.33 M²
ANALISA HARGA SATUAN PEKERJAAN
I PEKERJAAN PERSIAPAN
1. An1. MEMBERSIHKAN LAHAN & MERATAKAN TANAH /M²
0.100 OH PEKERJA @ Rp 72,000.00
0.050 OH MANDOR @ Rp 96,000.00

2. AnLn. PAGAR PENGAMAN SENG /M¹


Bahan
0.012 M³ KAYU BEKISTING @ Rp 2,500,000.00
0.200 Kg PAKU SENG @ Rp 30,000.00
1.500 Lb SENG BERGELOMBANG @ Rp 75,000.00
Upah
0.100 OH TUKANG KAYU @ Rp 90,000.00
0.050 OH PEKERJA @ Rp 72,000.00
0.025 OH MANDOR @ Rp 96,000.00

3. An2. PASANG BOUWPLANK /M¹


Bahan
0.012 M³ KAYU MERANTI 5/7 @ Rp 2,200,000.00
0.020 Kg PAKU USUK/RENG @ Rp 30,000.00
0.007 M³ KAYU BEKISTING @ Rp 2,500,000.00
Upah
0.100 OH TUKANG KAYU @ Rp 90,000.00
0.010 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.100 OH PEKERJA @ Rp 72,000.00
0.005 OH MANDOR @ Rp 96,000.00

II PEKERJAAN TANAH
1. An3. GALIAN TANAH PONDASI /M³
0.400 OH PEKERJA @ Rp 72,000.00
0.040 OH MANDOR @ Rp 96,000.00

2. An9. URUG KEMBALI GALIAN PONDASI /M³


0.192 OH PEKERJA @ Rp 72,000.00
0.019 OH MANDOR @ Rp 96,000.00

3. AnLn. URUG TANAH BAWAH LANTAI /M³


Bahan
1.350 M³ TANAH URUG @ Rp 90,000.00
Upah
0.360 OH PEKERJA @ Rp 72,000.00
0.012 OH MANDOR @ Rp 96,000.00

4. An10. URUG PASIR /M³


Bahan
1.200 M³ PASIR URUG @ Rp 150,000.00
Upah
0.300 OH PEKERJA @ Rp 72,000.00
0.010 OH MANDOR @ Rp 96,000.00

5. An11. URUG SIRTU /M³


Bahan
1.200 M³ SIRTU @ Rp 160,000.00
Upah
0.250 OH PEKERJA @ Rp 72,000.00
0.025 OH MANDOR @ Rp 96,000.00

III PEKERJAAN PONDASI


1. An12. PEKERJAAN PASANGAN PONDASI BATU KALI, 1PC : 3KP: 10PS /M³
Bahan
1.100 M³ BATU KALI @ Rp 220,000.00
0.147 M³ KAPUR @ Rp 259,500.00
0.492 M³ PASIR URUG @ Rp 150,000.00
61.000 Kg PC @ Rp 1,000.00
Upah
0.600 OH TUKANG BATU @ Rp 84,000.00
0.067 OH KEPALA TUKANG BATU @ Rp 90,000.00
1.500 OH PEKERJA @ Rp 72,000.00
0.075 OH MANDOR @ Rp 96,000.00

2. An15. PEKERJAAN PASANGAN PONDASI BATU KOSONG /M³


Bahan
1.200 M³ BATU KALI @ Rp 220,000.00
0.300 M³ PASIR URUG @ Rp 150,000.00
Upah
0.390 OH TUKANG BATU @ Rp 84,000.00
0.039 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.780 OH PEKERJA @ Rp 72,000.00
0.039 OH MANDOR @ Rp 96,000.00

3. An101. MEMBUAT BETON DENGAN MUTU K 225/M³


Bahan
0.650 M³ BATU SPLIT 1/2 @ Rp 185,000.00
0.650 M³ PASIR PASANG @ Rp 225,000.00
388.000 Kg PC @ Rp 1,000.00
Upah
1.000 OH TUKANG BATU @ Rp 84,000.00
0.1000 OH KEPALA TUKANG BATU @ Rp 90,000.00
6.000 OH PEKERJA @ Rp 72,000.00
0.3000 OH MANDOR @ Rp 96,000.00

4. An100. PEMBESIAN DENGAN BESI POLOS / ULIR / Kg


Bahan
1.050 Kg BESI BETON @ Rp 15,000.00
0.015 Kg BENDRAT @ Rp 18,400.00
Upah
0.007 OH TUKANG BESI @ Rp 85,000.00
0.0007 OH KEPALA TUKANG BESI @ Rp 90,000.00
0.007 OH PEKERJA @ Rp 72,000.00
0.0003 OH MANDOR @ Rp 96,000.00

5. AnLn. PASANG BEKESTING UNTUK FOOTPLAT/M²


Bahan
0.030 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.400 Kg PAKU 2"-5" @ Rp 24,000.00
0.200 Ltr MINYAK BEKESTING @ Rp 8,500.00
Upah
0.007 OH TUKANG KAYU @ Rp 90,000.00
0.0007 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.007 OH PEKERJA @ Rp 72,000.00
0.0003 OH MANDOR @ Rp 96,000.00

