BRIDGE & STRUCTURES
RESEARCH, DESIGN & DEVEPLOPMENT
SOME RECENT ACHIEVEMENTS
New Initiatives in Design and Fabrication
Revision of Railway Codes for Seismic
Design of Railway Bridges
+ The existing Design provisions of Bridge
Rule for Seismic Design of Railway Bridge
% Design of 91.44m span has been standardized. are Obsolete as these were based on
“Bow string gitders for NHAI drawings of 42m 1S:1893-1984 which has been completely
‘span bow string ROBs have been issued for revised with new design philosophy in Year
‘one way twolane. 2002, The Seismic design methods have
+ Design of 60m Bow Arch Bridge for NHAI one ‘also advanced all over the world.
way two lane isin progress. 4 Based upon new IS Codes and prevailing
+ Design of 72m Bow Arch girder has been latest international practices, IITK-RDSO
completed.
On-Going Research Projects
ey i371
Review of Fi
Railway Bridges
4 The Fatigue Criteria for design of Railway
Brides was revised vide correction slip no in
the June, 2012
‘ The Implication of the revised Fatigue
criteria has been a large and somewhat
unjustified increase in the sectional area in
some members. This necessitates a
Review of the Design Criteria for Fatigue.
4 The increase in the section from old to new
fatigue criteria is up to 150% in the
Diagonals etc resulting in large increase in
Steel Weight.
ia for Design of
Guideline were issued in Nov-2010. The
New methodology suggested takes into
account the Flexibility of the structures in
calculating design Seismic Forces and it
also takes into account the Duetilty factor of
the bridge in absorbing and sustaining
Earthquake forces by going into inelastic
range
+ Certain issues were pointed out regarding
these guidelines, especially related
Response reduction factor and Live Load
factors. This matter was discussed in 82nd
BSC jin 2014, The issues have been
‘examined and revised RDSO guidelines for
seismic design of bridges have been issued
in January 2015.
+ The correction slips to Bridge Rules and
‘Most ofthe problems in the Railway bridges (RSW CaRaereNE SeeN once eM Unter
have been found in the Fatigue failures of
preparation
Stringer! Rail Bearers where the increased _
section isjustited % The matter was discussed in 83° BSC
+ The reasons for this change has been es ee atoe ipa rer a
identified as follows
i. Use of complete stress cycle for
members like diagonals.
correction slips are to be proposed by B&S.
dte.
On-Going Important Design Projects
ii. Use of full impact factor for fatigue = Design of 106.6 m Span Open Web Girder
design (In Euro codes, 50% of impact + 106.6 m span open web girder is required
factor is used). forimportant bridges.
ili, Use of rivets which have low fatigue % Design work has been taken up in hand
strength. (This problem has been + Steel proposed is E350 B0, with double-
solved by using HSFG bolts). diamond type truss.
‘Matter was discussed in 83" BSC and as = Design of 30.5 m Span Ballasted Deck
per discussions, the revision will be done by
RDSO and presented during the next BSC
meeting.
Through Type Girders
+ The through girder drawings are all with
steel channel sleepers.
= a
TRDS eS Aeli ele ee oy
*
+
For better riding and for permitting laying of
LWR on bridge, ballasted deckis preferred.
Design of 30.5 m span with RCC deck over
stringers has been taken in hand.
Design of Bow-String Girders for Revised
Lane width ROBs
°
Design of Bow string girders for revised
lane width is required as per IRC
guidelines.
The work is held up because there is no
‘AEN/XEN forthe same.
Design of ROBs for Revised Lane
Configurations
*
°
The lane widths have been revised by
MOST for different locations of ridges.
‘All existing designs need to be checked and
revised forthese.
Design work has been taken up and likely to
be completed by 30.09.2016,
Drawings will then be required to be
prepared for different spans.
Progress of On-Going Research Projects
(External)
Development of Railway Bridge Health
Monitoring System with Wireless Sensor
Network
*
*
BENEFITS EXPECTED
> The use of wireless sensors reduces
the losses associated with the wires
such as thermal effects, drop in
voltage etc,
> Setting up of test is very fast and
convenient
> — Long term monitoring of bridges can
be done.
SALIENT FEATURES
> Category ofproject — Artificial
Inteligence
> Sanctionedcost — Rs. 187.02 lakhs.
> ExecutiveAgency - Centerfor
Railway Research
(IIT Kharagpur)
> Exp. Upto Mar, 2016 — Rs. 181.02 lakhs
> Budget Grant — Rs.2.09 lakhs
> Exp. In Current Year — NIL
OBJECTIVES/DELIVERABLES
> Extensive literature survey to find out
state of art system of Wireless Sensors
suitable for Indian Railways.
> Development of energy efficient and
secure topology design to reduce
battery consumption & pilferage.
