CHEVES HYDROPOWER PROJECT HL z622
ceNRROTEC PROCEDURE OF ACCUMULATOR TEST — | Ro.cor} 1/7
SN Power
PROCEDURE OF ACCUMULATOR TEST
CHEVES PROJECT
NORCONSULT DOCUMENT REVIEW
Cheves Project
REV-CO1
LIMA, SEPTEMBER 30TH, 2015
Car ISSUEDTOR REVIEW SEP2015 TCUARESMA | __R-CROSS
REVISION DESCRIPTION DATE MADE BY | APPROVED BYCHEVES HYDROPOWER PROJECT T2022
PROCEDURE OF ACCUMULATOR TEST | Recor | 3/7
CEMPROTEC
INDEX
L OBJECTIVE. 4
2. SCOPE... 4
3. PERSONAL PROTECTIVE EQUIPMENT AND SAFETY MESURES.. 4
4. ACTIONS TO REDUCE RISKS.... ¥
& DESCRIPTION OF INSPECTIONS AND TESTS. 6
Obpersactones :
- Falh verificer [a carga de fos acumvfrclores anfes ole cualyvier
accion (blo)
- CHET iene gue confiimae anbs de is pruebas:
8 tarimelos de funcionamisnto del acumulader.
° Bist e inknuplor de bgja_y elt presieh (olera a
Cali bjacion ),
+ Valoes de calibacion del acumulador presion minima y maxim
prenen ce Henado. ¢ Cuantas ber?
~ Todas fas unidedes tidhaulicas Yendlay un med de purcionamiento
normal y ef modo extemo. Cf Sish debe ser probedo en auibos
modes de acueido a hus wpecificociones goncialss,
o “oe ta veilvala 3 on th proton maxinta del sista
OP he ela praica maxima de helgc), para ito data la Uatdadl
bidtaulica , atte coakguiei fedlla aul pesosteto de alta presioa de traajo .
-Talle onlregot documento de calibracion de la Unidad Hidtaulica oon
° Sus ciones cleehicas, ecinica alle preston excero de dcvite-
nivel weiximo , nivel minimo, feyperduia de aceite pluberia ola, ete
~Falla erheaat frlesofia ol ppp avlouiticn de piss zack,
pare el funtionamienle de la ‘bohba jockey y bowha de accionamien to
Cn cos de [es \wlake son iguales .
- decuenci, dt (nctonantenlo de las bombas cvaido oe muever clos
Comainadl A =
,EM) CHEVES HYDROPOWER PROJECT neHt2-022
Soupeavec PROCEDURE OF ACCUMULATOR TEST — | Revcor] 4/7
1.
PROCEDURE OF ACCUMULATOR TEST
OBJECTIVE
This procedure aims to describe the proveture of accumulator test which is installed in the
hydraulic pressure units:
2
SCOPE
‘This test procedure applies for accumulator, bladder type, installed on each hydraulic
pressure unit
3.
PERSONAL PROTECTIVE EQUIPMENT AND SAFETY MESURES
> The hydraulic personnel will work with pressurized system, so the oil leak needs to be
verified or checked by disabling the electric motor or the originating source of
pressurizing the hydraulic system. It must have the following considerations:
‘The work area must be cleanned, unmarked and should restrict access to anyone other
than the test personnel
Electrical and htydraulic responsible must keep constant communication via radio,
‘The porsonnel must have safety equipment such as safety shoes, helmet, goggles, ear
protection, Tyvek suit and gloves Hyeron,
ys
‘The electrical personnel should apply the five golden rules on electrical safety before
proceeding to work:
“Disconnect the board.
+ Prevent any possible feedback
Verify the absence of voltage.
% Verify any possible energy source.
+ Mark out the test area
‘The personnel responsible for the test must have the appropriate personal protective
equipment: Dielectric shoes, helmet, dielectric gloves, goggles and ear protection, See
picture N°L