6. An115i. MEMBUAT BETON FOOTPLAT/M³


Bahan
1.000 M³ CAMPURAN BETON K 225 @ Rp 1,444,810.00
106.000 Kg BESI BETON POLOS @ Rp 17,216.80
8.330 M² BEKESTING FOOTPLAT @ Rp 99,953.00

IV PEKERJAAN BETON BERTULANG


1. An113i. PEKERJAAN BETON BERTULANG 15/25 (SLOOF & BALOK MENARA) /M¹
Bahan
0.00681 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.04540 Kg PAKU 2"-5" @ Rp 24,000.00
8.17200 Kg BESI BETON @ Rp 15,000.00
0.11350 Kg BENDRAT @ Rp 18,400.00
12.48500 Kg PC @ Rp 1,000.00
0.03410 M³ BATU SPLIT @ Rp 185,000.00
0.02043 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.033 OH TUKANG BATU @ Rp 84,000.00
0.033 OH TUKANG KAYU @ Rp 90,000.00
0.033 OH TUKANG BESI @ Rp 85,000.00
0.010 OH KEP. TUKANG @ Rp 90,000.00
0.100 OH PEKERJA @ Rp 72,000.00
0.005 OH MANDOR @ Rp 96,000.00

2. An112i. PEKERJAAN KOLOM BETON BERTULANG dia 50 CM /M¹


Bahan
0.0410 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.2060 Kg PAKU 2"-5" @ Rp 24,000.00
61.9830 Kg BESI BETON @ Rp 15,000.00
9.2975 Kg BENDRAT @ Rp 18,400.00
82.6611 Kg PC @ Rp 1,000.00
0.1859 M³ BATU SPLIT @ Rp 185,000.00
0.1239 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.020 OH TUKANG BATU @ Rp 84,000.00
0.020 OH TUKANG KAYU @ Rp 90,000.00
0.020 OH TUKANG BESI @ Rp 85,000.00
0.006 OH KEPALA TUKANG @ Rp 90,000.00
0.060 OH PEKERJA @ Rp 72,000.00
0.003 OH MANDOR @ Rp 96,000.00

3. An112i. PEKERJAAN KOLOM BETON BERTULANG 40/40 /M¹


Bahan
0.0264 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.1322 Kg PAKU 2"-5" @ Rp 24,000.00
39.2231 Kg BESI BETON @ Rp 15,000.00
5.9504 Kg BENDRAT @ Rp 18,400.00
52.8925 Kg PC @ Rp 1,000.00
0.1190 M³ BATU SPLIT @ Rp 185,000.00
0.0793 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.020 OH TUKANG BATU @ Rp 84,000.00
0.020 OH TUKANG KAYU @ Rp 90,000.00
0.020 OH TUKANG BESI @ Rp 85,000.00
0.006 OH KEPALA TUKANG @ Rp 90,000.00
0.060 OH PEKERJA @ Rp 72,000.00
0.003 OH MANDOR @ Rp 96,000.00

4. An113i. PEKERJAAN RINGBALK BETON BERTULANG 15/20 /M¹


Bahan
0.0040 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.0266 Kg PAKU 2"-5" @ Rp 24,000.00
4.7880 Kg BESI BETON @ Rp 15,000.00
0.0665 Kg BENDRAT @ Rp 18,400.00
7.3150 Kg PC @ Rp 1,000.00
0.0190 M³ BATU SPLIT @ Rp 185,000.00
0.0120 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.033 OH TUKANG BATU @ Rp 84,000.00
0.033 OH TUKANG KAYU @ Rp 90,000.00
0.033 OH TUKANG BESI @ Rp 85,000.00
0.010 OH KEP. TUKANG @ Rp 90,000.00
0.100 OH PEKERJA @ Rp 72,000.00
0.005 OH MANDOR @ Rp 96,000.00

5. An113i. PEKERJAAN BALOK LANTAI BETON BERTULANG 30/60 /M¹


Bahan
0.0327 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.2181 Kg PAKU 2"-5" @ Rp 24,000.00
39.2727 Kg BESI BETON @ Rp 15,000.00
4.9090 Kg BENDRAT @ Rp 18,400.00
60.0000 Kg PC @ Rp 1,000.00
0.1636 M³ BATU SPLIT @ Rp 185,000.00
0.0981 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.033 OH TUKANG BATU @ Rp 84,000.00
0.033 OH TUKANG KAYU @ Rp 90,000.00
0.033 OH TUKANG BESI @ Rp 85,000.00
0.010 OH KEP. TUKANG @ Rp 90,000.00
0.100 OH PEKERJA @ Rp 72,000.00
0.005 OH MANDOR @ Rp 96,000.00

