SPOOLS PAINTING- STATUS AT OOSC WORKSHOP AS ON 15/4/2019
No. Number of Spools Status Remarks
52 Large Spools Two loads collected yesterday and third load being 1 (3 trailer loads) Completed, Inspected and passed on 11 April collected today.
Status of balance 250 spools at OOSC Workshop.
2 70 spools Completed and scheduled for inspection at 4 PM Today. 70 spools can be collected tomorrow.
Work in progress. In mid coat/ topcoat stage. Will be
3 150 spools 150 spools can be collected on 17/4 and 18/4 in 3-4 lots completed and offered for inspection on 17/4 morning. Paint system Specs provided yesterday noon. Blasted and 4 30 Spools offered for inspection this morning. Inspected and Can be collected on 19/4. cleared. Will be primed today.
Other than the above, we do not have any spools due for painting at OOSC Workshop.