gulf of mexico

Project 20K aims to unlock Russell McCulley

HP/HT deepwater reserves


Senior Technical Editor

Key vendors, researchers recruited to reach 20,000-psi target

O
ver the past several years, superma-
jor BP has built up reserves by
acquiring acreage in some of the
world’s most challenging deepwater
basins, including the Gulf of Mexi-
co’s ultra-deepwater Paleogene, Egypt’s
West Nile Delta, and offshore Azerbaijan,
where reservoir pressures and tempera-
tures exceed the industry’s current tech-
nology capacity. It stands to reason, then,
that BP has taken a leading position in the
effort to develop that technology.
BP is concentrating its 20K initiative in four areas: well design, drilling and completions; rig, riser, and
Early last year, the company announced BOP equipment; subsea production system; and intervention and containment. (Image courtesy BP)
Project 20K, a multi-pronged research and de-
velopment program to “develop, by the end of
the decade, the technologies to be able to drill, new rigs are expected to include advanced Industry evolution
complete, produce, and intervene in deepwa- operating systems, real-time BOP monitor- High-pressure/high-temperature (HP/HT)
ter reservoirs that have (pressures of) 20,000 ing, and “significantly enhanced mechanical technology has evolved incrementally, with
psi at the mudline,” as BP’s Project 20K leader capabilities of the BOP, rig structures, and higher capacity achieved first in onshore ap-
in Houston, Kevin Kennelly, puts it. “Today’s piping systems,” BP said at the time of the plications, Kennelly explains.
limit is at 15,000 psi. So this is an evolution up announcement. Engineers are using de- “The way the industry has evolved, it
to the next spec break in equipment.” sign criteria geared to the US Gulf of Mex- started at 5,000-psi equipment onshore, and
The Project 20K R&D effort encompasses ico, where BP is appraising the Paleogene then it went to 10,000 psi onshore. We took
four main areas of focus: well design and Kaskida and Tiber prospects. the 5,000-psi equipment and marinized it
completions; rigs, risers, and BOPs; subsea “We are looking at a deepwater unit with for offshore. When they went to 15,000 psi
production systems; and well intervention a high hook load capacity and high variable onshore, we took the 10,000-psi equipment
and containment. In addition to the 20,000- deck load capacity,” says Maersk chief tech- and marinized it, so it could be used in deep-
psi target, the equipment will need to with- nology officer Frederik Smidth. Although water. Today, there’s 20,000-psi equipment
stand reservoir temperatures as high as the team has yet to make a formal recom- onshore, but there’s no 20,000 psi capability
350°F (175°C). About 70 BP engineers are mendation, engineers are leaning toward a offshore. It’s limited to 15,000. That’s why
assigned to the program, most of them in drillship concept. “Originally, we were open we say it’s an evolution.”
Houston, where the project team is based. to both a semi and a ship,” he says. “But as Raising the bar to 20,000 psi offshore will
In November 2012, BP awarded its initial it looks right now, due to the functional re- follow a similar pattern of marinization “in
Project 20K contracts to KBR and FMC Tech- quirements, it looks like we will end up with overall terms,” he says. “You have the design,
nologies. The former was tasked with devel- a ship-shaped hull. the build, the qualification testing, and then
oping program execution and management “Ultimately, the intention for both parties, you put it into service. Those fundamental
plans for the project, including cost (which I hope, is to continue the work, and that it steps are the same. But we’re going to do
Kennelly will only say is “in the range of bil- will end up in contracts for a number of rigs some things different in 20K. We’re going
lions of dollars”) and schedule estimates, with good, long drilling contracts.” to do a lot more qualification testing on the
risk assessment, and technical designs. FMC Kennelly agrees: “The idea is, we design engineered systems, not just components or
was enlisted to work with BP to design and one and build several. And they can be used individual pieces of equipment. The reason
develop the subsea production equipment, in- anywhere around the world. The big driver for that is we want to be absolutely sure that
cluding a 20,000-psi subsea tree and a high in- here is reservoir pressure, not water depth. the equipment is safe, that it’s reliable, and
tegrity pressure protection system (HIPPS). We’re not breaking new ground with water that it operates to its intended function. So
Last February, the company announced depth; we’re designing this equipment for there’s quite a bit more qualification testing
that it had selected Maersk Drilling to be 10,000-ft water depth. This project is de- that we’re going to do on this project.”
its collaborator on the program’s rig, risers, signed for deepwater applications, but we’re In August, 2012, BP pledged $100 mil-
and BOP design segment. Maersk’s team, targeting a range.” lion to establish the BP International Centre
in both Houston and Copenhagen, has been Hook load capacity on the new vessels, he for Advanced Materials, an academic pro-
performing engineering studies to select the says, could reach 3 million pounds, well above gram devoted to the research and develop-
rig and equipment design for the task. The the current capacity of 2.5 million pounds. ment of new materials for offshore applica-
gulf of mexico