6. An113i. PEKERJAAN BALOK LANTAI BETON BERTULANG 25/45 /M¹


Bahan
0.0204 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.1363 Kg PAKU 2"-5" @ Rp 24,000.00
24.5454 Kg BESI BETON @ Rp 15,000.00
0.3409 Kg BENDRAT @ Rp 18,400.00
37.5000 Kg PC @ Rp 1,000.00
0.1022 M³ BATU SPLIT @ Rp 185,000.00
0.0613 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.033 OH TUKANG BATU @ Rp 84,000.00
0.033 OH TUKANG KAYU @ Rp 90,000.00
0.033 OH TUKANG BESI @ Rp 85,000.00
0.010 OH KEP. TUKANG @ Rp 90,000.00
0.100 OH PEKERJA @ Rp 72,000.00
0.005 OH MANDOR @ Rp 96,000.00

7. An111. PEKERJAAN TANGGA BETON BERTULANG (200Kg BESI + BEKESTING) /M³


Bahan
0.2500 M³ KAYU TERENTANG @ Rp 2,500,000.00
3.0000 Kg PAKU 2"-5" @ Rp 24,000.00
1.2000 Ltr MINYAK BEKESTING @ Rp 8,500.00
200.0000 Kg BESI BETON @ Rp 15,000.00
3.0000 Kg BENDRAT @ Rp 18,400.00
323.0000 Kg PC @ Rp 1,000.00
0.7800 M³ BATU SPLIT @ Rp 185,000.00
0.5200 M³ PASIR PASANG @ Rp 225,000.00
0.1050 M³ KAYU MERANTI 5/7 @ Rp 2,200,000.00
2.5000 Lbr PLYWOOD T=9mm @ Rp 100,000.00
14.0000 Btg KAYU DOLKEN dia 8-10/4M @ Rp 22,000.00
Upah
0.350 OH TUKANG BATU @ Rp 84,000.00
2.300 OH TUKANG KAYU @ Rp 90,000.00
1.400 OH TUKANG BESI @ Rp 85,000.00
0.405 OH KEP. TUKANG @ Rp 90,000.00
5.600 OH PEKERJA @ Rp 72,000.00
0.202 OH MANDOR @ Rp 96,000.00

8. AnLn. MEMBUAT BETON DENGAN MUTU K 225/M³


Bahan
0.650 M³ BATU SPLIT 1/2 @ Rp 185,000.00
0.650 M³ PASIR PASANG @ Rp 225,000.00
388.000 Kg PC @ Rp 1,000.00
Upah
1.000 OH TUKANG BATU @ Rp 84,000.00
0.1000 OH KEPALA TUKANG BATU @ Rp 90,000.00
6.000 OH PEKERJA @ Rp 72,000.00
0.3000 OH MANDOR @ Rp 96,000.00

9. An100. PEMBESIAN DENGAN BESI POLOS / ULIR / Kg


Bahan
1.050 Kg BESI BETON @ Rp 15,000.00
0.015 Kg BENDRAT @ Rp 18,400.00
Upah
0.007 OH TUKANG BESI @ Rp 85,000.00
0.0007 OH KEPALA TUKANG BESI @ Rp 90,000.00
0.007 OH PEKERJA @ Rp 72,000.00
0.0003 OH MANDOR @ Rp 96,000.00

10. An106. PASANG BEKESTING UNTUK PLAT/M²


Bahan
0.040 M³ KAYU TERENTANG @ Rp 2,500,000.00
0.400 Kg PAKU 2"-5" @ Rp 24,000.00
0.200 Ltr MINYAK BEKESTING @ Rp 8,500.00
0.015 M³ KAYU MERANTI 5/7 @ Rp 2,200,000.00
0.350 Lbr PLYWOOD T=9mm @ Rp 100,000.00
6.000 Btg KAYU DOLKEN dia 8-10/4M @ Rp 22,000.00
Upah
0.330 OH TUKANG KAYU @ Rp 90,000.00
0.0330 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.320 OH PEKERJA @ Rp 72,000.00
0.0060 OH MANDOR @ Rp 96,000.00

11. An105i. MEMBUAT BETON BETON BERTULANG PLAT/M³


Bahan
1.000 M³ CAMPURAN BETON K 225 @ Rp 1,444,810.00
106.000 Kg BESI BETON POLOS @ Rp 17,216.80
8.330 M² BEKESTING PLAT @ Rp 385,144.00

V PEKERJAAN DINDING PASANGAN


1. An18. PEKERJAAN BATA MERAH TRASRAAM 1PC : 3 PS /M²
Bahan
30.000 Bj BATA MERAH @ Rp 600.00
14.370 Kg PC @ Rp 1,000.00
0.040 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.100 OH TUKANG BATU @ Rp 84,000.00
0.010 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.320 OH PEKERJA @ Rp 72,000.00
0.015 OH MANDOR @ Rp 96,000.00

2. An23. PEKERJAAN PASANG BATA MERAH 1PC : 3KP : 10PS /M²


Bahan
80.000 Bj BATA MERAH @ Rp 600.00
4.500 Kg PC @ Rp 1,000.00
0.015 M³ KAPUR @ Rp 259,500.00
0.050 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.100 OH TUKANG BATU @ Rp 84,000.00
0.010 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.320 OH PEKERJA @ Rp 72,000.00
0.015 OH MANDOR @ Rp 96,000.00