Developing numerical models for four
Representative Standard Span for
Railway Bridges,
> Analysis of Superstructure & Sub-
structure to find the locations for placing
the sensors
Design of Wireless Sensor Network for
Bridge Health Monitoring,
> Investigation for use of suitable Wireless
Sensors for Flood Water Level
monitoring,
> Testing of Sensors on a model through
simulation.
> Training of25 Railway Engineers.
STATUS
> Literature Survey Completed.
> Sensors and base stations procured for
wireless network
> Water level sensor procured and initial
testing done on Bridge No 57 in SE
Railway.
Instrumentation testing completed on
one bridge in SE Railway to check the
arrangement proposed.
> Numerical models prepared for four
types of girders, viz Plate girder, open
web girder, PSC Box and PSC girders
> Design of 12m Span Model Bridge for
outdoor experiments finalized & same to
be fabricated
> Final Report on Flood Water Monitoring
‘System has been submitted to RDSO on
21-02-2016
> Some sensors and wireless data
collection system is being tested
Testing of sensors also done on Br No.
168 UP. Validation of Numerical Model,
fine tuning of system under progress.
> Draft final Report on ‘Numerical
Modeling of Railway Bridges” has been
submitted by IITIKGP for scrutiny of
RDSO on 30-4-2016.After Scrutiny by
RDSO the shortcomings in report has
been advisedto IITIKGP on 19.05.2016.
> On receipt of Second Draft Final Report
on 14-07-2016, shortcomings again
advised vide RDSO letter dated 19-07-
v
v
vBRIDGE & STRUCTURES:
2016. Final report from lIT/KGP and
validation of whole system on Bridge
168 Upisstill pending,
> Request for expediting the project done
0n21.07,2016.
Prof /Civil Engg. With SRA had meeting
in RDSO on ist & 2nd August/2016 for
detailed discussion and assured to
‘complete the project atthe earliest
> Draft final Report on “Numerical
Modeling of Railway Bridges” has been
submitted by IITIKGP for scrutiny of
RDSO on 30.4.16. After Scrutiny by
RDSO the shortcomings in report has
been advised to IIT/IKGP on 19.05.16,
v
™ Development of Criteria for Dynamic
Analysis of Steel Railway Bridges
°
*
ey i371
BENEFITS EXPECTED
> Optimization and extension of impact
values to be considered in bridge design
for speeds upto which dynamic analysis
is not required (~ 200 KMPH). The
existing codal values are for 125/160
KMPH only,
> Criteria for dynamic analysis of bridges
for higher speeds (Upto 350 KMPH)
where CDAvalues cannotbe used.
SALIENT FEATURES
> Sanctionedcost - Rs. 43,22,640.00
> Yearofsanction - 2012-13, DF-3,
PH-18
> Agency - IITRoorkee
> MOUDate = 09.10.2012
> Expendituretill - Rs40.01 Lakhs.
31.03.2016
> BudgetGrant = Rs 1.12 Lakhs,
15-16
> Expenditurein = Nil
currentyear
OBJECTIVE / DELIVERABLES
» Dynamic Analysis of all types of Girder
and Truss bridges including
Comparisons of Dynamic analysis with
CDA based normal analysis, for
Passenger speeds 160 Kmph to 300
Kmph and Freight 125 Kmph to 150
Kmph for MBG, HM, 25 t and 32.5 t
loading.
> Procedure (step by step) to conduct
Dynamic analysis.
> Draft Provisions for Bridge Rules/ Stee!
Bridge Code along with design
implications.
‘+ CURRENTSTATUS
> Results of Dead Load and Free vibration
analysis completed for all Plate Girder
and Truss Bridges.
> Dynamic analysis for all Plate Girder
Bridges completed (including case with
CDA).
> Dynamic analysis of OWG completed.
> IIT Roorkee has informed that all
analysis work has been completed and
report preparation work is going on.
Development of Provision for Design of
Steel Concrete Composite Railway Bridges
for Normal Speed ad Special Provisions for
High Speed Passenger Traffic
‘+ EXPECTED BENEFITS
> Code for design of steel-concrete
composite girders will be developed,
benchmarking the same with other
international codes.
> Shear connectors will be tested to verity
their strength in static and dynamic
conditions.
Methodology for design of continuous
composite girders for high speed train
operations will be finalized.
> Existing steel bridge code will be
converted to limits state to make itin tine
with the concrete bridge code which is
already inlimitstate
% SALIENTFEATURES
> Sanctionedcost - Rs. 118.95 lakhs
> ExecutiveAgency— Centre for Railway
v
Research (IIT
Kharagpur).
> Exp.UptoMar,2016 — Rs. 78.55 lakhs.
> BudgetGrant — Rs. 3.48 lakhs.
2015-16
> Expenditurein — Nil
current year
OBJECTIVESIDELIVERABLES
> Report on analysis and design of
Composite Bridge girders for normal
speed (up to 160 kmph) in phase-1 and
special provisions for high speed
Passenger Traffic in phase-2 (up to 350
kmph). The report will contain the design
= a
TRDS eS A