tions, including HP/HT. The University of


Manchester’s Faculty of Engineering and
Physical Sciences serves as a hub for the
program, which also funds researchers at
the University of Cambridge, Imperial Col-
lege London, and the University of Illinois at
Urbana-Champaign. The 10-year investment
program will sponsor research into advanced
materials and is expected to support 25 new
academic posts, along with 100 post-graduate
researchers and 80 post-doctoral fellows. The
program will examine the adaptation of mate-
rials developed for other industries, including
aerospace, for the offshore energy realm.
“Our work has shown us that we need to
go beyond just making things bigger and
The drilling simulator at Maersk Training, in Svendborg, Denmark, will be used to train crews work-
heavier,” Kennelly says. “We’re looking at
ing on 20K-capable drilling rigs. (Image courtesy Maersk)
new, lightweight, high-strength materials that
can withstand these higher pressures and
temperatures up to 350°F. And we’re looking to be able to drill them efficiently, meaning company recently installed a drilling simula-
at ways to incorporate inherently safer sealing that we need high hook load capacity. What tor that can support 20,000-psi instruction. The
components and designs.” number we are going to end up with we do complex includes a rig control room simulator,
Testing will be conducted at pressures and not know yet. But it’s a high number.” engine room simulator, and crane simulators
temperatures higher than those found in the Working closely with BP has given Maersk for integrated crew training.
reservoirs, he adds: “There are testing ven- an opportunity to identify potential inefficien- Kennelly says much of the 20K tool kit will
ues out there capable of doing that, but we cies, information that the company plans to draw on proven “but enhanced” technologies.
think there will be some upgrading involved.” use to help improve margins with the new “KBR is working with BP and other contrac-
Project 20K research includes methods rigs, Smidth says. tors to develop the functional specifications for
to minimize human error in drilling and pro- “The intention is to come up with a rig that all equipment,” he said. “Once we do that, we
duction operations by improving what Ken- can safely drill in 20,000-psi conditions. But work with the vendors to help develop equip-
nelly calls the “man-machine interface.” One beyond that, we also expect to learn what ment that complies with those specs.”
example is the use of shape rather than col- brings value to our client, the oil company.” A There could be a substantial payoff should
or alone to distinguish buttons or switches. significant reduction in non-productive time BP be the first to break deepwater HP/HT
Color blindness, he notes, is fairly common – for example, employing new material tech- barriers. BP’s offshore acreage alone could
in men, making color-coded buttons harder nology that would enable less frequent seal hold 10-20 Bbbl in HP/HT reservoirs, accord-
to identify in an emergency. Advanced sys- replacements – could help offset the inevita- ing to the company’s estimates. But Kennelly
tems will also rely more on computers to as- bly higher day rates of the next-generation insists that “we’re not out to establish a com-
sist in decision-making. drilling rigs, he says. petitive advantage. We’re out to develop indus-
“That’s one of the things we’re looking at “I think it goes without saying that these try solutions.
a lot, the man-machine interface,” Kennelly units are going to be more expensive than “In our case, we’re at the very forefront
says: “How, when we can, do we take the man traditional 15,000-psi rigs,” Smidth said. “Our of deepwater discoveries that require 20,000
out of the decision-making process? And if we goal, together with BP, is to design a rig so that psi, compared to some of our competitors.
can’t, how do we get the right information to we can construct a 20,000-psi well at more or But from a materiality scope and scale, there
the person early enough, so that we know he less the cost of a 15,000-psi well. Obviously, wouldn’t be enough business for the ven-
will make the right decision?” you will need a higher day rate for a more dors to be interested in equipment only for
expensive unit. But if we can do it faster and BP. Again, we want to develop solutions that
Capacity and cost smarter, then we will reduce non-productive the industry can use, and we have a need for
Project 20K rig design has been largely time. There’s a lot of knowledge there that that sooner rather than later.
driven by the load capacity necessary to should be harvested, and shared.” “Our commitment is to develop this new
conduct drilling operations under the more With Project 20K, he added, “we now technology, and what’s absolutely paramount
rigorous reservoir conditions, says Smidth. have access, with BP, to look at that non- to us is that it’s safe, reliable, and operates to
“A semi could certainly do the job, and in productive time to see if there’s anything we its intended design. That’s where our com-
some aspects might even be an advantage,” he can do from a rig perspective to minimize mitment is for the whole team. What’s unique
says. “But the issue is that a semi capable of car- that, or reduce the risk of that kind of non- here, I think, is that this is a joint project be-
rying the load that we’re talking about would be productive time from occurring.” tween our global projects organization and our
a huge semi. From a cost perspective, we are global wells organization.
almost certain that a ship is a better solution. Industry solutions “And we’ve brought some of our key ven-
“The well design is the basis, obviously,” When the various pieces of Project 20K come dors in very, very early. We spent a lot of time
he continues, “and we look at what casing together and the new rigs set to work, perhaps looking at the contractors we wanted to work
will need to be run, what extra services we as early as 2018, reaching the safety targets with. We wanted to make sure they had the
need to provide, and so on. So it’s not only that BP has set forth will ultimately come down same aligned vision as us, the same ideas on
the pressure-bearing equipment. That is to properly trained personnel. Much of that safety, reliability, on performance, and ap-
pretty straightforward. But these wells re- training will be done at the Maersk Training proach to design. And I’m very proud of who
quire very long and heavy casing strings complex in Svendborg, Denmark, where the we’re working with.” •