VI PEKERJAAN PLESTERAN
1. An28. PEKERJAAN PLESTERAN DINDING BM , TEBAL 20 MM , 1PC : 4PS /M²
Bahan
6.916 Kg PC @ Rp 1,000.00
0.027 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.150 OH TUKANG BATU @ Rp 84,000.00
0.015 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.200 OH PEKERJA @ Rp 72,000.00
0.010 OH MANDOR @ Rp 96,000.00

2. An37. PEKERJAAN PLESTERAN SKONING , 1PC : 2PS /M¹


Bahan
0.500 Kg PC @ Rp 1,000.00
0.002 M³ PASIR PASANG @ Rp 225,000.00
Upah
0.038 OH TUKANG BATU @ Rp 84,000.00
0.038 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.057 OH PEKERJA @ Rp 72,000.00
0.002 OH MANDOR @ Rp 96,000.00

VII PEKERJAAN CAT


1. An94. PEKERJAAN CAT TEMBOK BARU ( 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 CAT) & PLAFOND /M²
Bahan
0.100 Kg PLAMIR TEMBOK @ Rp 18,200.00
0.100 Kg CAT DASAR NIPPON PAINT @ Rp 45,000.00
0.260 Kg CAT PENUTUP NIPPON PAINT @ Rp 45,000.00
Upah
0.0630 OH TUKANG CAT @ Rp 85,000.00
0.0063 OH KEPALA TUKANG CAT @ Rp 90,000.00
0.0200 OH PEKERJA @ Rp 72,000.00
0.0025 OH MANDOR @ Rp 96,000.00

2. An93. PEKERJAAN PELABURAN BIDANG KAYU DENGAN POLITUR /M²


Bahan
0.150 Ltr POLITUR JAGO @ Rp 50,000.00
0.372 Ltr POLITUR JADI MOWILEX @ Rp 50,000.00
2.000 Lb AMPLAS @ Rp 3,300.00
Upah
0.0600 OH TUKANG CAT @ Rp 85,000.00
0.0160 OH KEPALA TUKANG CAT @ Rp 90,000.00
0.0025 OH MANDOR @ Rp 96,000.00

VIII PEKERJAAN KUSEN & DAUN PINTU JENDELA


1. An40. PEKERJAAN KUSEN PINTU & JENDELA KAYU BENGKIRAI /M³
Bahan
1.200 M³ KAYU BENGKIRAI BALOK @ Rp 12,500,000.00
Upah
18.000 OH TUKANG KAYU @ Rp 90,000.00
2.000 OH KEPALA TUKANG KAYU @ Rp 96,000.00
6.000 OH PEKERJA @ Rp 72,000.00
0.300 OH MANDOR @ Rp 96,000.00

2. AnLn. PASANG PINTU PANEL KAYU BENGKIRAI /M²


Bahan
0.040 M³ KAYU BENGKIRAI PAPAN @ Rp 10,000,000.00
Upah
2.500 OH TUKANG KAYU @ Rp 90,000.00
0.250 OH KEPALA TUKANG KAYU @ Rp 96,000.00
1.000 OH PEKERJA @ Rp 72,000.00
0.050 OH MANDOR @ Rp 96,000.00

3. AnLn. PASANG PINTU & JENDELA KACA KAYU BENGKIRAI /M²


Bahan
0.035 M³ KAYU BENGKIRAI PAPAN @ Rp 10,000,000.00
Upah
2.000 OH TUKANG KAYU @ Rp 90,000.00
0.200 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.800 OH PEKERJA @ Rp 72,000.00
0.040 OH MANDOR @ Rp 96,000.00

IX PEKERJAAN INSTALASI LISTRIK


1. PENYAMBUNGAN PAL PLN 1200 KWh @ Rp 2,500,000.00
2. TITIK LAMPU + STOP KONTAK @ Rp 150,000.00
X PEKERJAAN KERAMIK
1. An89i. PAKERJAAN PASANG KERAMIK LANTAI 50x50 CM /M²
Bahan
6.250 Bh UBIN KERAMIK 50/50 (MOTIF) @ Rp 15,000.00
11.280 Kg PC @ Rp 1,000.00
0.042 M³ PASIR pasang @ Rp 225,000.00
1.500 Kg PC WARNA @ Rp 10,000.00
Upah
0.350 OH TUKANG BATU @ Rp 84,000.00
0.035 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.620 OH PEKERJA @ Rp 72,000.00
0.030 OH MANDOR @ Rp 96,000.00

2. An89i. PAKERJAAN PASANG KERAMIK LANTAI 40×40 CM /M²


Bahan
6.250 Bh UBIN KERAMIK 40/40 (MOTIF) @ Rp 10,000.00
11.280 Kg PC @ Rp 1,000.00
0.042 M³ PASIR pasang @ Rp 225,000.00
1.500 Kg PC WARNA @ Rp 10,000.00
Upah
0.350 OH TUKANG BATU @ Rp 84,000.00
0.035 OH KEPALA TUKANG BATU @ Rp 90,000.00
0.620 OH PEKERJA @ Rp 72,000.00
0.030 OH MANDOR @ Rp 96,000.00

