Upgrading of FFS at KOTC GFB-S Classic Schedule Layout Apr-12-19 17:50

Activity ID Activity Name Original Month


Duration
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Upgrading of FFS at KOTC GFB-S J...

STAGE 1 Design Developement M...

A1000 Date of Signing Contract 1m D...


A1010 Issue of Commencement notice 2m I...
A1020 Commencement & Mobilization 1m C...
A1030 Modify Concept Design 2m M...
A1050 Prepare Final design documents for new FF 4m P...
A1060 Prepare & Submit SOW & Technical Spec 2m P...
A1070 Document Submission to KFSD 2m D...
A1080 Tender Floating & Bid Receiving 12m T...
A1110 Review Bidder's Submission and recommen 1m R...

STAGE 2 Construction Supervision J...


A1090 Contractor Mobilization 1m C...
A1100 Project Execution 12m P...

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation