WEST QURNA I~ SECTION-L
IR— INSPECTION REQUEST
Contractor No.: AWQ0109
ExonMobil Project Title: eae Sct
Produced Water Treatment M109
LOCATION: DS-8 | IRNO:IRNOCE-CO060 | IRISSUE DATE: 20 February 2017 DISCIPLINE: Civil
SUBJECT: Witness INSPECTION REQUIRED DATE:21 February 2017 | TINMIE:13:00
REF-SPECIFICATION: | QWQ-FT-NSPDS-00-040901 REV.1 EARTHWORK 7
‘ TQWO-CE1091-CDFND-D8-0002_2 FOUNDATION FOR PRE SEPARATOR [GDS
Be eerie: ‘ABJ681050 PLAN SECTION & DETAIL it
REF. ITP: QWQ-CE1092-CPQAC-00-00DIREV. 0 CIVILINSPECTION AND TEST PLAN
OTHERS REF.
[ATTACHMENT /CHECK UST IF ANY:
NAME OF CONTRACTOR/SUBCONTRACTOR: crecc/mFco
‘Our request the inspection of the following works for certficate/witness that all tems has been properly executed in
accordance with approved procedures, specifications, drawings and all items has been coordinated with future works.
DISCRIPTION OF WORK TO BE WITNESS:
Witness to take samples for the second layer ( 2 points ) for the purpose of compaction degree test in
ps8
‘COMMENTS:
fnccePTED Claccerre with comments CiresecreD
OWworkis not ready
Glunacceptable inspection result
Osee comments
CI TICK THIS BOX IF “NO” EMIL / SOC and fits a “WITNESS” as per ITP,
(boy ticking this box means CPECC needs to produce all the related documents and sign / close this If)
SIGNATURE FOR NOTIFICATION/ ACKNOWLEGEMENT
SUBCONTRACTOR cpecc COMPANY OTHERS
PRINT NAME: PRINT NAME: PRINT NAME PRINT NAME
manned Alasq Ma Sng posses shut
SIGNATUR 2 SIGNATURE: wae SIGNATURE:
onte:a1-F4 2017 [ome 30/7-2-2) [ome OEP UZ | omeExxonMobil
West Qurna |
Contract:AWQ0109
Project Location: Basra, Iraq
Lise
Form No. F70101Q
Rev. 0
Serial No.
QUALITY CHECKSHEET - SOIL INSPECTION CHECKLIST
Remarks:
Tag Description | PRODUCED WATER TREATMENT | Tag No pss |
Contract No. ‘AWQ0109 System No
Contractor CPECC 7 Sub-System No. | IQDS8-ABJ681050
Drawing Reference | QWOCEIOI-CDFND Loeation sé
DrawingNoz — IQWQ-CE1091-CDFND-D8-0002
Specification No: IQWQ-FT-NSPDS-00-040901 REV.1 EARTHWORK , $-CE0109-EMIL-0005,
Inspection Reference Contractor | West aural
1. Excavation cleared of foreign and lose materia oy eH Oe
2. Slopes shored or correctly stepped, oe) VIE
c On
3, Fill Material cleans and conforms to requirements oe] oy
— oh a,
4, Lift thickness and compaction procedures in accordance with specifications. Ae
9. Final elevation in accordance to drawings. 0% aT, Wf UE
6. Moisture control acceptable. vk hye yz WE
7. Compaction Method and Equipment. lly i. fF
Contractor/Construetion Rep.
Contractor/Quality Rep.
Company Rep.
Ne aharameed Alsat
Signature
bac yf 2- 30']
*PI/1*