XI PEKERJAAN PASANG ALAT GANTUNG & KACA


PEKERJAAN PASANG ALAT GANTUNG KUDA KUDA & KUSEN
1. AnLn. PASANG ANGKUR /Kg
Bahan
1.000 Kg ANGKUR @ Rp 9,000.00

PEKERJAAN PASANG ALAT GANTUNG PINTU


1. An82. PEKERJAAN PASANG ENGSEL PINTU /Bj
Bahan
1.000 Bh ENGSEL PINTU "SOLID" @ Rp 600,000.00
Upah
0.1500 OH TUKANG KAYU @ Rp 90,000.00
0.0150 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.0150 OH PEKERJA @ Rp 72,000.00
0.0006 OH MANDOR @ Rp 96,000.00

2. An79. PASANG KUNCI TANAM ANTIK /Bh


Bahan
1.000 Bh KUNCI TANAM ANTIK @ Rp 800,000.00
Upah
0.600 OH TUKANG KAYU @ Rp 90,000.00
0.060 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.060 OH PEKERJA @ Rp 72,000.00
0.003 OH MANDOR @ Rp 96,000.00

3. An85. PASANG KUNCI SELOT BIASA /Bh


Bahan
1.000 Bh KUNCI TANAM BIASA @ Rp 500,000.00
Upah
0.200 OH TUKANG KAYU @ Rp 90,000.00
0.020 OH KEPALA TUKANG KAYU @ Rp 96,000.00
0.020 OH PEKERJA @ Rp 72,000.00
0.001 OH MANDOR @ Rp 96,000.00

4. AnLn. PASANG GRENDEL PINTU /Bh


Bahan
1.000 Bh GRENDEL PINTU "SOLID" @ Rp 30,000.00
Upah
0.1000 OH TUKANG KAYU @ Rp 90,000.00
0.0100 OH KEPALA TUKANG KAYU @ Rp 96,000.00

PEKERJAAN PASANG KACA


1. An86. PEKERJAAN PASANG KACA TEBAL 5 MM /M²
Bahan
1.100 M² KACA TEBAL 5 MM @ Rp 89,600.00
Upah
0.1500 OH TUKANG KAYU @ Rp 90,000.00
0.0150 OH KEPALA TUKANG @ Rp 96,000.00
0.0150 OH PEKERJA @ Rp 72,000.00
0.0006 OH MANDOR @ Rp 96,000.00
JAAN

Rp 7,200.00
Rp 4,800.00
Rp 12,000.00 /M²

Rp 30,000.00
Rp 6,000.00
Rp 112,500.00

Rp 9,000.00
Rp 3,600.00
Rp 2,400.00
Rp 163,500.00 /M¹

Rp 26,400.00
Rp 600.00
Rp 17,500.00

Rp 9,000.00
Rp 960.00
Rp 7,200.00
Rp 480.00
Rp 62,140.00 /M¹

Rp 28,800.00
Rp 3,840.00
Rp 32,640.00 /M³

Rp 13,824.00
Rp 1,824.00
Rp 15,648.00 /M³

Rp 121,500.00

Rp 25,920.00
Rp 1,152.00
Rp 148,572.00 /M³

Rp 180,000.00
Rp 21,600.00
Rp 960.00
Rp 202,560.00 /M³

Rp 192,000.00

Rp 18,000.00
Rp 2,400.00
Rp 212,400.00 /M³

Rp 242,000.00
Rp 38,146.50
Rp 73,800.00
Rp 61,000.00

Rp 50,400.00
Rp 6,030.00
Rp 108,000.00
Rp 7,200.00
Rp 586,576.50 /M³

Rp 264,000.00
Rp 45,000.00

Rp 32,760.00
Rp 3,510.00
Rp 56,160.00
Rp 3,744.00
Rp 405,174.00 /M³

Rp 120,250.00
Rp 146,250.00
Rp 388,000.00

Rp 84,000.00
Rp 9,000.00
Rp 432,000.00
Rp 28,800.000
Rp 1,208,300.00 /M³

Rp 15,750.00
Rp 276.00

Rp 595.00
Rp 63.00
Rp 504.00
Rp 28.800
Rp 17,216.80 /M³

Rp 75,000.00
Rp 9,600.00
Rp 1,700.00

Rp 630.00
Rp 67.20
Rp 504.00
Rp 28.800
Rp 87,530.00 /M³

Rp 1,444,810.00
Rp 1,824,980.80
Rp 832,608.49
Rp 4,102,399.29 /M³

Rp 17,025.00
Rp 1,089.60
Rp 122,580.00
Rp 2,088.40
Rp 12,485.00
Rp 6,308.50
Rp 4,596.75

Rp 2,772.00
Rp 2,970.00
Rp 2,805.00
Rp 900.00
Rp 7,200.00
Rp 480.00
Rp 183,300.25 /M¹

Rp 102,500.00
Rp 4,944.00
Rp 929,745.00
Rp 171,074.00
Rp 82,661.10
Rp 34,391.50
Rp 27,877.50

Rp 1,680.00
Rp 1,800.00
Rp 1,700.00
Rp 540.00
Rp 4,320.00
Rp 288.00
Rp 1,363,521.10 /M¹

Rp 66,000.00
Rp 3,172.80
Rp 588,346.50
Rp 109,487.36
Rp 52,892.50
Rp 22,015.00
Rp 17,842.50

Rp 1,680.00
Rp 1,800.00
Rp 1,700.00
Rp 540.00
Rp 4,320.00
Rp 288.00
Rp 870,084.66 /M¹

Rp 10,000.00
Rp 638.40
Rp 71,820.00
Rp 1,223.60
Rp 7,315.00
Rp 3,515.00
Rp 2,700.00

Rp 2,772.00
Rp 2,970.00
Rp 2,805.00
Rp 900.00
Rp 7,200.00
Rp 480.00
Rp 114,339.00 /M¹

Rp 81,750.00
Rp 5,234.40
Rp 589,090.50
Rp 90,325.60
Rp 60,000.00
Rp 30,266.00
Rp 22,072.50

Rp 2,772.00
Rp 2,970.00
Rp 2,805.00
Rp 900.00
Rp 7,200.00
Rp 480.00
Rp 895,866.00 /M¹

Rp 51,000.00
Rp 3,271.20
Rp 368,181.00
Rp 6,272.56
Rp 37,500.00
Rp 18,907.00
Rp 13,792.50

Rp 2,772.00
Rp 2,970.00
Rp 2,805.00
Rp 900.00
Rp 7,200.00
Rp 480.00
Rp 516,051.26 /M¹

Rp 625,000.00
Rp 72,000.00
Rp 10,200.00
Rp 3,000,000.00
Rp 55,200.00
Rp 323,000.00
Rp 144,300.00
Rp 117,000.00
Rp 231,000.00
Rp 250,000.00
Rp 308,000.00

Rp 29,400.00
Rp 207,000.00
Rp 119,000.00
Rp 36,450.00
Rp 403,200.00
Rp 19,392.00
Rp 5,950,142.00 /M³

Rp 120,250.00
Rp 146,250.00
Rp 388,000.00

Rp 84,000.00
Rp 9,000.00
Rp 432,000.00
Rp 28,800.000
Rp 1,208,300.00 /M³

Rp 15,750.00
Rp 276.00

Rp 595.00
Rp 63.00
Rp 504.00
Rp 28.800
Rp 17,216.80 /M³

Rp 100,000.00
Rp 9,600.00
Rp 1,700.00
Rp 33,000.00
Rp 35,000.00
Rp 132,000.00

Rp 29,700.00
Rp 3,168.00
Rp 23,040.00
Rp 576.000
Rp 367,784.00 /M³

Rp 1,444,810.00
Rp 1,824,980.80
Rp 3,208,249.52
Rp 6,478,040.32 /M³
Rp 18,000.00
Rp 14,370.00
Rp 9,000.00

Rp 8,400.00
Rp 900.00
Rp 23,040.00
Rp 1,440.00
Rp 75,150.00 /M²

Rp 48,000.00
Rp 4,500.00
Rp 3,892.50
Rp 11,250.00

Rp 8,400.00
Rp 900.00
Rp 23,040.00
Rp 1,440.00
Rp 101,422.50 /M²

Rp 6,916.00
Rp 5,985.00

Rp 12,600.00
Rp 1,350.00
Rp 14,400.00
Rp 960.00
Rp 42,211.00 /M²

Rp 500.00
Rp 450.00

Rp 3,192.00
Rp 3,420.00
Rp 4,104.00
Rp 192.00
Rp 11,858.00 /M¹

AFOND /M²

Rp 1,820.00
Rp 4,500.00
Rp 11,700.00
Rp 5,355.00
Rp 567.00
Rp 1,440.00
Rp 240.00
Rp 25,622.00 /M²

Rp 7,500.00
Rp 18,600.00
Rp 6,600.00

Rp 5,100.00
Rp 1,440.00
Rp 240.00
Rp 39,480.00 /M²

Rp 15,000,000.00

Rp 1,620,000.00
Rp 192,000.00
Rp 432,000.00
Rp 28,800.00
Rp 17,272,800.00 /M³

Rp 400,000.00

Rp 225,000.00
Rp 24,000.00
Rp 72,000.00
Rp 4,800.00
Rp 725,800.00 /M²

Rp 350,000.00

Rp 180,000.00
Rp 19,200.00
Rp 57,600.00
Rp 3,840.00
Rp 610,640.00 /M²

Rp 2,500,000.00
Rp 150,000.00
Rp 2,650,000.00 /Bh
Rp 93,750.00
Rp 11,280.00
Rp 9,450.00
Rp 15,000.00

Rp 29,400.00
Rp 3,150.00
Rp 44,640.00
Rp 2,880.00
Rp 209,550.00 /M²

Rp 62,500.00
Rp 11,280.00
Rp 9,450.00
Rp 15,000.00

Rp 29,400.00
Rp 3,150.00
Rp 44,640.00
Rp 2,880.00
Rp 178,300.00 /M²

Rp 9,000.00
Rp 9,000.00 /Kg

Rp 600,000.00

Rp 13,500.00
Rp 1,440.00
Rp 1,080.00
Rp 57.60
Rp 616,077.60 /Bj

Rp 800,000.00

Rp 54,000.00
Rp 5,760.00
Rp 4,320.00
Rp 288.00
Rp 864,368.00 /Bh

Rp 500,000.00

Rp 18,000.00
Rp 1,920.00
Rp 1,440.00
Rp 96.00
Rp 521,456.00 /Bh

Rp 30,000.00

Rp 9,000.00
Rp 960.00
Rp 39,960.00 /Bh

Rp 98,560.00

Rp 13,500.00
Rp 1,440.00
Rp 1,080.00
Rp 57.60
Rp 114,637.60 /M²
RINCIAN RENCANA ANGGARAN BIAYA
NO NAMA JENIS PEKERJAAN An VOLUME SATUAN HARGA SATUAN
I PEKERJAAN PERSIAPAN
1. MEMBERSIHKAN & MERATAKAN TANAH An1 256 M² Rp 12,000.00
2. PAGAR PENGAMAN SENG AnLn 110 M¹ Rp 163,500.00
3. PASANG BOWPLANK An2 64 M¹ Rp 62,140.00
II PEKERJAAN TANAH
1. GALIAN TANAH An3 195.72 M³ Rp 32,640.00
2. URUG KEMBALI GALIAN TANAH An9 73.972 M³ Rp 15,648.00
3. URUG TANAH BAWAH LANTAI AnLn 196 M³ Rp 148,572.00
4. URUG PASIR An10 55.65 M³ Rp 202,560.00
5. URUG SIRTU An11 6.338 M³ Rp 212,400.00
III PEKERJAAN PONDASI
1. PEKERJAAN PASANGAN PONDASI BATU An12 96.05 M³ Rp 586,576.50
KALI 1PC : 3KP : 10PS
2. PEKERJAAN PASANGAN BATU KOSONG An15 26.68 M³ Rp 405,174.00
3. PEKERJAAN BETON FOOTPLAT An115i 22.42 M³ Rp 4,102,399.29
IV PEKERJAAN BETON BERTULANG
1. BALOK 15/25 (SLOOF DAN BALOK MENARA) An113i 272 M¹ Rp 183,300.25
2. KOLOM dia 50 CM An112i 212 M¹ Rp 1,363,521.10
3. KOLOM 40/40 An112i 193.8 M¹ Rp 870,084.66
4. RINGBALK 15/20 An113i 35.67 M¹ Rp 114,339.00
5. BALOK LANTAI 30/60 An113i 16 M¹ Rp 895,866.00
6. BALOK LANTAI 25/45 An113i 140 M¹ Rp 516,051.26
7. BETON TANGGA An111 0.14 M³ Rp 5,950,142.00
8. PLAT LANTAI T=12CM An105i 34.66 M³ Rp 6,478,040.32
9. BETON MULDING An105i 4.998 M³ Rp 6,478,040.32
10. BETON MENARA & KUBAH An105i 29.87 M³ Rp 6,478,040.32
V PEKERJAAN DINDING PASANGAN
1. PEKERJAAN TRASRAAM 1PC : 3 PS An18 210.98 M² Rp 75,150.00
2. PEKERJAAN DINDING BATA MERAH 1PC : An23 71.00 M² Rp 101,422.50
3KP : 10PS
VI PEKERJAAN PLESTERAN
1. PEKERJAAN PLESTERAN , TEBAL 15 MM An28 542.1 M² Rp 42,211.00
1PC : 4PS
2. PEKERJAAN LIST SUDUT PLESTERAN An37 500.98 M¹ Rp 11,858.00
1PC : 2PS
VII PEKERJAAN CAT & POLITUR
1. PEKERJAAN CAT INTERIOR EKSTERIOR An94 1105.46 M² Rp 25,622.00
2. PEKERJAAN CAT PLAFOND & PLAT LANTAI An94 352.2 M² Rp 25,622.00
3. PEKERJAAN POLITUR KUSEN An93 107.46 M² Rp 39,480.00
VIII PEKERJAAN KUSEN & DAUN PINTU JENDELA
1. PEKERJAAN KUSEN PINTU & JENDELA KAYU An40 2.72 M³ Rp 17,272,800.00
BENGKIRAI
2. PEKERJAAN PASANG PINTU PANEL KAYU AnLn 39.46 M² Rp 725,800.00
BENGKIRAI
3. PEKERJAAN PASANG PINTU & JENDELA AnLn 41.33 M² Rp 610,640.00
KACA KAYU BENGKIRAI
IX PEKERJAAN INSTALASI LISTRIK
1. PENYAMBUNGAN PLN AnLn 1 Bh Rp 2,500,000.00
2. TITIK LAMPU + STOP KONTAK AnLn 38 Bh Rp 150,000.00
X PEKERJAAN KERAMIK
1. PEKERJAAN LANTAI KERAMIK 50x50 An89i 322.07 M² Rp 209,550.00
2. PEKERJAAN LANTAI KERAMIK 40x40 AnLn 45.6 M² Rp 178,300.00
XI PEKERJAAN ALAT GANTUNG & KACA
PEKERJAAN ALAT GANTUNG PINTU KUSEN
1. PASANG ANGKUR AnLn 60 Kg Rp 9,000.00
PEKERJAAN ALAT GANTUNG PINTU
1. PEKERJAAN ENGSEL PINTU An82 27 Bh Rp 616,077.60
2. PEKERJAAN PASANG KUNCI TANAM ANTIK An79 3 Bh Rp 864,368.00
3. PEKERJAAN PASANG SELOT An85 6 Bh Rp 521,456.00
4. PEKERJAAN PASANG GRENDEL PINTU AnLn 18 Bh Rp 39,960.00
PEKERJAAN PASANG KACA
1. PEKERJAAN PASANG KACA 5 MM An86 41.33 M² Rp 114,637.60
XII JASA PERENC, PENGWS, DAN PENGELOLAAN
1. JASA PERENCANAAN AnLn 1 ˉ Rp 6,787,000.00
2. JASA PENGAWASAN AnLn 1 ˉ Rp 4,525,000.00
3. JASA PENGELOLAAN AnLn 1 ˉ Rp 2,262,000.00
AN BIAYA
HARGA PEKERJAAN KETERANGAN
Rp 25,033,960.00
Rp 3,072,000.00
Rp 17,985,000.00
Rp 3,976,960.00
Rp 49,284,581.86
Rp 6,388,300.80
Rp 1,157,513.86
Rp 29,120,112.00
Rp 11,272,464.00
Rp 1,346,191.20
Rp 159,126,507.23
Rp 56,340,672.83

Rp 10,810,042.32
Rp 91,975,792.08
Rp 1,049,444,260.09

Rp 49,857,668.00
Rp 289,066,473.20
Rp 168,622,407.11
Rp 4,078,472.13
Rp 14,333,856.00
Rp 72,247,176.40
Rp 833,019.88
Rp 224,528,877.49
Rp 32,377,245.52
Rp 193,499,064.36
Rp 23,056,144.50
Rp 15,855,147.00
Rp 7,200,997.50

Rp 28,823,203.94
Rp 22,882,583.10

Rp 5,940,620.84

Rp 41,590,685.32
Rp 28,324,096.12
Rp 9,024,068.40
Rp 4,242,520.80
Rp 100,859,835.20
Rp 46,982,016.00

Rp 28,640,068.00
Rp 25,237,751.20

Rp 8,200,000.00
Rp 2,500,000.00
Rp 5,700,000.00
Rp 75,620,248.50
Rp 67,489,768.50
Rp 8,130,480.00
Rp 28,353,187.21

Rp 540,000.00

Rp 16,634,095.20
Rp 2,593,104.00
Rp 3,128,736.00
Rp 719,280.00

Rp 4,737,972.01
Rp 13,574,000.00
Rp 6,787,000.00
Rp 4,525,000.00
Rp 2,262,000.00
REKAPITULASI ANGGARAN BIAYA
NAMA PROYEK : PENGADAAN MASJID "AL-ITTIHAD"
LOKASI : BABADAN, KADIPOLO, SENDANGTIRTO, BERBAH, SLEMAN, YOGYAKARTA
TAHUN : 2018

NO JENIS PEKERJAAN BOBOT (100%)


I PEKERJAAN PERSIAPAN 1.562%
II PEKERJAAN TANAH DAN GALIAN 3.075%
III PEKERJAAN PASANGAN PONDASI 9.927%
IV PEKERJAAN BETON BERTULANG 65.469%
V PEKERJAAN DINDING PASANGAN 1.438%
VI PEKERJAAN PLESTERAN 1.798%
VII PEKERJAAN CAT DAN POLITUR 2.595%
VIII PEKERJAAN KUSEN & DAUN PINTU JENDELA 6.292%
IX PEKERJAAN INSTALASI LISTRIK 0.512%
X PEKERJAAN KERAMIK LANTAI 4.718%
XI PEKERJAAN ALAT GANTUNG & KACA 1.769%
XII JASA PERENCANAAN DAN PENGAWASAN 0.847%
TOTAL 100.000%

TERBILANG =

1,602,966,614
HARGA PER 1 M² =
350

Bouwher

Drs. Supono
19631221 199003 1007
GARAN BIAYA

RBAH, SLEMAN, YOGYAKARTA

HARGA SATUAN
Rp 25,033,960.00
Rp 49,284,581.86
Rp 159,126,507.23
Rp 1,049,444,260.09
Rp 23,056,144.50
Rp 28,823,203.94
Rp 41,590,685.32
Rp 100,859,835.20
Rp 8,200,000.00
Rp 75,620,248.50
Rp 28,353,187.21
Rp 13,574,000.00
Rp 1,602,966,614

SATU MILYARD ENAM RATUS DUA JUTA


SEMBILAN RATUS ENAM PULUH TUJUH
RIBU RUPIAH

= Rp. 4,579,905

Sleman, 18 Mei 2018


Perencana / Drafter

Seto Ditosurya Aranta


NIS. 15927